|
|
|
date: Sun, 12 Oct 2008 17:50:00 -0700,
group: microsoft.public.project.server
back
Re: Inactive Resources
On Oct 13, 2:50 am, David F-H
wrote:
> We are using Project Server 2007 SP1, and have come across the following
> scenario :
> 1. Set up a resource that will also have logon ability to Project Server
> 2. Resource changes to a different business unit, and logon access is
> removed by marking the resource as inactive.
> 3. We still wish to assign this resource to some tasks within plans (even
> though they do not have logon ability)
> 4. The resource no longer displays as an available resource in Project
> Server, and error messages appear when opening plans for which that inactive
> resource has remaining work.
>
> Is there a better way to remove a user's login in these cases (we want to
> limit the number of licences due to budget), whilst still retaining the
> ability to assign the resource to tasks - basically would like to clear the
> "Resource can logon to Project Server" checkbox, but this is greyed out once
> it has been set ???
Hi David,
Project server's licencing works on each and every user that has the
log on permission. So i could suggest creating a diff group , with its
own security template
Category etc. Add these users to that group and apply the security
template to the group. They will be able to be assigned to tasks but
cannot log onto the server, all reporting would still be able
done on these resources.
Regards
Andre
date: Sun, 12 Oct 2008 23:55:29 -0700 (PDT)
author: ProjmanZA
Re: Inactive Resources
Thanks Andre,
That's probably the way to go - I didn't really notice the security setting
to Deny the logon, so I'll just set that. Still, it seems a bit of a strange
implementation in that there is a separate "Resource can logon to Project
Server" checkbox that is unable to be cleared once it is set on.
"ProjmanZA" wrote:
> On Oct 13, 2:50 am, David F-H
> wrote:
> > We are using Project Server 2007 SP1, and have come across the following
> > scenario :
> > 1. Set up a resource that will also have logon ability to Project Server
> > 2. Resource changes to a different business unit, and logon access is
> > removed by marking the resource as inactive.
> > 3. We still wish to assign this resource to some tasks within plans (even
> > though they do not have logon ability)
> > 4. The resource no longer displays as an available resource in Project
> > Server, and error messages appear when opening plans for which that inactive
> > resource has remaining work.
> >
> > Is there a better way to remove a user's login in these cases (we want to
> > limit the number of licences due to budget), whilst still retaining the
> > ability to assign the resource to tasks - basically would like to clear the
> > "Resource can logon to Project Server" checkbox, but this is greyed out once
> > it has been set ???
>
> Hi David,
>
> Project server's licencing works on each and every user that has the
> log on permission. So i could suggest creating a diff group , with its
> own security template
> Category etc. Add these users to that group and apply the security
> template to the group. They will be able to be assigned to tasks but
> cannot log onto the server, all reporting would still be able
> done on these resources.
>
> Regards
> Andre
>
date: Mon, 13 Oct 2008 21:23:01 -0700
author: David F-H
|
|