Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Thu, 29 May 2008 07:32:27 +0530,    group: microsoft.public.project.vba        back       


Adding Working Time Exception changing Actual Work   
Hi guys,

I'm having a problem when adding Working Time Exception for certain
resources such that MS Project kind of automatically recalculates the
existing Actual Work hours. For example, under the Resource Usage of
the affected resources, 8 hours Actual Work becomes 8.07 hours and some
becomes 0. The total Actual Work hours does not change, it's just the
number of Actual Work hours changes between the working days.

FYI, I'm using MS Project 2007. I believe this is caused by some
settings somewhere. However, I'm confused because this problem only
happens for certain resources only.

Would appreciate any help on this. Thank you.

Cheers,
Ted


-- 
TeddyLim
------------------------------------------------------------------------
TeddyLim's Profile: http://forums.techarena.in/member.php?userid=50524
View this thread: http://forums.techarena.in/showthread.php?t=977162

http://forums.techarena.in
date: Thu, 29 May 2008 07:32:27 +0530   author:   TeddyLim