Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: 12 Apr 2006 17:12:30 -0700,    group: microsoft.public.project.pro_and_server        back       


Manage Organization link not available in PWA   
Hello,

I've been going through previously posted comments about hiding deleted
tasks in the timesheet view in PWA and I've determined that in order to
correct this problem, I need to enable the "Hide" feature, only I
cannot seem to find the path that will allow me to do so.  As the
Administrator, I for some reason do not have the Manage Organization
link from the Admin menu.  Any suggestions as to how I get to Manage
Organization and furthermore, how I enable the Hide button so that it
is visible on the timesheets of our resources?

Any help would be appreciated.

Thanks!

Katie Begell
date: 12 Apr 2006 17:12:30 -0700   author:   unknown

Re: Manage Organization link not available in PWA   
Katie --

In the future, please post your Project Server questions to the 
microsoft.public.project.server newsgroup, as this newsgroup is going to 
close down.  To answer your question, complete the following steps:

1.  Log into PWA with administrator permissions
2.  Click Admin - Server configuration
3.  In the features grid, scroll to the Tasks section
4.  Set the Hide Task from Timesheet permission to Allow
5.  Click the Save Changes button

Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


 wrote in message 
news:1144887150.531492.148020@z34g2000cwc.googlegroups.com...
> Hello,
>
> I've been going through previously posted comments about hiding deleted
> tasks in the timesheet view in PWA and I've determined that in order to
> correct this problem, I need to enable the "Hide" feature, only I
> cannot seem to find the path that will allow me to do so.  As the
> Administrator, I for some reason do not have the Manage Organization
> link from the Admin menu.  Any suggestions as to how I get to Manage
> Organization and furthermore, how I enable the Hide button so that it
> is visible on the timesheets of our resources?
>
> Any help would be appreciated.
>
> Thanks!
>
> Katie Begell
>
date: Thu, 13 Apr 2006 08:32:45 -0600   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com