Hi, I fill in my timesheets .. save the same ... go to task update ...import timesheet data ...it updates task % complete .. to some say 30% .. now i open the task update and change the remaining work to 20% more time and recalculate .. the task complete % does not change .. Timesheet .... work: 50 hrs, Actual work 40 hrs ... Taks update ... import worksheet ..%complete: 80%... now if i change remaining work to 20 hrs ... and recalculate .. %complete remains 80%..
The project manager shall accept the update,and re-distribute the project to the project server, then the % will be updated on the server. Please try it. -- wendy.li ------------------------------------------------------------------------ wendy.li's Profile: http://forums.techarena.in/member.php?userid=37639 View this thread: http://forums.techarena.in/showthread.php?t=867760 http://forums.techarena.in