Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Sat, 8 Dec 2007 10:06:00 -0800,    group: microsoft.public.project.pro_and_server        back       


Resource assignments on Project Server 2007 shows wrong results   
Hi

I am facing a strange problems - i plan a project, allocate resources, level 
resources ...publish project on project server ... 

When I check resource assignments i find some of the resource assignments 
showing overallocation on the project server.. although Project Professional 
resource usage view shows them levelled ...
date: Sat, 8 Dec 2007 10:06:00 -0800   author:   Deshwal - Magus India