Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 20 Aug 2008 14:01:14 -0700,    group: microsoft.public.project.developer        back       


lock task start regardless of leveling   
Is there a way to lock when a task starts, regardless of leveling?  right now 
if i have a 5 day task starting on monday morning and a 1 day task starting 
on wednesday morning, and put "Must Start On" constraints on both, leveling 
still moves the wednesday task to start on the next monday morning, after the 
first task is done.  i'd like it to split the 5 day task so that the 1 day 
task is done on wednesday and the 5 day task resumes on thursday and 
continues through next monday.  

thanks!
scott
date: Wed, 20 Aug 2008 14:01:14 -0700   author:   theintern

Re: lock task start regardless of leveling   
Hi Scott,

I suggest removing the constraints.  Insert the priority field in a 
task view.  Set the priority of the 1 day task to 1000 and leave the 
5d task to 500.  In the leveling command, select the option leveling 
can split and then level using Priority, Standard.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information 
about Microsoft Project

"theintern"  wrote in message 
news:12B6D9B7-5541-46D5-89D4-D40D28C9DB1A@microsoft.com...
> Is there a way to lock when a task starts, regardless of leveling? 
> right now
> if i have a 5 day task starting on monday morning and a 1 day task 
> starting
> on wednesday morning, and put "Must Start On" constraints on both, 
> leveling
> still moves the wednesday task to start on the next monday morning, 
> after the
> first task is done.  i'd like it to split the 5 day task so that the 
> 1 day
> task is done on wednesday and the 5 day task resumes on thursday and
> continues through next monday.
>
> thanks!
> scott
date: Thu, 21 Aug 2008 06:59:51 -0400   author:   JulieS