Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 10 Oct 2007 16:34:29 -0700,    group: microsoft.public.project.pro_and_server        back       


External links between project not updating correctly.   
I have attempted to create a master project from tasks in multiple
subprojects.  I've tried two approaches and both fail but for
different reasons.

The first is to copy task and paste special/paste link into the master
plan.  This approach allows me to create a link where most fields sync
up except for the %work complete field, in the master project.  If I
change the %work complete field to anything other than 100% in the
subproject the field updates correctly, but once I change the %work
complete in the subproject to 100% complete the master project reverts
to 0% complete.

I've gone into the tools/options/calculate tab and verified that the
calculation mode is set to automatic and have clicked the calculate
now button, but no change.

The second approach was to open the task information box in the master
project and enter the subproject name and id into the ID field
[\projectname\taskID].  This approach created two task entries in the
master project and subproject - one with the correct %work complete
and the second task with the correct duration, start and finish
dates.  Deleting either from the master or subproject causes both
tasks to be deleted.

I can't figure out what I'm doing wrong.

Anyone got an idea???

Thanks in advance,
jag
date: Wed, 10 Oct 2007 16:34:29 -0700   author:   jaggy

Re: External links between project not updating correctly.   
Hello Jag,

There are two primary methods of creating master, or consolidated, 
project files.  One is to create the master project file which will be 
the shell for the inserted projects. Then in the master file, choose 
Insert > Project and select the project(s) you wish to insert into the 
master.  The inserted projects are embedded in the master and changes 
made to the inserted project will be reflected in the master file. 
Likewise, changes made to task(s) in the master project, will be 
reflected in the inserted project file.

The other method is to open the multiple subproject files and choose 
Window > New Window to create a consolidated master project.

See Help for further details.

In the future, please post your question to one of the following 
newsgroups:
Microsoft.public.project    -    for general (non-server) questions 
about Microsoft project
Microsoft.public.project.server     - for questions specific to Project 
Server
Microsoft.public.project.developer    -    for questions about using 
programming (VBA, VB, C, etc) in Project and Project server.

Note:  I have set the follow-up for this message to 
Microsoft.public.project

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information 
about Microsoft Project


"jaggy"  wrote in message 
news:1192059269.866968.271540@50g2000hsm.googlegroups.com...
>I have attempted to create a master project from tasks in multiple
> subprojects.  I've tried two approaches and both fail but for
> different reasons.
>
> The first is to copy task and paste special/paste link into the master
> plan.  This approach allows me to create a link where most fields sync
> up except for the %work complete field, in the master project.  If I
> change the %work complete field to anything other than 100% in the
> subproject the field updates correctly, but once I change the %work
> complete in the subproject to 100% complete the master project reverts
> to 0% complete.
>
> I've gone into the tools/options/calculate tab and verified that the
> calculation mode is set to automatic and have clicked the calculate
> now button, but no change.
>
> The second approach was to open the task information box in the master
> project and enter the subproject name and id into the ID field
> [\projectname\taskID].  This approach created two task entries in the
> master project and subproject - one with the correct %work complete
> and the second task with the correct duration, start and finish
> dates.  Deleting either from the master or subproject causes both
> tasks to be deleted.
>
> I can't figure out what I'm doing wrong.
>
> Anyone got an idea???
>
> Thanks in advance,
> jag
>
date: Sun, 14 Oct 2007 09:24:00 -0400   author:   JulieS passport6847 at maine dot rr dot com