|
|
|
date: 8 Mar 2007 23:21:33 -0800,
group: microsoft.public.project.pro_and_server
back
Re: High units on fixed duration tasks
Hi Richard,
Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .
Mike Glen
Project MVP
"rt" wrote in message
news:1173424892.922163.139930@h3g2000cwc.googlegroups.com...
> Good morning all,
>
> Some of my PM's have a problem which is already familiar to this
> audience: high units on fixed duration, non-effort driven tasks after
> entering actuals.
>
> I've read a few threads on this subject and found some very useful
> info (eg. entering 0 hours on the start of a task). Also, I tell my
> PM's to set the task type to fixed units before updating but they
> insist on fixed duration for reasons you have all heard before :-)
>
> However, there's one phenomenon I did not see explained and that is
> finish dates moving forward (not backward).
>
> What I see in some schedules is this: a task has a duration of, say 60
> days. After accepting actuals into the schedule, the remaining work is
> not spread over the remaining duration, but all remaining work is
> concentrated in one week and the task is scheduled to finish early
> (albeit by working a zillion hours a week).
>
> I understand how fixed duration tasks can have their duration extended
> but I do not understand why this happens. Can anybody help me out
> here? I can only tell the PM's "I told you so" for so long - they will
> want to understand what's happening.
>
date: Fri, 9 Mar 2007 22:10:05 -0000
author: Mike Glen glenATmvps.org
|
|