Hi, 1st Problem: when i need to change in project plan all changes are need to back its initial state because when it displays a message about to synchronize with protected actuals with time sheets and my changes in project plans will lost .. pls tell me how i can change the project plan with protected actuals. 2nd Problem: The user is entering hours in their timesheets but when i out the report through project professional the values or users are in decimal. its a big hurdle for me pls tell me the solution how i can resolve it regards Micheal