|
|
|
date: Wed, 9 Jul 2008 00:23:26 -0700 (PDT),
group: microsoft.public.project.developer
back
Having MPP calculate units based on actual finish dates
Dear MPP users,
I need one help. I use MPP 2003.
1. Let us say, I have a task A that has a planned work of 40 hours,
spanning Monday through Friday. This task has a resource 'R'
allocated. 'R' is supposed to spend 8 hours every day.
2. Now, on the 'next' Monday, when I want to take status from 'R', I
find from his timesheet, that he has over stayed and completed the
task in 4 days.
3. I now go to the 'Actual Work' column, enter 40, and then go to the
'Actual Finish' and say that the task finished on Thursday as against
a planned finish of Friday.
4. At this point I would expect MPP to change the units on 'R' to
indicate that, in reality, 'R' was overloaded and spent effort
equivalent to 125% units (as against planned 100% units planned).
Issue: (4) above does not work. When I enter the actual finish as
Thursday, then the MPP will go and change the 'Actual Work' to what is
thinks is possible in 4 days. Since I want the actual work to be
accurate, I'm forced to live with a situation where the actual finish
is incorrect. How do I resolve this situation?
Thanks in advance.
Prashanth
Bangalore, India
date: Wed, 9 Jul 2008 00:23:26 -0700 (PDT)
author: unknown
Re: Having MPP calculate units based on actual finish dates
Hi,
Simplest is to select the Resource Usage View
Right click the yellow timephased area and select Actual Work. Now enter
actual hours as entered into the timesheet. If you have 10h per day, then
there will be no work left for Friday and an actual finish date of Thursday
evening.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
wrote in message
news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> Dear MPP users,
>
> I need one help. I use MPP 2003.
>
> 1. Let us say, I have a task A that has a planned work of 40 hours,
> spanning Monday through Friday. This task has a resource 'R'
> allocated. 'R' is supposed to spend 8 hours every day.
> 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> find from his timesheet, that he has over stayed and completed the
> task in 4 days.
> 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> 'Actual Finish' and say that the task finished on Thursday as against
> a planned finish of Friday.
> 4. At this point I would expect MPP to change the units on 'R' to
> indicate that, in reality, 'R' was overloaded and spent effort
> equivalent to 125% units (as against planned 100% units planned).
>
> Issue: (4) above does not work. When I enter the actual finish as
> Thursday, then the MPP will go and change the 'Actual Work' to what is
> thinks is possible in 4 days. Since I want the actual work to be
> accurate, I'm forced to live with a situation where the actual finish
> is incorrect. How do I resolve this situation?
>
> Thanks in advance.
>
> Prashanth
> Bangalore, India
date: Wed, 9 Jul 2008 21:41:18 +1200
author: Rod Gill rodATproject-systemsDOTcoDOTnz
Re: Having MPP calculate units based on actual finish dates
Hello Rod,
Superb! It worked! Thanks so much! I did what you said and found that the
actual went to 125%.
However, is there still a way for MPP to automatically do it? The resource
usage view takes lot of time to update. I have 30 people on my team and it is
quite difficult to keep changing data on a 'day' basis.
Thanks again!
Prashanth
"Rod Gill" wrote:
> Hi,
>
> Simplest is to select the Resource Usage View
>
> Right click the yellow timephased area and select Actual Work. Now enter
> actual hours as entered into the timesheet. If you have 10h per day, then
> there will be no work left for Friday and an actual finish date of Thursday
> evening.
>
> --
>
> Rod Gill
> Microsoft MVP for Project
>
> Author of the only book on Project VBA, see:
> http://www.projectvbabook.com
>
>
>
> wrote in message
> news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> > Dear MPP users,
> >
> > I need one help. I use MPP 2003.
> >
> > 1. Let us say, I have a task A that has a planned work of 40 hours,
> > spanning Monday through Friday. This task has a resource 'R'
> > allocated. 'R' is supposed to spend 8 hours every day.
> > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> > find from his timesheet, that he has over stayed and completed the
> > task in 4 days.
> > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> > 'Actual Finish' and say that the task finished on Thursday as against
> > a planned finish of Friday.
> > 4. At this point I would expect MPP to change the units on 'R' to
> > indicate that, in reality, 'R' was overloaded and spent effort
> > equivalent to 125% units (as against planned 100% units planned).
> >
> > Issue: (4) above does not work. When I enter the actual finish as
> > Thursday, then the MPP will go and change the 'Actual Work' to what is
> > thinks is possible in 4 days. Since I want the actual work to be
> > accurate, I'm forced to live with a situation where the actual finish
> > is incorrect. How do I resolve this situation?
> >
> > Thanks in advance.
> >
> > Prashanth
> > Bangalore, India
>
>
date: Wed, 9 Jul 2008 03:53:00 -0700
author: Hemmige S Prashanth
Re: Having MPP calculate units based on actual finish dates
Prashanth
I am having the exact same problem which I haven't fully resolved.
As Rod previously mentioned, all it seems you can do is enter the actual
work in the time phased sheet, which I agree with. But like you I don't want
to enter time on a daily basis for all resources. I would rather just enter
the total actual work for each resource. One way I have reduced the number of
inputs is to actually change the timescale on the right to say months or
years. So rather than entering actual hours per day, you enter it per year,
this will spread the single input evenly over the duration of the task. (I
enter the actual Start and actual Finish dates first and then the actual
time). Of course if the task spans two calendar years, you need two inputs.
I have also played around with the "Updating task status updates resource
status" (under Tools/Options/Calculations), but this only seems to work as
long as the task is not 100% complete.
Would be very interested to know if you find a proper solution.
--
Robin
"Hemmige S Prashanth" wrote:
> Hello Rod,
>
> Superb! It worked! Thanks so much! I did what you said and found that the
> actual went to 125%.
>
> However, is there still a way for MPP to automatically do it? The resource
> usage view takes lot of time to update. I have 30 people on my team and it is
> quite difficult to keep changing data on a 'day' basis.
>
> Thanks again!
>
> Prashanth
>
>
> "Rod Gill" wrote:
>
> > Hi,
> >
> > Simplest is to select the Resource Usage View
> >
> > Right click the yellow timephased area and select Actual Work. Now enter
> > actual hours as entered into the timesheet. If you have 10h per day, then
> > there will be no work left for Friday and an actual finish date of Thursday
> > evening.
> >
> > --
> >
> > Rod Gill
> > Microsoft MVP for Project
> >
> > Author of the only book on Project VBA, see:
> > http://www.projectvbabook.com
> >
> >
> >
> > wrote in message
> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> > > Dear MPP users,
> > >
> > > I need one help. I use MPP 2003.
> > >
> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
> > > spanning Monday through Friday. This task has a resource 'R'
> > > allocated. 'R' is supposed to spend 8 hours every day.
> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> > > find from his timesheet, that he has over stayed and completed the
> > > task in 4 days.
> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> > > 'Actual Finish' and say that the task finished on Thursday as against
> > > a planned finish of Friday.
> > > 4. At this point I would expect MPP to change the units on 'R' to
> > > indicate that, in reality, 'R' was overloaded and spent effort
> > > equivalent to 125% units (as against planned 100% units planned).
> > >
> > > Issue: (4) above does not work. When I enter the actual finish as
> > > Thursday, then the MPP will go and change the 'Actual Work' to what is
> > > thinks is possible in 4 days. Since I want the actual work to be
> > > accurate, I'm forced to live with a situation where the actual finish
> > > is incorrect. How do I resolve this situation?
> > >
> > > Thanks in advance.
> > >
> > > Prashanth
> > > Bangalore, India
> >
> >
date: Wed, 9 Jul 2008 07:46:01 -0700
author: Robin Roe
Re: Having MPP calculate units based on actual finish dates
Hi,
Firstly you have to decide how accurately you need to report progress. If
this is by month, then you don't need to worry about a day here or there.
Make sure you update the actual start date for tasks and then updating
actual work and remaining work will be fine.
If you do need complete accuracy, then you need some automation. Provided
your timesheet has the unique ID of each task, then a VBA macro to update
your schedules automatically is relatively easy for a good VBA programmer.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"Robin Roe" wrote in message
news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
> Prashanth
>
> I am having the exact same problem which I haven't fully resolved.
> As Rod previously mentioned, all it seems you can do is enter the actual
> work in the time phased sheet, which I agree with. But like you I don't
> want
> to enter time on a daily basis for all resources. I would rather just
> enter
> the total actual work for each resource. One way I have reduced the number
> of
> inputs is to actually change the timescale on the right to say months or
> years. So rather than entering actual hours per day, you enter it per
> year,
> this will spread the single input evenly over the duration of the task. (I
> enter the actual Start and actual Finish dates first and then the actual
> time). Of course if the task spans two calendar years, you need two
> inputs.
>
> I have also played around with the "Updating task status updates resource
> status" (under Tools/Options/Calculations), but this only seems to work as
> long as the task is not 100% complete.
>
> Would be very interested to know if you find a proper solution.
>
> --
> Robin
>
>
> "Hemmige S Prashanth" wrote:
>
>> Hello Rod,
>>
>> Superb! It worked! Thanks so much! I did what you said and found that the
>> actual went to 125%.
>>
>> However, is there still a way for MPP to automatically do it? The
>> resource
>> usage view takes lot of time to update. I have 30 people on my team and
>> it is
>> quite difficult to keep changing data on a 'day' basis.
>>
>> Thanks again!
>>
>> Prashanth
>>
>>
>> "Rod Gill" wrote:
>>
>> > Hi,
>> >
>> > Simplest is to select the Resource Usage View
>> >
>> > Right click the yellow timephased area and select Actual Work. Now
>> > enter
>> > actual hours as entered into the timesheet. If you have 10h per day,
>> > then
>> > there will be no work left for Friday and an actual finish date of
>> > Thursday
>> > evening.
>> >
>> > --
>> >
>> > Rod Gill
>> > Microsoft MVP for Project
>> >
>> > Author of the only book on Project VBA, see:
>> > http://www.projectvbabook.com
>> >
>> >
>> >
>> > wrote in message
>> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
>> > > Dear MPP users,
>> > >
>> > > I need one help. I use MPP 2003.
>> > >
>> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
>> > > spanning Monday through Friday. This task has a resource 'R'
>> > > allocated. 'R' is supposed to spend 8 hours every day.
>> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
>> > > find from his timesheet, that he has over stayed and completed the
>> > > task in 4 days.
>> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
>> > > 'Actual Finish' and say that the task finished on Thursday as against
>> > > a planned finish of Friday.
>> > > 4. At this point I would expect MPP to change the units on 'R' to
>> > > indicate that, in reality, 'R' was overloaded and spent effort
>> > > equivalent to 125% units (as against planned 100% units planned).
>> > >
>> > > Issue: (4) above does not work. When I enter the actual finish as
>> > > Thursday, then the MPP will go and change the 'Actual Work' to what
>> > > is
>> > > thinks is possible in 4 days. Since I want the actual work to be
>> > > accurate, I'm forced to live with a situation where the actual finish
>> > > is incorrect. How do I resolve this situation?
>> > >
>> > > Thanks in advance.
>> > >
>> > > Prashanth
>> > > Bangalore, India
>> >
>> >
date: Thu, 10 Jul 2008 10:01:21 +1200
author: Rod Gill rodATproject-systemsDOTcoDOTnz
Re: Having MPP calculate units based on actual finish dates
Hello Rod,
You are right. I only need accuracy on a 'week' basis (i.e. I only need to
understand that a task was completed / started in a particular week - the
exact day may not be needed), so that should help a little.
However, I think I should explore the automation. We do have unique IDs in
the timesheets so we should be able to plug that into the MPP in the
Timephased view.
Thanks so much Rod!
Robin, thanks for your inputs too! I did not know about the "Updating task
status updates resource status" option.
Thanks,
Prashanth
"Rod Gill" wrote:
> Hi,
>
> Firstly you have to decide how accurately you need to report progress. If
> this is by month, then you don't need to worry about a day here or there.
> Make sure you update the actual start date for tasks and then updating
> actual work and remaining work will be fine.
>
> If you do need complete accuracy, then you need some automation. Provided
> your timesheet has the unique ID of each task, then a VBA macro to update
> your schedules automatically is relatively easy for a good VBA programmer.
>
> --
>
> Rod Gill
> Microsoft MVP for Project
>
> Author of the only book on Project VBA, see:
> http://www.projectvbabook.com
>
>
>
> "Robin Roe" wrote in message
> news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
> > Prashanth
> >
> > I am having the exact same problem which I haven't fully resolved.
> > As Rod previously mentioned, all it seems you can do is enter the actual
> > work in the time phased sheet, which I agree with. But like you I don't
> > want
> > to enter time on a daily basis for all resources. I would rather just
> > enter
> > the total actual work for each resource. One way I have reduced the number
> > of
> > inputs is to actually change the timescale on the right to say months or
> > years. So rather than entering actual hours per day, you enter it per
> > year,
> > this will spread the single input evenly over the duration of the task. (I
> > enter the actual Start and actual Finish dates first and then the actual
> > time). Of course if the task spans two calendar years, you need two
> > inputs.
> >
> > I have also played around with the "Updating task status updates resource
> > status" (under Tools/Options/Calculations), but this only seems to work as
> > long as the task is not 100% complete.
> >
> > Would be very interested to know if you find a proper solution.
> >
> > --
> > Robin
> >
> >
> > "Hemmige S Prashanth" wrote:
> >
> >> Hello Rod,
> >>
> >> Superb! It worked! Thanks so much! I did what you said and found that the
> >> actual went to 125%.
> >>
> >> However, is there still a way for MPP to automatically do it? The
> >> resource
> >> usage view takes lot of time to update. I have 30 people on my team and
> >> it is
> >> quite difficult to keep changing data on a 'day' basis.
> >>
> >> Thanks again!
> >>
> >> Prashanth
> >>
> >>
> >> "Rod Gill" wrote:
> >>
> >> > Hi,
> >> >
> >> > Simplest is to select the Resource Usage View
> >> >
> >> > Right click the yellow timephased area and select Actual Work. Now
> >> > enter
> >> > actual hours as entered into the timesheet. If you have 10h per day,
> >> > then
> >> > there will be no work left for Friday and an actual finish date of
> >> > Thursday
> >> > evening.
> >> >
> >> > --
> >> >
> >> > Rod Gill
> >> > Microsoft MVP for Project
> >> >
> >> > Author of the only book on Project VBA, see:
> >> > http://www.projectvbabook.com
> >> >
> >> >
> >> >
> >> > wrote in message
> >> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> >> > > Dear MPP users,
> >> > >
> >> > > I need one help. I use MPP 2003.
> >> > >
> >> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
> >> > > spanning Monday through Friday. This task has a resource 'R'
> >> > > allocated. 'R' is supposed to spend 8 hours every day.
> >> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> >> > > find from his timesheet, that he has over stayed and completed the
> >> > > task in 4 days.
> >> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> >> > > 'Actual Finish' and say that the task finished on Thursday as against
> >> > > a planned finish of Friday.
> >> > > 4. At this point I would expect MPP to change the units on 'R' to
> >> > > indicate that, in reality, 'R' was overloaded and spent effort
> >> > > equivalent to 125% units (as against planned 100% units planned).
> >> > >
> >> > > Issue: (4) above does not work. When I enter the actual finish as
> >> > > Thursday, then the MPP will go and change the 'Actual Work' to what
> >> > > is
> >> > > thinks is possible in 4 days. Since I want the actual work to be
> >> > > accurate, I'm forced to live with a situation where the actual finish
> >> > > is incorrect. How do I resolve this situation?
> >> > >
> >> > > Thanks in advance.
> >> > >
> >> > > Prashanth
> >> > > Bangalore, India
> >> >
> >> >
>
>
date: Wed, 9 Jul 2008 21:21:00 -0700
author: Hemmige S Prashanth
Re: Having MPP calculate units based on actual finish dates
Good luck and let me know if you need help with a macro to update your
projects.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"Hemmige S Prashanth" wrote in
message news:A035C760-987C-4B56-9034-2B505D211818@microsoft.com...
> Hello Rod,
>
> You are right. I only need accuracy on a 'week' basis (i.e. I only need to
> understand that a task was completed / started in a particular week - the
> exact day may not be needed), so that should help a little.
>
> However, I think I should explore the automation. We do have unique IDs in
> the timesheets so we should be able to plug that into the MPP in the
> Timephased view.
>
> Thanks so much Rod!
>
> Robin, thanks for your inputs too! I did not know about the "Updating task
> status updates resource status" option.
>
> Thanks,
> Prashanth
>
> "Rod Gill" wrote:
>
>> Hi,
>>
>> Firstly you have to decide how accurately you need to report progress. If
>> this is by month, then you don't need to worry about a day here or there.
>> Make sure you update the actual start date for tasks and then updating
>> actual work and remaining work will be fine.
>>
>> If you do need complete accuracy, then you need some automation. Provided
>> your timesheet has the unique ID of each task, then a VBA macro to update
>> your schedules automatically is relatively easy for a good VBA
>> programmer.
>>
>> --
>>
>> Rod Gill
>> Microsoft MVP for Project
>>
>> Author of the only book on Project VBA, see:
>> http://www.projectvbabook.com
>>
>>
>>
>> "Robin Roe" wrote in message
>> news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
>> > Prashanth
>> >
>> > I am having the exact same problem which I haven't fully resolved.
>> > As Rod previously mentioned, all it seems you can do is enter the
>> > actual
>> > work in the time phased sheet, which I agree with. But like you I don't
>> > want
>> > to enter time on a daily basis for all resources. I would rather just
>> > enter
>> > the total actual work for each resource. One way I have reduced the
>> > number
>> > of
>> > inputs is to actually change the timescale on the right to say months
>> > or
>> > years. So rather than entering actual hours per day, you enter it per
>> > year,
>> > this will spread the single input evenly over the duration of the task.
>> > (I
>> > enter the actual Start and actual Finish dates first and then the
>> > actual
>> > time). Of course if the task spans two calendar years, you need two
>> > inputs.
>> >
>> > I have also played around with the "Updating task status updates
>> > resource
>> > status" (under Tools/Options/Calculations), but this only seems to work
>> > as
>> > long as the task is not 100% complete.
>> >
>> > Would be very interested to know if you find a proper solution.
>> >
>> > --
>> > Robin
>> >
>> >
>> > "Hemmige S Prashanth" wrote:
>> >
>> >> Hello Rod,
>> >>
>> >> Superb! It worked! Thanks so much! I did what you said and found that
>> >> the
>> >> actual went to 125%.
>> >>
>> >> However, is there still a way for MPP to automatically do it? The
>> >> resource
>> >> usage view takes lot of time to update. I have 30 people on my team
>> >> and
>> >> it is
>> >> quite difficult to keep changing data on a 'day' basis.
>> >>
>> >> Thanks again!
>> >>
>> >> Prashanth
>> >>
>> >>
>> >> "Rod Gill" wrote:
>> >>
>> >> > Hi,
>> >> >
>> >> > Simplest is to select the Resource Usage View
>> >> >
>> >> > Right click the yellow timephased area and select Actual Work. Now
>> >> > enter
>> >> > actual hours as entered into the timesheet. If you have 10h per day,
>> >> > then
>> >> > there will be no work left for Friday and an actual finish date of
>> >> > Thursday
>> >> > evening.
>> >> >
>> >> > --
>> >> >
>> >> > Rod Gill
>> >> > Microsoft MVP for Project
>> >> >
>> >> > Author of the only book on Project VBA, see:
>> >> > http://www.projectvbabook.com
>> >> >
>> >> >
>> >> >
>> >> > wrote in message
>> >> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
>> >> > > Dear MPP users,
>> >> > >
>> >> > > I need one help. I use MPP 2003.
>> >> > >
>> >> > > 1. Let us say, I have a task A that has a planned work of 40
>> >> > > hours,
>> >> > > spanning Monday through Friday. This task has a resource 'R'
>> >> > > allocated. 'R' is supposed to spend 8 hours every day.
>> >> > > 2. Now, on the 'next' Monday, when I want to take status from 'R',
>> >> > > I
>> >> > > find from his timesheet, that he has over stayed and completed the
>> >> > > task in 4 days.
>> >> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to
>> >> > > the
>> >> > > 'Actual Finish' and say that the task finished on Thursday as
>> >> > > against
>> >> > > a planned finish of Friday.
>> >> > > 4. At this point I would expect MPP to change the units on 'R' to
>> >> > > indicate that, in reality, 'R' was overloaded and spent effort
>> >> > > equivalent to 125% units (as against planned 100% units planned).
>> >> > >
>> >> > > Issue: (4) above does not work. When I enter the actual finish as
>> >> > > Thursday, then the MPP will go and change the 'Actual Work' to
>> >> > > what
>> >> > > is
>> >> > > thinks is possible in 4 days. Since I want the actual work to be
>> >> > > accurate, I'm forced to live with a situation where the actual
>> >> > > finish
>> >> > > is incorrect. How do I resolve this situation?
>> >> > >
>> >> > > Thanks in advance.
>> >> > >
>> >> > > Prashanth
>> >> > > Bangalore, India
>> >> >
>> >> >
>>
>>
date: Thu, 10 Jul 2008 17:02:36 +1200
author: Rod Gill rodATproject-systemsDOTcoDOTnz
|
|