|
|
|
date: Mon, 25 Aug 2008 22:23:00 -0700,
group: microsoft.public.project.developer
back
RE: Correct algorithm to create Project using PSI?
Martin,
Can you please elaborate on what is a Project Plan? I cant see why
QueueUpdateProject needs to be called because I can see that the Task Custom
Fields (we use a couple of them) have been pushed once I open the newly
created Project.
Regards,
Subramanian
"Martin Winzig" wrote:
> It's nearly correct.
>
>
> but After QueueAddToProject you ussualy have to call queueUpdateProject
> because same data tables from ProjectDataset ( for example task custom
> fields) are not added to project plan.
>
>
>
>
>
> With
> --
> Blog: http://www.projectserver.cz
>
>
> "Subramanian Vasudevan" wrote:
>
> > We are interning in a software firm and are building a 3rd party Application
> > that integrates into Microsoft Project using the Microsoft Project Server
> > 2007 PSI Webservices. We are facing a problem that we will be grateful if
> > anybody could solve.
> >
> > These are the kind of Projects which will be supplied by our application.
> > All the Resources we use must fit into the category of Enterprise Resources,
> > since Status Updates through PSI are only possible with assignments of
> > Enterprise Resources. We have such need of performing time-phased actuals
> > updates on Resource Assignments.
> >
> > Hence, the Global Resources must first be created in the Enterprise Pool if
> > not found, and then be imported into the Project's Team.
> > The flow of our algorithm for creating such a project given all the data is
> > as follows:
> >
> > First create the empty Project in Project Server using QueueCreateProject
> > function. It will not have tasks and assignments yet. (roughly 1 second)
> > Go through the list of resources and create them in the Enterprise Pool if
> > not already found. (roughly 1-2 secs)
> >
> > Import those Enterprise Resources into the Project's Team by using
> > QueueUpdateProjectTeam function. This step requires that the Project have
> > been created in the first place, otherwise it throws an exception. (roughly
> > 1-2 secs)
> >
> > Now add the list of tasks and assignments to an empty Project DataSet.
> > Use QueueAddToProject function to add the tasks and assignments to the
> > Project created in step 1. (roughly 3 secs)
> >
> > Finally Publish the Project. (roughly 4-5 secs)
> >
> > This way of doing things takes a lot of processing time, which we want to
> > avoid. Whereas if the same steps are carried out using the Microsoft Project
> > Client, the whole thing completes in one Queue Job called 'Project Save from
> > Project Professional', which seemingly does all 6 steps in much lesser time.
> >
> > Are we missing something here? Is there a better way of doing the same thing
> > that takes lesser time? What is the proper method to create such a Project in
> > MS Project Server using the PSI? We would be very grateful if you could help
> > us out.
date: Wed, 27 Aug 2008 05:49:00 -0700
author: Subramanian Vasudevan
RE: Correct algorithm to create Project using PSI?
They aree added correctly when you cal queuecreateproject
But you can't add them using queueaddtoproject
--
Blog: http://www.projectserver.cz
"Subramanian Vasudevan" wrote:
> Martin,
>
> Can you please elaborate on what is a Project Plan? I cant see why
> QueueUpdateProject needs to be called because I can see that the Task Custom
> Fields (we use a couple of them) have been pushed once I open the newly
> created Project.
>
> Regards,
>
> Subramanian
>
> "Martin Winzig" wrote:
>
> > It's nearly correct.
> >
> >
> > but After QueueAddToProject you ussualy have to call queueUpdateProject
> > because same data tables from ProjectDataset ( for example task custom
> > fields) are not added to project plan.
> >
> >
> >
> >
> >
> > With
> > --
> > Blog: http://www.projectserver.cz
> >
> >
> > "Subramanian Vasudevan" wrote:
> >
> > > We are interning in a software firm and are building a 3rd party Application
> > > that integrates into Microsoft Project using the Microsoft Project Server
> > > 2007 PSI Webservices. We are facing a problem that we will be grateful if
> > > anybody could solve.
> > >
> > > These are the kind of Projects which will be supplied by our application.
> > > All the Resources we use must fit into the category of Enterprise Resources,
> > > since Status Updates through PSI are only possible with assignments of
> > > Enterprise Resources. We have such need of performing time-phased actuals
> > > updates on Resource Assignments.
> > >
> > > Hence, the Global Resources must first be created in the Enterprise Pool if
> > > not found, and then be imported into the Project's Team.
> > > The flow of our algorithm for creating such a project given all the data is
> > > as follows:
> > >
> > > First create the empty Project in Project Server using QueueCreateProject
> > > function. It will not have tasks and assignments yet. (roughly 1 second)
> > > Go through the list of resources and create them in the Enterprise Pool if
> > > not already found. (roughly 1-2 secs)
> > >
> > > Import those Enterprise Resources into the Project's Team by using
> > > QueueUpdateProjectTeam function. This step requires that the Project have
> > > been created in the first place, otherwise it throws an exception. (roughly
> > > 1-2 secs)
> > >
> > > Now add the list of tasks and assignments to an empty Project DataSet.
> > > Use QueueAddToProject function to add the tasks and assignments to the
> > > Project created in step 1. (roughly 3 secs)
> > >
> > > Finally Publish the Project. (roughly 4-5 secs)
> > >
> > > This way of doing things takes a lot of processing time, which we want to
> > > avoid. Whereas if the same steps are carried out using the Microsoft Project
> > > Client, the whole thing completes in one Queue Job called 'Project Save from
> > > Project Professional', which seemingly does all 6 steps in much lesser time.
> > >
> > > Are we missing something here? Is there a better way of doing the same thing
> > > that takes lesser time? What is the proper method to create such a Project in
> > > MS Project Server using the PSI? We would be very grateful if you could help
> > > us out.
date: Wed, 27 Aug 2008 06:26:00 -0700
author: Martin Winzig
|
|