|
|
|
date: Wed, 23 Jul 2008 06:16:59 -0700 (PDT),
group: microsoft.public.project.developer
back
RE: Adding to Baseline data
Prashanth,
If you have an earlier version of the project before you entered status, you
could use that to baseline your schedule and then redo your updates.
Or you could remove your updates from the existing schedule (make it all
match baseline) then set your resource rates and rebaseline. Then update
again.
Those would be the only two ways to do it that I know of.
-Jack Dahlgren
"prashanth.sharangapani@gmail.com" wrote:
> Dear MPP users,
>
> I need one help. I use project 2003.
>
> I have one schedule already baselined. However, at the time of
> baselining, I had forgot to update the resources charge rate and it
> remained as $0. Now I have begun tracking the schedule, but SPI never
> shows up because BCWP is $0. I can go and re-baseline, but that will
> over write the previous baseline data (my first week of tracking
> indicates that we are doing very well on CPI, if I re-baseline, I will
> lose that!).
>
> Any idea on how to get around this?
>
> Thanks for the help.
>
> Prashanth
> Bangalore, India
>
date: Wed, 23 Jul 2008 07:22:00 -0700
author: Jack Dahlgren
Re: Adding to Baseline data
In article
,
prashanth.sharangapani@gmail.com wrote:
> Dear MPP users,
>
> I need one help. I use project 2003.
>
> I have one schedule already baselined. However, at the time of
> baselining, I had forgot to update the resources charge rate and it
> remained as $0. Now I have begun tracking the schedule, but SPI never
> shows up because BCWP is $0. I can go and re-baseline, but that will
> over write the previous baseline data (my first week of tracking
> indicates that we are doing very well on CPI, if I re-baseline, I will
> lose that!).
>
> Any idea on how to get around this?
>
> Thanks for the help.
>
> Prashanth
> Bangalore, India
Prashanth,
Let me offer a couple more options in addition to what Jack suggested.
You didn't specify exactly which baseline data you are concerned about
losing. Surely you want to "lose" the cost baseline because that is
incorrect anyway. If I assume you want to preserve basic baseline fields
such as start, finish, and duration, you could copy those existing
baseline fields into spare fields (e.g. Start1, Finish1, Duration1). Fix
your resource pay rate and re-baseline. Then copy the baseline data you
saved in the spare fields back to their original baseline fields.
This may be a bit overkill for a one-time problem but the above process
or something very similar could be automated with VBA.
John
Project MVP
date: Wed, 23 Jul 2008 07:57:42 -0700
author: John
|
|