Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Thu, 15 Feb 2007 06:59:59 -0800,    group: microsoft.public.project.pro_and_server        back       


Project Server   
Hi,
We have recently implemented microsoft project server 2003 in our 
oragnisation.
My projects team is facing big issuse in project server, ie whenever a 
resource submit his timesheet (effort) in project web access approved by the 
project manager, this will be updating the actuals in microsoft project plan 
in the server, the problem is the plan effort is also changing to actual 
effort.

For Example the resource A has planned effort of 4 hrs, but the resources 
complete the task within 3 hrs and sent for manager approval. When the 
manager approve the time sheet. The planned effort of 4 hrs is changed to 3 
hrs.

Please hlep me on the above issuse

Thanks in advance

Regards,
Ramesh
date: Thu, 15 Feb 2007 06:59:59 -0800   author:   Ramesh

Re: Project Server   
Ramesh --

In the future, please post your Project Server questions in the 
microsoft.public.project.server newsgroup, as this newsgroup is closing 
down.  To answer your question, you are missing a fundamental principle of 
how Microsoft Project works, which is "actuals always replace estimates." 
If you schedule a task to take 4 hours of Work, and a resource submits 3 
hours of Actual Work and sets Remaining Work to 0 hours (indicating the task 
is complete), the system replaces the 4 hours of planned Work with the 3 
hours of Actual Work and marks the task as 100% complete.  This is the 
default behavior of the software and you cannot change this behavior.

Now, here's what else you don't know.  You preserve the original planned 
Work for each task in your project by saving a project baseline before you 
begin collecting actuals in the project.  To save a baseline, click Tools - 
Tracking - Save Baseline.  You can compare the variance between baseline 
values and current/actual values by displaying any task View, such as the 
Gantt Chart, and then applying either the Work, Cost, and Variance tables. 
For example, to apply the Work table, click View - Table - Work.  Hope this 
helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"



"Ramesh"  wrote in message 
news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
> Hi,
> We have recently implemented microsoft project server 2003 in our
> oragnisation.
> My projects team is facing big issuse in project server, ie whenever a
> resource submit his timesheet (effort) in project web access approved by 
> the
> project manager, this will be updating the actuals in microsoft project 
> plan
> in the server, the problem is the plan effort is also changing to actual
> effort.
>
> For Example the resource A has planned effort of 4 hrs, but the resources
> complete the task within 3 hrs and sent for manager approval. When the
> manager approve the time sheet. The planned effort of 4 hrs is changed to 
> 3
> hrs.
>
> Please hlep me on the above issuse
>
> Thanks in advance
>
> Regards,
> Ramesh
date: Thu, 15 Feb 2007 09:56:39 -0700   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Re: Project Server   
Thanks Dale Howard,

This answer my question 
Henceforth i will post all my questions to microsoft.public.project.server 
newsgroup 

Thank you for quick reply

Regards,
Ramesh


"Dale Howard [MVP]" wrote:

> Ramesh --
> 
> In the future, please post your Project Server questions in the 
> microsoft.public.project.server newsgroup, as this newsgroup is closing 
> down.  To answer your question, you are missing a fundamental principle of 
> how Microsoft Project works, which is "actuals always replace estimates." 
> If you schedule a task to take 4 hours of Work, and a resource submits 3 
> hours of Actual Work and sets Remaining Work to 0 hours (indicating the task 
> is complete), the system replaces the 4 hours of planned Work with the 3 
> hours of Actual Work and marks the task as 100% complete.  This is the 
> default behavior of the software and you cannot change this behavior.
> 
> Now, here's what else you don't know.  You preserve the original planned 
> Work for each task in your project by saving a project baseline before you 
> begin collecting actuals in the project.  To save a baseline, click Tools - 
> Tracking - Save Baseline.  You can compare the variance between baseline 
> values and current/actual values by displaying any task View, such as the 
> Gantt Chart, and then applying either the Work, Cost, and Variance tables. 
> For example, to apply the Work table, click View - Table - Work.  Hope this 
> helps.
> 
> -- 
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
> 
> 
> 
> "Ramesh"  wrote in message 
> news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
> > Hi,
> > We have recently implemented microsoft project server 2003 in our
> > oragnisation.
> > My projects team is facing big issuse in project server, ie whenever a
> > resource submit his timesheet (effort) in project web access approved by 
> > the
> > project manager, this will be updating the actuals in microsoft project 
> > plan
> > in the server, the problem is the plan effort is also changing to actual
> > effort.
> >
> > For Example the resource A has planned effort of 4 hrs, but the resources
> > complete the task within 3 hrs and sent for manager approval. When the
> > manager approve the time sheet. The planned effort of 4 hrs is changed to 
> > 3
> > hrs.
> >
> > Please hlep me on the above issuse
> >
> > Thanks in advance
> >
> > Regards,
> > Ramesh 
> 
> 
>
date: Thu, 15 Feb 2007 21:07:03 -0800   author:   Ramesh

Re: Project Server   
Ramesh --

You are more than welcome, my friend!  :)

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"



"Ramesh"  wrote in message 
news:944B7AC3-0BD5-485A-A474-0E21B5EEA099@microsoft.com...
> Thanks Dale Howard,
>
> This answer my question
> Henceforth i will post all my questions to microsoft.public.project.server
> newsgroup
>
> Thank you for quick reply
>
> Regards,
> Ramesh
>
>
> "Dale Howard [MVP]" wrote:
>
>> Ramesh --
>>
>> In the future, please post your Project Server questions in the
>> microsoft.public.project.server newsgroup, as this newsgroup is closing
>> down.  To answer your question, you are missing a fundamental principle 
>> of
>> how Microsoft Project works, which is "actuals always replace estimates."
>> If you schedule a task to take 4 hours of Work, and a resource submits 3
>> hours of Actual Work and sets Remaining Work to 0 hours (indicating the 
>> task
>> is complete), the system replaces the 4 hours of planned Work with the 3
>> hours of Actual Work and marks the task as 100% complete.  This is the
>> default behavior of the software and you cannot change this behavior.
>>
>> Now, here's what else you don't know.  You preserve the original planned
>> Work for each task in your project by saving a project baseline before 
>> you
>> begin collecting actuals in the project.  To save a baseline, click 
>> Tools -
>> Tracking - Save Baseline.  You can compare the variance between baseline
>> values and current/actual values by displaying any task View, such as the
>> Gantt Chart, and then applying either the Work, Cost, and Variance 
>> tables.
>> For example, to apply the Work table, click View - Table - Work.  Hope 
>> this
>> helps.
>>
>> -- 
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>>
>> "Ramesh"  wrote in message
>> news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
>> > Hi,
>> > We have recently implemented microsoft project server 2003 in our
>> > oragnisation.
>> > My projects team is facing big issuse in project server, ie whenever a
>> > resource submit his timesheet (effort) in project web access approved 
>> > by
>> > the
>> > project manager, this will be updating the actuals in microsoft project
>> > plan
>> > in the server, the problem is the plan effort is also changing to 
>> > actual
>> > effort.
>> >
>> > For Example the resource A has planned effort of 4 hrs, but the 
>> > resources
>> > complete the task within 3 hrs and sent for manager approval. When the
>> > manager approve the time sheet. The planned effort of 4 hrs is changed 
>> > to
>> > 3
>> > hrs.
>> >
>> > Please hlep me on the above issuse
>> >
>> > Thanks in advance
>> >
>> > Regards,
>> > Ramesh
>>
>>
>>
date: Fri, 16 Feb 2007 08:19:42 -0700   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us