Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Tue, 4 Apr 2006 15:12:35 +0100,    group: microsoft.public.project.pro_and_server        back       


Resource Calendar   
Most of the resources in my Enterprise Resource Pool are using the Standard
calendar as defined in the Enterprise Global project. However a few
resources have changed themselves to use a 'Nondefault working time' for all
dates in their calendar. When I try to set selected dates back to 'Use
default' in the radion button selection, it does not allow this setting and
instanly reverts back to "Nondefault working time"

Many Thanks,

David
date: Tue, 4 Apr 2006 15:12:35 +0100   author:   David Bowen temp

Re: Resource Calendar   
David --

I am totally puzzled by your problem description since resources CANNOT 
change their own calendars in the Enterprise Resource Pool.  To solve this 
problem, I would suggest you open the Enterprise Resource Pool for editing 
and examine the Base Calendar column.  The value should be set to Standard 
for all resources in the pool.  If this does not solve the problem, let us 
know.

Also, in the future, please post your Project Server questions to the 
microsoft.public.project.server newsgroup, as this newsgroup is going to 
close down.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"David Bowen" <temp> wrote in message 
news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
> Most of the resources in my Enterprise Resource Pool are using the 
> Standard
> calendar as defined in the Enterprise Global project. However a few
> resources have changed themselves to use a 'Nondefault working time' for 
> all
> dates in their calendar. When I try to set selected dates back to 'Use
> default' in the radion button selection, it does not allow this setting 
> and
> instanly reverts back to "Nondefault working time"
>
> Many Thanks,
>
> David
>
date: Fri, 7 Apr 2006 15:34:53 -0600   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Re: Resource Calendar   
Hi Dale,

I have looked in the pool and all resources are set to standard for their 
base calendar. When I say resource have changed themselves, a person has not 
physically changed their settings but within the system the resource seems 
to different settings to the others and will not allow this setting to 
revert back.

Dale

"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in 
message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
> David --
>
> I am totally puzzled by your problem description since resources CANNOT 
> change their own calendars in the Enterprise Resource Pool.  To solve this 
> problem, I would suggest you open the Enterprise Resource Pool for editing 
> and examine the Base Calendar column.  The value should be set to Standard 
> for all resources in the pool.  If this does not solve the problem, let us 
> know.
>
> Also, in the future, please post your Project Server questions to the 
> microsoft.public.project.server newsgroup, as this newsgroup is going to 
> close down.
>
> -- 
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
> "David Bowen" <temp> wrote in message 
> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>> Most of the resources in my Enterprise Resource Pool are using the 
>> Standard
>> calendar as defined in the Enterprise Global project. However a few
>> resources have changed themselves to use a 'Nondefault working time' for 
>> all
>> dates in their calendar. When I try to set selected dates back to 'Use
>> default' in the radion button selection, it does not allow this setting 
>> and
>> instanly reverts back to "Nondefault working time"
>>
>> Many Thanks,
>>
>> David
>>
>
>
date: Mon, 10 Apr 2006 14:02:05 +0100   author:   David Bowen temp

Re: Resource Calendar   
David --

Do these changes represent vacation or other nonworking time?

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"David Bowen" <temp> wrote in message 
news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
> Hi Dale,
>
> I have looked in the pool and all resources are set to standard for their 
> base calendar. When I say resource have changed themselves, a person has 
> not physically changed their settings but within the system the resource 
> seems to different settings to the others and will not allow this setting 
> to revert back.
>
> Dale
>
> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in 
> message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>> David --
>>
>> I am totally puzzled by your problem description since resources CANNOT 
>> change their own calendars in the Enterprise Resource Pool.  To solve 
>> this problem, I would suggest you open the Enterprise Resource Pool for 
>> editing and examine the Base Calendar column.  The value should be set to 
>> Standard for all resources in the pool.  If this does not solve the 
>> problem, let us know.
>>
>> Also, in the future, please post your Project Server questions to the 
>> microsoft.public.project.server newsgroup, as this newsgroup is going to 
>> close down.
>>
>> -- 
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>> "David Bowen" <temp> wrote in message 
>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>> Most of the resources in my Enterprise Resource Pool are using the 
>>> Standard
>>> calendar as defined in the Enterprise Global project. However a few
>>> resources have changed themselves to use a 'Nondefault working time' for 
>>> all
>>> dates in their calendar. When I try to set selected dates back to 'Use
>>> default' in the radion button selection, it does not allow this setting 
>>> and
>>> instanly reverts back to "Nondefault working time"
>>>
>>> Many Thanks,
>>>
>>> David
>>>
>>
>>
>
>
date: Mon, 10 Apr 2006 08:27:35 -0600   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Re: Resource Calendar   
We have about 20 enterprise resources and for the majority of these 
resources, all of the date in the calendar arre set to use default, so these 
resources inherit the non-working time days that I haved defined in the 
Enterprise Global Project standard calendar.

Three of these resources seem to not be able to pick up the standard 
calander settings and instead all days in their calendar are set to 
nondefault working time. Hence the bank holidays that are defined in the 
standard calendar are not picked up for these resources and I have to add 
them in as nonworking time against these resources again.

If I try to click 'Use default' against the resources calendar it does not 
set the radion button but reverts the radion button back to 'nondefault 
working time'

My question is how I can ensure these resources use the standard calader for 
all days?

David


"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in 
message news:%23M%23%23XoKXGHA.3448@TK2MSFTNGP03.phx.gbl...
> David --
>
> Do these changes represent vacation or other nonworking time?
>
> -- 
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
> "David Bowen" <temp> wrote in message 
> news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
>> Hi Dale,
>>
>> I have looked in the pool and all resources are set to standard for their 
>> base calendar. When I say resource have changed themselves, a person has 
>> not physically changed their settings but within the system the resource 
>> seems to different settings to the others and will not allow this setting 
>> to revert back.
>>
>> Dale
>>
>> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote 
>> in message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>>> David --
>>>
>>> I am totally puzzled by your problem description since resources CANNOT 
>>> change their own calendars in the Enterprise Resource Pool.  To solve 
>>> this problem, I would suggest you open the Enterprise Resource Pool for 
>>> editing and examine the Base Calendar column.  The value should be set 
>>> to Standard for all resources in the pool.  If this does not solve the 
>>> problem, let us know.
>>>
>>> Also, in the future, please post your Project Server questions to the 
>>> microsoft.public.project.server newsgroup, as this newsgroup is going to 
>>> close down.
>>>
>>> -- 
>>> Dale A. Howard [MVP]
>>> Enterprise Project Trainer/Consultant
>>> http://www.msprojectexperts.com
>>> http://www.projectserverexperts.com
>>> "We wrote the book on Project Server"
>>>
>>>
>>> "David Bowen" <temp> wrote in message 
>>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>>> Most of the resources in my Enterprise Resource Pool are using the 
>>>> Standard
>>>> calendar as defined in the Enterprise Global project. However a few
>>>> resources have changed themselves to use a 'Nondefault working time' 
>>>> for all
>>>> dates in their calendar. When I try to set selected dates back to 'Use
>>>> default' in the radion button selection, it does not allow this setting 
>>>> and
>>>> instanly reverts back to "Nondefault working time"
>>>>
>>>> Many Thanks,
>>>>
>>>> David
>>>>
>>>
>>>
>>
>>
>
>
date: Tue, 11 Apr 2006 14:15:25 +0100   author:   David Bowen temp

Re: Resource Calendar   
David --

Thank you for your clear explanation.  Now I understand.  I have never seen 
the behavior you describe.  What happens if you check out these three 
resources for editing, set their Base Calendar to something else (assuming 
you have another base calendar), save the Enterprise Resource Pool, then 
change their Base Calendar back to the Standar calendar and save the 
Enterprise Resource Pool again?  Are their calendars now correct?  Let us 
know.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"David Bowen" <temp> wrote in message 
news:Ox4YEoWXGHA.128@TK2MSFTNGP05.phx.gbl...
> We have about 20 enterprise resources and for the majority of these 
> resources, all of the date in the calendar arre set to use default, so 
> these resources inherit the non-working time days that I haved defined in 
> the Enterprise Global Project standard calendar.
>
> Three of these resources seem to not be able to pick up the standard 
> calander settings and instead all days in their calendar are set to 
> nondefault working time. Hence the bank holidays that are defined in the 
> standard calendar are not picked up for these resources and I have to add 
> them in as nonworking time against these resources again.
>
> If I try to click 'Use default' against the resources calendar it does not 
> set the radion button but reverts the radion button back to 'nondefault 
> working time'
>
> My question is how I can ensure these resources use the standard calader 
> for all days?
>
> David
>
>
> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in 
> message news:%23M%23%23XoKXGHA.3448@TK2MSFTNGP03.phx.gbl...
>> David --
>>
>> Do these changes represent vacation or other nonworking time?
>>
>> -- 
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>> "David Bowen" <temp> wrote in message 
>> news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
>>> Hi Dale,
>>>
>>> I have looked in the pool and all resources are set to standard for 
>>> their base calendar. When I say resource have changed themselves, a 
>>> person has not physically changed their settings but within the system 
>>> the resource seems to different settings to the others and will not 
>>> allow this setting to revert back.
>>>
>>> Dale
>>>
>>> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote 
>>> in message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>>>> David --
>>>>
>>>> I am totally puzzled by your problem description since resources CANNOT 
>>>> change their own calendars in the Enterprise Resource Pool.  To solve 
>>>> this problem, I would suggest you open the Enterprise Resource Pool for 
>>>> editing and examine the Base Calendar column.  The value should be set 
>>>> to Standard for all resources in the pool.  If this does not solve the 
>>>> problem, let us know.
>>>>
>>>> Also, in the future, please post your Project Server questions to the 
>>>> microsoft.public.project.server newsgroup, as this newsgroup is going 
>>>> to close down.
>>>>
>>>> -- 
>>>> Dale A. Howard [MVP]
>>>> Enterprise Project Trainer/Consultant
>>>> http://www.msprojectexperts.com
>>>> http://www.projectserverexperts.com
>>>> "We wrote the book on Project Server"
>>>>
>>>>
>>>> "David Bowen" <temp> wrote in message 
>>>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>>>> Most of the resources in my Enterprise Resource Pool are using the 
>>>>> Standard
>>>>> calendar as defined in the Enterprise Global project. However a few
>>>>> resources have changed themselves to use a 'Nondefault working time' 
>>>>> for all
>>>>> dates in their calendar. When I try to set selected dates back to 'Use
>>>>> default' in the radion button selection, it does not allow this 
>>>>> setting and
>>>>> instanly reverts back to "Nondefault working time"
>>>>>
>>>>> Many Thanks,
>>>>>
>>>>> David
>>>>>
>>>>
>>>>
>>>
>>>
>>
>>
>
>
date: Tue, 11 Apr 2006 08:33:38 -0600   author:   Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us