Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: 9 Jun 2006 12:08:57 -0700,    group: microsoft.public.project.pro_and_server        back       


Summary Tasks and Subtasks - Calculating Duration   
Hello,

I am a new user of Microsoft Project 2003 Professional. I am trying to
outlining a multi phase process where the five phases are displayed as
summary tasks with each having a number of subsequent subtasks. When
entering duration for each subtask, the duration value calculated for
the summary task is the highest subtask duration. For example:

                                   Duration
Summary Task                       2
  subtask                          2
  subtask                          2
  subtask                          2

I would be interested in displaying a total duration for the summary
task (Phase) based on the time required to complete each subtask. So,
using the above example, the Summary Task duration value would be 6.

Can this be done?

Thank you very much for your time.

Cheers,

Tim
date: 9 Jun 2006 12:08:57 -0700   author:   unknown

Re: Summary Tasks and Subtasks - Calculating Duration   
Tim --

In the future, please post your questions in either the 
microsoft.public.project newsgroup (for questons about the Microsoft Project 
desktop app) or in the  microsoft.public.project.server newsgroup (for 
Project Server questions).  To answer your question, you are 
misunderstanding how Microsoft Project calculates the Duration of a summary 
task.  The system calculates the Duration of the summary task from the Start 
date of the earliest-starting task to the Finish date of the 
latest-finishing task, minus any non-working days.  In your example, it 
sounds like you have a series of parallel tasks, each of which is 2 days 
Duration.  There is no way to force Microsoft Project to calculate the 
Duration of a summary task any other way.  Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


 wrote in message 
news:1149880137.431680.166640@j55g2000cwa.googlegroups.com...
> Hello,
>
> I am a new user of Microsoft Project 2003 Professional. I am trying to
> outlining a multi phase process where the five phases are displayed as
> summary tasks with each having a number of subsequent subtasks. When
> entering duration for each subtask, the duration value calculated for
> the summary task is the highest subtask duration. For example:
>
>                                   Duration
> Summary Task                       2
>  subtask                          2
>  subtask                          2
>  subtask                          2
>
> I would be interested in displaying a total duration for the summary
> task (Phase) based on the time required to complete each subtask. So,
> using the above example, the Summary Task duration value would be 6.
>
> Can this be done?
>
> Thank you very much for your time.
>
> Cheers,
>
> Tim
>
date: Fri, 9 Jun 2006 17:25:14 -0600   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us