Hi, I have in the enterprise global a base calendar named "Estandar" (8am ..12pm and 1pm to 5pm), and also my resources use this calendar. The problem is that I have some projects that were imported to the project server with a differente calendar named "standard" (9am..1pm and 2pm to 6pm). There are resourses (Estandar calendar) asigned to the projects with "Standard" calendar. The problem is that if I have linked tasks (Finish to Start), the duration is 1 day, but the Star is 9/dec/07 and Finish is 10/dec/07. When I see the view of Task usage I found that tue work is 1hr 9/dec/07 and 7hr 10/dec/07 because the predecesor task has less than 8hrs of work. For my company we work with complete days of 8 hrs, we do not use decimal days (ex. 1.3day) What can I do? Also I trying to change calendars but it does not work. And sometimes when I try to add a resource from the resource pool, project show me a message that said something that I need to synchronize the project pro calendar with the project server calendar. (How can I do for do this when this process is not automátic?) Thank you for your answers!! You can write me to: rasaglez@hotmail.com -- Rafael S
Hi Rasaglez, Try posting on the server newsgroup as this one is closing down. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address:http://project.mvps.org/faqs.htm . Mike Glen Project MVP "Rasaglez" wrote in message news:628CF1BE-499B-48FC-9C1A-D1D7E7329BB7@microsoft.com... > Hi, > I have in the enterprise global a base calendar named "Estandar" (8am > ..12pm > and 1pm to 5pm), and also my resources use this calendar. > > The problem is that I have some projects that were imported to the project > server with a differente calendar named "standard" (9am..1pm and 2pm to > 6pm). > > There are resourses (Estandar calendar) asigned to the projects with > "Standard" calendar. The problem is that if I have linked tasks (Finish to > Start), the duration is 1 day, but the Star is 9/dec/07 and Finish is > 10/dec/07. When I see the view of Task usage I found that tue work is 1hr > 9/dec/07 and 7hr 10/dec/07 because the predecesor task has less than 8hrs > of > work. > > For my company we work with complete days of 8 hrs, we do not use decimal > days (ex. 1.3day) > > What can I do? > > Also I trying to change calendars but it does not work. And sometimes when > I > try to add a resource from the resource pool, project show me a message > that > said something that I need to synchronize the project pro calendar with > the > project server calendar. (How can I do for do this when this process is > not > automátic?) > > Thank you for your answers!! > > You can write me to: rasaglez@hotmail.com > > > -- > Rafael S