Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Mon, 05 Nov 2007 07:08:06 -0800,    group: microsoft.public.project.pro_and_server        back       


Assign tasks to team instead of invidual resources?   
We are running Project Server 2003 and Project Professional 2003. If
someone could point me in the right direction towards finding a
solution for the following I would be much obliged. I tried searching
on my own and did not get very far.

We have resources assigned to each task in our plan. However it so
happens that it is not always the resources assigned to the task who
actually perform the task. As a result, come time for time-entry, they
cannot enter time in PWA since they have not been assigned to the
task.

Unfortunately, we in the PMO almost never receive advance notification
of such substitutions. It is always on time-entry day that the
resource comes up to us and says that he cannot enter time.

If I could create teams and assign people to teams, and if I could
assign tasks at team level so that it would show up in PWA for all
that team's resources, then anyone from that team could enter actuals
and we would be able to save some time.

Is this possible at all or am I asking for too much? If this is not
directly possible, would someone with more experience that I be able
to suggest a work-around to achieve similar functionality?

Thanks and cheers
date: Mon, 05 Nov 2007 07:08:06 -0800   author:   unknown

Re: Assign tasks to team instead of invidual resources?   
dossmk --

In the future, please post your Project Server questions in the 
microsoft.public.project.server newsgroup, as this newsgroup is closing 
down.  To answer your question, you cannot assign a team of resources in 
Project Server 2003.  However, if you upgrade to Project Server 2007, you 
can use the new Team resource functionality that is built into the tool and 
works exactly the way you want.  Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


 wrote in message 
news:1194275286.321751.201480@d55g2000hsg.googlegroups.com...
> We are running Project Server 2003 and Project Professional 2003. If
> someone could point me in the right direction towards finding a
> solution for the following I would be much obliged. I tried searching
> on my own and did not get very far.
>
> We have resources assigned to each task in our plan. However it so
> happens that it is not always the resources assigned to the task who
> actually perform the task. As a result, come time for time-entry, they
> cannot enter time in PWA since they have not been assigned to the
> task.
>
> Unfortunately, we in the PMO almost never receive advance notification
> of such substitutions. It is always on time-entry day that the
> resource comes up to us and says that he cannot enter time.
>
> If I could create teams and assign people to teams, and if I could
> assign tasks at team level so that it would show up in PWA for all
> that team's resources, then anyone from that team could enter actuals
> and we would be able to save some time.
>
> Is this possible at all or am I asking for too much? If this is not
> directly possible, would someone with more experience that I be able
> to suggest a work-around to achieve similar functionality?
>
> Thanks and cheers
>
date: Mon, 5 Nov 2007 08:24:51 -0700   author:   Dale Howard [MVP] dale(dot)howard(at)msprojecexperts(dot)com