Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 20 Aug 2008 23:55:41 -0400,    group: microsoft.public.project.developer        back       


Automatically running VBA code in Project   
Hello,

  I want to display remaining budget amount for a task. I start with
a fixed budget amount for the first task with zero expense. Then I enter
expenses for following tasks. The aim is to calculate the remaining amount 
for
each task automatically as one enters the expenses.

    I created three columns: Budget, Expenses and Remaining Budget. The
example below shows values for these fields for the first three tasks.

Task 1: Budget=250,000 Expense=0.0        Remaining Budget = 250,000
Task 2: Budget=250,000 Expense=3,055    Remaining Budget = 246,945
Task 3: Budget=246.945 Expense=40,000  Remaining Budget = 206,945
....

    i.e. (new) Remaining Budget = Budget - sum of expenses so far. So the
formula should be if it were in Excel (Using the letter column headers) : G1
= E1, G2 = E2 - F1, G3 = E3 - F2, ....

    Here is the table  (Please view the email in html format to be able to
see the table)

        A                           E                    F                G
    Task Name           Budget         Expense    Remaining Budget

1    Close TS          "$250,000"   "$0.00"      "$250,000"
2    Drafting            "$250,000"   "$3,055"    "$246,945"
3    Pay Salary        "$246,945"  "$40,000"   "$206,945"

    I believe the only way to do this is to use VBA. Although I know VB6
very well I am not familiar with VBA for Project.

I wrote the code below and run it in form click event. It is working.

Now I have two questions:

1. I want to calculate the remaining budget for tasks only not for sub 
tasks. How can I do this programmatically in VBA?
2. I want to have this feature (macro/program) to start when I load this 
Project automatically rather than running it manually. How can I do that?

    Thank you for any help.

Athena

Code:
--------------------------------------------------
Dim ts As Tasks

SelectAll
Set ts = ActiveSelection.Tasks

Dim t As Task

Dim budget As Single
Dim expense As Single
Dim remainingbudget As Single

i = 0
For Each t In ts
    i = i + 1
    If i = 3 Then budget = t.Cost1
    If i > 2 Then
        expense = t.Cost2
        t.Cost1 = FormatCurrency(budget, 2)
        budget = budget - expense
        remainingbudget = budget
        t.Text2 = FormatCurrency(remainingbudget, 2)
    End If
Next t
date: Wed, 20 Aug 2008 23:55:41 -0400   author:   Athena