Hi. I"m trying to have my custom field to roll up but to summary as a weighted average by the Effort (Work). The same thing % work complete would roll up. Unfortunately the only method is MS project has is simple average. this is distorting my comparaison with the % work complete. Any help is appreciated. Nash
See answer in other newsgroup. Generally it is good practice to only post in ONE newsgroup. -Jack Dahlgren "Nash" wrote in message news:B5D8ED11-C308-48D2-B300-C344F9476A1C@microsoft.com... > Hi. > > I"m trying to have my custom field to roll up but to summary as a weighted > average by the Effort (Work). The same thing % work complete would roll > up. > > Unfortunately the only method is MS project has is simple average. this > is > distorting my comparaison with the % work complete. > > Any help is appreciated. > > Nash