|
|
|
date: Thu, 8 Mar 2007 13:38:04 -0800,
group: microsoft.public.project.pro_and_server
back
Re: Surrogate Timesheet
Jerry --
In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup as this newsgroup is closing down.
To answer your question, you can create a Surrogate Timesheet on behalf of a
resource who is not able to access their PWA timesheet page for one reason
or another. For example, the resource has been out sick all week and the
company requires the resource to submit at timesheet at the end of the week.
Or a resource is working in the field away from the corporate network and
calls in actuals to you each day, but is still required to submit a
timesheet at the end of the week.
As their Timesheet Manager, you could create a resource on behalf of each of
these two resources and then submit it. For the first resource, you could
create the Surrogate Timesheet, enter 40 hours of Sick Leave and then submit
it. For the second resource, you might enter the Actual Work on tasks
performed by the resource that week, and then submit it. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Jerry" wrote in message
news:7EB2A185-A84A-48D7-AAD9-4FB82D75644F@microsoft.com...
> Hi all! What is a Surrogate Timesheet and what is it used for?
>
> Thanks!!
>
> Jerry
date: Thu, 8 Mar 2007 17:12:05 -0700
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com
Re: Surrogate Timesheet
Thanks Dale, it certainly does help. Sorry about the post location, thought
I was in the right one.
Jerry
"Dale Howard [MVP]" wrote:
> Jerry --
>
> In the future, please post your Project Server questions in the
> microsoft.public.project.server newsgroup as this newsgroup is closing down.
> To answer your question, you can create a Surrogate Timesheet on behalf of a
> resource who is not able to access their PWA timesheet page for one reason
> or another. For example, the resource has been out sick all week and the
> company requires the resource to submit at timesheet at the end of the week.
> Or a resource is working in the field away from the corporate network and
> calls in actuals to you each day, but is still required to submit a
> timesheet at the end of the week.
>
> As their Timesheet Manager, you could create a resource on behalf of each of
> these two resources and then submit it. For the first resource, you could
> create the Surrogate Timesheet, enter 40 hours of Sick Leave and then submit
> it. For the second resource, you might enter the Actual Work on tasks
> performed by the resource that week, and then submit it. Hope this helps.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
>
> "Jerry" wrote in message
> news:7EB2A185-A84A-48D7-AAD9-4FB82D75644F@microsoft.com...
> > Hi all! What is a Surrogate Timesheet and what is it used for?
> >
> > Thanks!!
> >
> > Jerry
>
>
>
date: Mon, 12 Mar 2007 05:47:05 -0700
author: Jerry
|
|