|
|
|
date: Tue, 4 Apr 2006 15:12:35 +0100,
group: microsoft.public.project.pro_and_server
back
Re: Resource Calendar
Hi Dale,
I have looked in the pool and all resources are set to standard for their
base calendar. When I say resource have changed themselves, a person has not
physically changed their settings but within the system the resource seems
to different settings to the others and will not allow this setting to
revert back.
Dale
"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
> David --
>
> I am totally puzzled by your problem description since resources CANNOT
> change their own calendars in the Enterprise Resource Pool. To solve this
> problem, I would suggest you open the Enterprise Resource Pool for editing
> and examine the Base Calendar column. The value should be set to Standard
> for all resources in the pool. If this does not solve the problem, let us
> know.
>
> Also, in the future, please post your Project Server questions to the
> microsoft.public.project.server newsgroup, as this newsgroup is going to
> close down.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
> "David Bowen" <temp> wrote in message
> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>> Most of the resources in my Enterprise Resource Pool are using the
>> Standard
>> calendar as defined in the Enterprise Global project. However a few
>> resources have changed themselves to use a 'Nondefault working time' for
>> all
>> dates in their calendar. When I try to set selected dates back to 'Use
>> default' in the radion button selection, it does not allow this setting
>> and
>> instanly reverts back to "Nondefault working time"
>>
>> Many Thanks,
>>
>> David
>>
>
>
date: Mon, 10 Apr 2006 14:02:05 +0100
author: David Bowen temp
Re: Resource Calendar
David --
Do these changes represent vacation or other nonworking time?
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"David Bowen" <temp> wrote in message
news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
> Hi Dale,
>
> I have looked in the pool and all resources are set to standard for their
> base calendar. When I say resource have changed themselves, a person has
> not physically changed their settings but within the system the resource
> seems to different settings to the others and will not allow this setting
> to revert back.
>
> Dale
>
> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
> message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>> David --
>>
>> I am totally puzzled by your problem description since resources CANNOT
>> change their own calendars in the Enterprise Resource Pool. To solve
>> this problem, I would suggest you open the Enterprise Resource Pool for
>> editing and examine the Base Calendar column. The value should be set to
>> Standard for all resources in the pool. If this does not solve the
>> problem, let us know.
>>
>> Also, in the future, please post your Project Server questions to the
>> microsoft.public.project.server newsgroup, as this newsgroup is going to
>> close down.
>>
>> --
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>> "David Bowen" <temp> wrote in message
>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>> Most of the resources in my Enterprise Resource Pool are using the
>>> Standard
>>> calendar as defined in the Enterprise Global project. However a few
>>> resources have changed themselves to use a 'Nondefault working time' for
>>> all
>>> dates in their calendar. When I try to set selected dates back to 'Use
>>> default' in the radion button selection, it does not allow this setting
>>> and
>>> instanly reverts back to "Nondefault working time"
>>>
>>> Many Thanks,
>>>
>>> David
>>>
>>
>>
>
>
date: Mon, 10 Apr 2006 08:27:35 -0600
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com
Re: Resource Calendar
We have about 20 enterprise resources and for the majority of these
resources, all of the date in the calendar arre set to use default, so these
resources inherit the non-working time days that I haved defined in the
Enterprise Global Project standard calendar.
Three of these resources seem to not be able to pick up the standard
calander settings and instead all days in their calendar are set to
nondefault working time. Hence the bank holidays that are defined in the
standard calendar are not picked up for these resources and I have to add
them in as nonworking time against these resources again.
If I try to click 'Use default' against the resources calendar it does not
set the radion button but reverts the radion button back to 'nondefault
working time'
My question is how I can ensure these resources use the standard calader for
all days?
David
"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
message news:%23M%23%23XoKXGHA.3448@TK2MSFTNGP03.phx.gbl...
> David --
>
> Do these changes represent vacation or other nonworking time?
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We wrote the book on Project Server"
>
>
> "David Bowen" <temp> wrote in message
> news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
>> Hi Dale,
>>
>> I have looked in the pool and all resources are set to standard for their
>> base calendar. When I say resource have changed themselves, a person has
>> not physically changed their settings but within the system the resource
>> seems to different settings to the others and will not allow this setting
>> to revert back.
>>
>> Dale
>>
>> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote
>> in message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>>> David --
>>>
>>> I am totally puzzled by your problem description since resources CANNOT
>>> change their own calendars in the Enterprise Resource Pool. To solve
>>> this problem, I would suggest you open the Enterprise Resource Pool for
>>> editing and examine the Base Calendar column. The value should be set
>>> to Standard for all resources in the pool. If this does not solve the
>>> problem, let us know.
>>>
>>> Also, in the future, please post your Project Server questions to the
>>> microsoft.public.project.server newsgroup, as this newsgroup is going to
>>> close down.
>>>
>>> --
>>> Dale A. Howard [MVP]
>>> Enterprise Project Trainer/Consultant
>>> http://www.msprojectexperts.com
>>> http://www.projectserverexperts.com
>>> "We wrote the book on Project Server"
>>>
>>>
>>> "David Bowen" <temp> wrote in message
>>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>>> Most of the resources in my Enterprise Resource Pool are using the
>>>> Standard
>>>> calendar as defined in the Enterprise Global project. However a few
>>>> resources have changed themselves to use a 'Nondefault working time'
>>>> for all
>>>> dates in their calendar. When I try to set selected dates back to 'Use
>>>> default' in the radion button selection, it does not allow this setting
>>>> and
>>>> instanly reverts back to "Nondefault working time"
>>>>
>>>> Many Thanks,
>>>>
>>>> David
>>>>
>>>
>>>
>>
>>
>
>
date: Tue, 11 Apr 2006 14:15:25 +0100
author: David Bowen temp
Re: Resource Calendar
David --
Thank you for your clear explanation. Now I understand. I have never seen
the behavior you describe. What happens if you check out these three
resources for editing, set their Base Calendar to something else (assuming
you have another base calendar), save the Enterprise Resource Pool, then
change their Base Calendar back to the Standar calendar and save the
Enterprise Resource Pool again? Are their calendars now correct? Let us
know.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"David Bowen" <temp> wrote in message
news:Ox4YEoWXGHA.128@TK2MSFTNGP05.phx.gbl...
> We have about 20 enterprise resources and for the majority of these
> resources, all of the date in the calendar arre set to use default, so
> these resources inherit the non-working time days that I haved defined in
> the Enterprise Global Project standard calendar.
>
> Three of these resources seem to not be able to pick up the standard
> calander settings and instead all days in their calendar are set to
> nondefault working time. Hence the bank holidays that are defined in the
> standard calendar are not picked up for these resources and I have to add
> them in as nonworking time against these resources again.
>
> If I try to click 'Use default' against the resources calendar it does not
> set the radion button but reverts the radion button back to 'nondefault
> working time'
>
> My question is how I can ensure these resources use the standard calader
> for all days?
>
> David
>
>
> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
> message news:%23M%23%23XoKXGHA.3448@TK2MSFTNGP03.phx.gbl...
>> David --
>>
>> Do these changes represent vacation or other nonworking time?
>>
>> --
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>> "David Bowen" <temp> wrote in message
>> news:eunG97JXGHA.4148@TK2MSFTNGP03.phx.gbl...
>>> Hi Dale,
>>>
>>> I have looked in the pool and all resources are set to standard for
>>> their base calendar. When I say resource have changed themselves, a
>>> person has not physically changed their settings but within the system
>>> the resource seems to different settings to the others and will not
>>> allow this setting to revert back.
>>>
>>> Dale
>>>
>>> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote
>>> in message news:ucjTJpoWGHA.4580@TK2MSFTNGP04.phx.gbl...
>>>> David --
>>>>
>>>> I am totally puzzled by your problem description since resources CANNOT
>>>> change their own calendars in the Enterprise Resource Pool. To solve
>>>> this problem, I would suggest you open the Enterprise Resource Pool for
>>>> editing and examine the Base Calendar column. The value should be set
>>>> to Standard for all resources in the pool. If this does not solve the
>>>> problem, let us know.
>>>>
>>>> Also, in the future, please post your Project Server questions to the
>>>> microsoft.public.project.server newsgroup, as this newsgroup is going
>>>> to close down.
>>>>
>>>> --
>>>> Dale A. Howard [MVP]
>>>> Enterprise Project Trainer/Consultant
>>>> http://www.msprojectexperts.com
>>>> http://www.projectserverexperts.com
>>>> "We wrote the book on Project Server"
>>>>
>>>>
>>>> "David Bowen" <temp> wrote in message
>>>> news:%23EhtTH$VGHA.4416@TK2MSFTNGP15.phx.gbl...
>>>>> Most of the resources in my Enterprise Resource Pool are using the
>>>>> Standard
>>>>> calendar as defined in the Enterprise Global project. However a few
>>>>> resources have changed themselves to use a 'Nondefault working time'
>>>>> for all
>>>>> dates in their calendar. When I try to set selected dates back to 'Use
>>>>> default' in the radion button selection, it does not allow this
>>>>> setting and
>>>>> instanly reverts back to "Nondefault working time"
>>>>>
>>>>> Many Thanks,
>>>>>
>>>>> David
>>>>>
>>>>
>>>>
>>>
>>>
>>
>>
>
>
date: Tue, 11 Apr 2006 08:33:38 -0600
author: Dale Howard [MVP] dale(dot)howard(at)msprojectexperts(dot)com
|
|