Re: Manage Organization link not available in PWA
Katie --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is going to
close down. To answer your question, complete the following steps:
1. Log into PWA with administrator permissions
2. Click Admin - Server configuration
3. In the features grid, scroll to the Tasks section
4. Set the Hide Task from Timesheet permission to Allow
5. Click the Save Changes button
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
wrote in message
news:1144887150.531492.148020@z34g2000cwc.googlegroups.com...
> Hello,
>
> I've been going through previously posted comments about hiding deleted
> tasks in the timesheet view in PWA and I've determined that in order to
> correct this problem, I need to enable the "Hide" feature, only I
> cannot seem to find the path that will allow me to do so. As the
> Administrator, I for some reason do not have the Manage Organization
> link from the Admin menu. Any suggestions as to how I get to Manage
> Organization and furthermore, how I enable the Hide button so that it
> is visible on the timesheets of our resources?
>
> Any help would be appreciated.
>
> Thanks!
>
> Katie Begell
>
date: Thu, 13 Apr 2006 08:32:45 -0600
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com