|
|
|
date: Tue, 22 Jul 2008 04:08:00 -0700,
group: microsoft.public.project.developer
back
Re: Export Task Information to Excel
In article ,
TonyK wrote:
> Hi John
> Now I understand why it is not printing detail for all milestones.
> You can tell I am NOT a programmer can't you.
> Many thanks for your help.
> Kind regards
> --
> TonyK
TonyK,
You're welcome and thanks for the feedback.
John
Project MVP
>
>
> "John" wrote:
>
> > In article ,
> > TonyK wrote:
> >
> > > Hi
> > > I am using the code kindly made available by Jack Dahlgren to export
> > > certain
> > > data to Excel. I am exporting Milestone information to a spreadsheet
> > > however
> > > on some of the milestones it is only exporting the milestone name and not
> > > the
> > > following fields I have requested:
> > > Milestone
> > > Work
> > > Actual Work
> > > Duration
> > > Baseline Start
> > > Actual Start
> > > Baseline Finish
> > > Actual Finish
> > > It should be noted that the first two milestones within the range I am
> > > exporting contains this information.
> > > I have checked the MSP Plan and the information is there.
> > > In summary I am exporting milestone for the month of July and there are
> > > seven of them. Two of them contain all the information (the first two).
> > > The
> > > remaining 5 only contain the milestone name.
> > > Any advice would be appreciated.
> >
> > TonyK,
> > Just for reference, there should be no work, actual or otherwise,
> > associated with a milestone. A milestone by definition is a "0" duration
> > event that marks the start of a group of tasks or the completion of a
> > group of tasks. It is either complete or not complete - there is no
> > partial completion of a milestone.
> >
> > With regard to using Jack's macro, I assume you are using his "export
> > hierarchy to Excel" code that has been modified to include the extra
> > fields. Unless a task has resources assigned, Jack's code will only
> > export the task name - that may be why you only see task name
> > information for some milestones. You can further modify the code to
> > include all the data you want by writing Project data outside the
> > assignment loop.
> >
> > Hope this helps.
> > John
> > Project MVP
> >
date: Wed, 23 Jul 2008 07:48:41 -0700
author: John
|
|