|
|
|
date: Thu, 15 Feb 2007 06:59:59 -0800,
group: microsoft.public.project.pro_and_server
back
Re: Project Server
Ramesh --
In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is closing
down. To answer your question, you are missing a fundamental principle of
how Microsoft Project works, which is "actuals always replace estimates."
If you schedule a task to take 4 hours of Work, and a resource submits 3
hours of Actual Work and sets Remaining Work to 0 hours (indicating the task
is complete), the system replaces the 4 hours of planned Work with the 3
hours of Actual Work and marks the task as 100% complete. This is the
default behavior of the software and you cannot change this behavior.
Now, here's what else you don't know. You preserve the original planned
Work for each task in your project by saving a project baseline before you
begin collecting actuals in the project. To save a baseline, click Tools -
Tracking - Save Baseline. You can compare the variance between baseline
values and current/actual values by displaying any task View, such as the
Gantt Chart, and then applying either the Work, Cost, and Variance tables.
For example, to apply the Work table, click View - Table - Work. Hope this
helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Ramesh" wrote in message
news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
> Hi,
> We have recently implemented microsoft project server 2003 in our
> oragnisation.
> My projects team is facing big issuse in project server, ie whenever a
> resource submit his timesheet (effort) in project web access approved by
> the
> project manager, this will be updating the actuals in microsoft project
> plan
> in the server, the problem is the plan effort is also changing to actual
> effort.
>
> For Example the resource A has planned effort of 4 hrs, but the resources
> complete the task within 3 hrs and sent for manager approval. When the
> manager approve the time sheet. The planned effort of 4 hrs is changed to
> 3
> hrs.
>
> Please hlep me on the above issuse
>
> Thanks in advance
>
> Regards,
> Ramesh
date: Thu, 15 Feb 2007 09:56:39 -0700
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com
Re: Project Server
Thanks Dale Howard,
This answer my question
Henceforth i will post all my questions to microsoft.public.project.server
newsgroup
Thank you for quick reply
Regards,
Ramesh
"Dale Howard [MVP]" wrote:
> Ramesh --
>
> In the future, please post your Project Server questions in the
> microsoft.public.project.server newsgroup, as this newsgroup is closing
> down. To answer your question, you are missing a fundamental principle of
> how Microsoft Project works, which is "actuals always replace estimates."
> If you schedule a task to take 4 hours of Work, and a resource submits 3
> hours of Actual Work and sets Remaining Work to 0 hours (indicating the task
> is complete), the system replaces the 4 hours of planned Work with the 3
> hours of Actual Work and marks the task as 100% complete. This is the
> default behavior of the software and you cannot change this behavior.
>
> Now, here's what else you don't know. You preserve the original planned
> Work for each task in your project by saving a project baseline before you
> begin collecting actuals in the project. To save a baseline, click Tools -
> Tracking - Save Baseline. You can compare the variance between baseline
> values and current/actual values by displaying any task View, such as the
> Gantt Chart, and then applying either the Work, Cost, and Variance tables.
> For example, to apply the Work table, click View - Table - Work. Hope this
> helps.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
>
> "Ramesh" wrote in message
> news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
> > Hi,
> > We have recently implemented microsoft project server 2003 in our
> > oragnisation.
> > My projects team is facing big issuse in project server, ie whenever a
> > resource submit his timesheet (effort) in project web access approved by
> > the
> > project manager, this will be updating the actuals in microsoft project
> > plan
> > in the server, the problem is the plan effort is also changing to actual
> > effort.
> >
> > For Example the resource A has planned effort of 4 hrs, but the resources
> > complete the task within 3 hrs and sent for manager approval. When the
> > manager approve the time sheet. The planned effort of 4 hrs is changed to
> > 3
> > hrs.
> >
> > Please hlep me on the above issuse
> >
> > Thanks in advance
> >
> > Regards,
> > Ramesh
>
>
>
date: Thu, 15 Feb 2007 21:07:03 -0800
author: Ramesh
Re: Project Server
Ramesh --
You are more than welcome, my friend! :)
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Ramesh" wrote in message
news:944B7AC3-0BD5-485A-A474-0E21B5EEA099@microsoft.com...
> Thanks Dale Howard,
>
> This answer my question
> Henceforth i will post all my questions to microsoft.public.project.server
> newsgroup
>
> Thank you for quick reply
>
> Regards,
> Ramesh
>
>
> "Dale Howard [MVP]" wrote:
>
>> Ramesh --
>>
>> In the future, please post your Project Server questions in the
>> microsoft.public.project.server newsgroup, as this newsgroup is closing
>> down. To answer your question, you are missing a fundamental principle
>> of
>> how Microsoft Project works, which is "actuals always replace estimates."
>> If you schedule a task to take 4 hours of Work, and a resource submits 3
>> hours of Actual Work and sets Remaining Work to 0 hours (indicating the
>> task
>> is complete), the system replaces the 4 hours of planned Work with the 3
>> hours of Actual Work and marks the task as 100% complete. This is the
>> default behavior of the software and you cannot change this behavior.
>>
>> Now, here's what else you don't know. You preserve the original planned
>> Work for each task in your project by saving a project baseline before
>> you
>> begin collecting actuals in the project. To save a baseline, click
>> Tools -
>> Tracking - Save Baseline. You can compare the variance between baseline
>> values and current/actual values by displaying any task View, such as the
>> Gantt Chart, and then applying either the Work, Cost, and Variance
>> tables.
>> For example, to apply the Work table, click View - Table - Work. Hope
>> this
>> helps.
>>
>> --
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>>
>> "Ramesh" wrote in message
>> news:177BFD0D-5E8A-4CF2-A112-696530875C0C@microsoft.com...
>> > Hi,
>> > We have recently implemented microsoft project server 2003 in our
>> > oragnisation.
>> > My projects team is facing big issuse in project server, ie whenever a
>> > resource submit his timesheet (effort) in project web access approved
>> > by
>> > the
>> > project manager, this will be updating the actuals in microsoft project
>> > plan
>> > in the server, the problem is the plan effort is also changing to
>> > actual
>> > effort.
>> >
>> > For Example the resource A has planned effort of 4 hrs, but the
>> > resources
>> > complete the task within 3 hrs and sent for manager approval. When the
>> > manager approve the time sheet. The planned effort of 4 hrs is changed
>> > to
>> > 3
>> > hrs.
>> >
>> > Please hlep me on the above issuse
>> >
>> > Thanks in advance
>> >
>> > Regards,
>> > Ramesh
>>
>>
>>
date: Fri, 16 Feb 2007 08:19:42 -0700
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com
|
|