Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Tue, 6 Mar 2007 20:41:08 +0530,    group: microsoft.public.project.pro_and_server        back       


Timesheet Dates Problem   
Hello

I did following settings in server setting - timesheet periods.
No of periods to be created - 52
Date the first periods start 1/1/2007
Type the standard period - 7

Now when ever I create bulk, it generates dates like
1/1/2007 - 1/5/2007
1/6/2007 - 1/10/2007
and so on

If you see january 2007 calendar, dates should be
1/1/2007 - 1/5/2007
1/8/2007 - 1/12/2007
and so on

I have alreayd set non working days as Sat-Sub, thne why it is not 
considering in timesheet date generation.

Please let me know whats wrong I am doing?

Ashish
date: Tue, 6 Mar 2007 20:41:08 +0530   author:   Ashish kanoongo