Hi, In what is the difference between Proposals and Activities in ProjectwebAccess2007?
SD -- In the future, please post your Project Server 2007 questions in the microsoft.public.project.server, as this newsgroup is closing down. To answer your question: 1. Proposals are used by organizations that have a formal approval process to initiate new enterprise projects. The PM creates a new Proposal, consisting of high-level tasks only, and saves it. Someone from the Proposal Reviewers group must then formally approve it, at which time the PM can convert the Proposal to an enterprise project. 2. Activity plans are using for planning on-going work for tasks that do not have a Finish date. For example, you could use an Activity plan for a DBA team to track their work on DBA support tasks. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "SD" wrote in message news:EE832D24-2C73-431E-A7F0-28006E444E0B@microsoft.com... > Hi, > In what is the difference between Proposals and Activities in > ProjectwebAccess2007?