Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 9 Jul 2008 00:23:26 -0700 (PDT),    group: microsoft.public.project.developer        back       


Having MPP calculate units based on actual finish dates   
Dear MPP users,

I need one help. I use MPP 2003.

1. Let us say, I have a task A that has a planned work of 40 hours,
spanning Monday through Friday. This task has a resource 'R'
allocated. 'R' is supposed to spend 8 hours every day.
2. Now, on the 'next' Monday, when I want to take status from 'R', I
find from his timesheet, that he has over stayed and completed the
task in 4 days.
3. I now go to the 'Actual Work' column, enter 40, and then go to the
'Actual Finish' and say that the task finished on Thursday as against
a planned finish of Friday.
4. At this point I would expect MPP to change the units on 'R' to
indicate that, in reality, 'R' was overloaded and spent effort
equivalent to 125% units (as against planned 100% units planned).

Issue: (4) above does not work. When I enter the actual finish as
Thursday, then the MPP will go and change the 'Actual Work' to what is
thinks is possible in 4 days. Since I want the actual work to be
accurate, I'm forced to live with a situation where the actual finish
is incorrect. How do I resolve this situation?

Thanks in advance.

Prashanth
Bangalore, India
date: Wed, 9 Jul 2008 00:23:26 -0700 (PDT)   author:   unknown

Re: Having MPP calculate units based on actual finish dates   
Hi,

Simplest is to select the Resource Usage View

Right click the yellow timephased area and select Actual Work. Now enter 
actual hours as entered into the timesheet. If you have 10h per day, then 
there will be no work left for Friday and an actual finish date of Thursday 
evening.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



 wrote in message 
news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> Dear MPP users,
>
> I need one help. I use MPP 2003.
>
> 1. Let us say, I have a task A that has a planned work of 40 hours,
> spanning Monday through Friday. This task has a resource 'R'
> allocated. 'R' is supposed to spend 8 hours every day.
> 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> find from his timesheet, that he has over stayed and completed the
> task in 4 days.
> 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> 'Actual Finish' and say that the task finished on Thursday as against
> a planned finish of Friday.
> 4. At this point I would expect MPP to change the units on 'R' to
> indicate that, in reality, 'R' was overloaded and spent effort
> equivalent to 125% units (as against planned 100% units planned).
>
> Issue: (4) above does not work. When I enter the actual finish as
> Thursday, then the MPP will go and change the 'Actual Work' to what is
> thinks is possible in 4 days. Since I want the actual work to be
> accurate, I'm forced to live with a situation where the actual finish
> is incorrect. How do I resolve this situation?
>
> Thanks in advance.
>
> Prashanth
> Bangalore, India
date: Wed, 9 Jul 2008 21:41:18 +1200   author:   Rod Gill rodATproject-systemsDOTcoDOTnz

Re: Having MPP calculate units based on actual finish dates   
Hello Rod,

Superb! It worked! Thanks so much! I did what you said and found that the 
actual went to 125%.

However, is there still a way for MPP to automatically do it? The resource 
usage view takes lot of time to update. I have 30 people on my team and it is 
quite difficult to keep changing data on a 'day' basis.

Thanks again!

Prashanth


"Rod Gill" wrote:

> Hi,
> 
> Simplest is to select the Resource Usage View
> 
> Right click the yellow timephased area and select Actual Work. Now enter 
> actual hours as entered into the timesheet. If you have 10h per day, then 
> there will be no work left for Friday and an actual finish date of Thursday 
> evening.
> 
> -- 
> 
> Rod Gill
> Microsoft MVP for Project
> 
> Author of the only book on Project VBA, see:
> http://www.projectvbabook.com
> 
> 
> 
>  wrote in message 
> news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> > Dear MPP users,
> >
> > I need one help. I use MPP 2003.
> >
> > 1. Let us say, I have a task A that has a planned work of 40 hours,
> > spanning Monday through Friday. This task has a resource 'R'
> > allocated. 'R' is supposed to spend 8 hours every day.
> > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> > find from his timesheet, that he has over stayed and completed the
> > task in 4 days.
> > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> > 'Actual Finish' and say that the task finished on Thursday as against
> > a planned finish of Friday.
> > 4. At this point I would expect MPP to change the units on 'R' to
> > indicate that, in reality, 'R' was overloaded and spent effort
> > equivalent to 125% units (as against planned 100% units planned).
> >
> > Issue: (4) above does not work. When I enter the actual finish as
> > Thursday, then the MPP will go and change the 'Actual Work' to what is
> > thinks is possible in 4 days. Since I want the actual work to be
> > accurate, I'm forced to live with a situation where the actual finish
> > is incorrect. How do I resolve this situation?
> >
> > Thanks in advance.
> >
> > Prashanth
> > Bangalore, India 
> 
>
date: Wed, 9 Jul 2008 03:53:00 -0700   author:   Hemmige S Prashanth

Re: Having MPP calculate units based on actual finish dates   
Prashanth

I am having the exact same problem which I haven't fully resolved. 
As Rod previously mentioned, all it seems you can do is enter the actual 
work in the time phased sheet, which I agree with. But like you I don't want 
to enter time on a daily basis for all resources. I would rather just enter 
the total actual work for each resource. One way I have reduced the number of 
inputs is to actually change the timescale on the right to say months or 
years. So rather than entering actual hours per day, you enter it per year, 
this will spread the single input evenly over the duration of the task. (I 
enter the actual Start and actual Finish dates first and then the actual 
time). Of course if the task spans two calendar years, you need two inputs.

I have also played around with the "Updating task status updates resource 
status" (under Tools/Options/Calculations), but this only seems to work as 
long as the task is not 100% complete.

Would be very interested to know if you find a proper solution.

-- 
Robin


"Hemmige S Prashanth" wrote:

> Hello Rod,
> 
> Superb! It worked! Thanks so much! I did what you said and found that the 
> actual went to 125%.
> 
> However, is there still a way for MPP to automatically do it? The resource 
> usage view takes lot of time to update. I have 30 people on my team and it is 
> quite difficult to keep changing data on a 'day' basis.
> 
> Thanks again!
> 
> Prashanth
> 
> 
> "Rod Gill" wrote:
> 
> > Hi,
> > 
> > Simplest is to select the Resource Usage View
> > 
> > Right click the yellow timephased area and select Actual Work. Now enter 
> > actual hours as entered into the timesheet. If you have 10h per day, then 
> > there will be no work left for Friday and an actual finish date of Thursday 
> > evening.
> > 
> > -- 
> > 
> > Rod Gill
> > Microsoft MVP for Project
> > 
> > Author of the only book on Project VBA, see:
> > http://www.projectvbabook.com
> > 
> > 
> > 
> >  wrote in message 
> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> > > Dear MPP users,
> > >
> > > I need one help. I use MPP 2003.
> > >
> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
> > > spanning Monday through Friday. This task has a resource 'R'
> > > allocated. 'R' is supposed to spend 8 hours every day.
> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> > > find from his timesheet, that he has over stayed and completed the
> > > task in 4 days.
> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> > > 'Actual Finish' and say that the task finished on Thursday as against
> > > a planned finish of Friday.
> > > 4. At this point I would expect MPP to change the units on 'R' to
> > > indicate that, in reality, 'R' was overloaded and spent effort
> > > equivalent to 125% units (as against planned 100% units planned).
> > >
> > > Issue: (4) above does not work. When I enter the actual finish as
> > > Thursday, then the MPP will go and change the 'Actual Work' to what is
> > > thinks is possible in 4 days. Since I want the actual work to be
> > > accurate, I'm forced to live with a situation where the actual finish
> > > is incorrect. How do I resolve this situation?
> > >
> > > Thanks in advance.
> > >
> > > Prashanth
> > > Bangalore, India 
> > 
> >
date: Wed, 9 Jul 2008 07:46:01 -0700   author:   Robin Roe

Re: Having MPP calculate units based on actual finish dates   
Hi,

Firstly you have to decide how accurately you need to report progress. If 
this is by month, then you don't need to worry about a day here or there. 
Make sure you update the actual start date for tasks and then updating 
actual work and remaining work will be fine.

If you do need complete accuracy, then you need some automation. Provided 
your timesheet has the unique ID of each task, then a VBA macro to update 
your schedules automatically is relatively easy for a good VBA programmer.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"Robin Roe"  wrote in message 
news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
> Prashanth
>
> I am having the exact same problem which I haven't fully resolved.
> As Rod previously mentioned, all it seems you can do is enter the actual
> work in the time phased sheet, which I agree with. But like you I don't 
> want
> to enter time on a daily basis for all resources. I would rather just 
> enter
> the total actual work for each resource. One way I have reduced the number 
> of
> inputs is to actually change the timescale on the right to say months or
> years. So rather than entering actual hours per day, you enter it per 
> year,
> this will spread the single input evenly over the duration of the task. (I
> enter the actual Start and actual Finish dates first and then the actual
> time). Of course if the task spans two calendar years, you need two 
> inputs.
>
> I have also played around with the "Updating task status updates resource
> status" (under Tools/Options/Calculations), but this only seems to work as
> long as the task is not 100% complete.
>
> Would be very interested to know if you find a proper solution.
>
> -- 
> Robin
>
>
> "Hemmige S Prashanth" wrote:
>
>> Hello Rod,
>>
>> Superb! It worked! Thanks so much! I did what you said and found that the
>> actual went to 125%.
>>
>> However, is there still a way for MPP to automatically do it? The 
>> resource
>> usage view takes lot of time to update. I have 30 people on my team and 
>> it is
>> quite difficult to keep changing data on a 'day' basis.
>>
>> Thanks again!
>>
>> Prashanth
>>
>>
>> "Rod Gill" wrote:
>>
>> > Hi,
>> >
>> > Simplest is to select the Resource Usage View
>> >
>> > Right click the yellow timephased area and select Actual Work. Now 
>> > enter
>> > actual hours as entered into the timesheet. If you have 10h per day, 
>> > then
>> > there will be no work left for Friday and an actual finish date of 
>> > Thursday
>> > evening.
>> >
>> > -- 
>> >
>> > Rod Gill
>> > Microsoft MVP for Project
>> >
>> > Author of the only book on Project VBA, see:
>> > http://www.projectvbabook.com
>> >
>> >
>> >
>> >  wrote in message
>> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
>> > > Dear MPP users,
>> > >
>> > > I need one help. I use MPP 2003.
>> > >
>> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
>> > > spanning Monday through Friday. This task has a resource 'R'
>> > > allocated. 'R' is supposed to spend 8 hours every day.
>> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
>> > > find from his timesheet, that he has over stayed and completed the
>> > > task in 4 days.
>> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
>> > > 'Actual Finish' and say that the task finished on Thursday as against
>> > > a planned finish of Friday.
>> > > 4. At this point I would expect MPP to change the units on 'R' to
>> > > indicate that, in reality, 'R' was overloaded and spent effort
>> > > equivalent to 125% units (as against planned 100% units planned).
>> > >
>> > > Issue: (4) above does not work. When I enter the actual finish as
>> > > Thursday, then the MPP will go and change the 'Actual Work' to what 
>> > > is
>> > > thinks is possible in 4 days. Since I want the actual work to be
>> > > accurate, I'm forced to live with a situation where the actual finish
>> > > is incorrect. How do I resolve this situation?
>> > >
>> > > Thanks in advance.
>> > >
>> > > Prashanth
>> > > Bangalore, India
>> >
>> >
date: Thu, 10 Jul 2008 10:01:21 +1200   author:   Rod Gill rodATproject-systemsDOTcoDOTnz

Re: Having MPP calculate units based on actual finish dates   
Hello Rod,

You are right. I only need accuracy on a 'week' basis (i.e. I only need to 
understand that a task was completed / started in a particular week - the 
exact day may not be needed), so that should help a little.

However, I think I should explore the automation. We do have unique IDs in 
the timesheets so we should be able to plug that into the MPP in the 
Timephased view.

Thanks so much Rod!

Robin, thanks for your inputs too! I did not know about the "Updating task 
status updates resource status" option.

Thanks,
Prashanth

"Rod Gill" wrote:

> Hi,
> 
> Firstly you have to decide how accurately you need to report progress. If 
> this is by month, then you don't need to worry about a day here or there. 
> Make sure you update the actual start date for tasks and then updating 
> actual work and remaining work will be fine.
> 
> If you do need complete accuracy, then you need some automation. Provided 
> your timesheet has the unique ID of each task, then a VBA macro to update 
> your schedules automatically is relatively easy for a good VBA programmer.
> 
> -- 
> 
> Rod Gill
> Microsoft MVP for Project
> 
> Author of the only book on Project VBA, see:
> http://www.projectvbabook.com
> 
> 
> 
> "Robin Roe"  wrote in message 
> news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
> > Prashanth
> >
> > I am having the exact same problem which I haven't fully resolved.
> > As Rod previously mentioned, all it seems you can do is enter the actual
> > work in the time phased sheet, which I agree with. But like you I don't 
> > want
> > to enter time on a daily basis for all resources. I would rather just 
> > enter
> > the total actual work for each resource. One way I have reduced the number 
> > of
> > inputs is to actually change the timescale on the right to say months or
> > years. So rather than entering actual hours per day, you enter it per 
> > year,
> > this will spread the single input evenly over the duration of the task. (I
> > enter the actual Start and actual Finish dates first and then the actual
> > time). Of course if the task spans two calendar years, you need two 
> > inputs.
> >
> > I have also played around with the "Updating task status updates resource
> > status" (under Tools/Options/Calculations), but this only seems to work as
> > long as the task is not 100% complete.
> >
> > Would be very interested to know if you find a proper solution.
> >
> > -- 
> > Robin
> >
> >
> > "Hemmige S Prashanth" wrote:
> >
> >> Hello Rod,
> >>
> >> Superb! It worked! Thanks so much! I did what you said and found that the
> >> actual went to 125%.
> >>
> >> However, is there still a way for MPP to automatically do it? The 
> >> resource
> >> usage view takes lot of time to update. I have 30 people on my team and 
> >> it is
> >> quite difficult to keep changing data on a 'day' basis.
> >>
> >> Thanks again!
> >>
> >> Prashanth
> >>
> >>
> >> "Rod Gill" wrote:
> >>
> >> > Hi,
> >> >
> >> > Simplest is to select the Resource Usage View
> >> >
> >> > Right click the yellow timephased area and select Actual Work. Now 
> >> > enter
> >> > actual hours as entered into the timesheet. If you have 10h per day, 
> >> > then
> >> > there will be no work left for Friday and an actual finish date of 
> >> > Thursday
> >> > evening.
> >> >
> >> > -- 
> >> >
> >> > Rod Gill
> >> > Microsoft MVP for Project
> >> >
> >> > Author of the only book on Project VBA, see:
> >> > http://www.projectvbabook.com
> >> >
> >> >
> >> >
> >> >  wrote in message
> >> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
> >> > > Dear MPP users,
> >> > >
> >> > > I need one help. I use MPP 2003.
> >> > >
> >> > > 1. Let us say, I have a task A that has a planned work of 40 hours,
> >> > > spanning Monday through Friday. This task has a resource 'R'
> >> > > allocated. 'R' is supposed to spend 8 hours every day.
> >> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', I
> >> > > find from his timesheet, that he has over stayed and completed the
> >> > > task in 4 days.
> >> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to the
> >> > > 'Actual Finish' and say that the task finished on Thursday as against
> >> > > a planned finish of Friday.
> >> > > 4. At this point I would expect MPP to change the units on 'R' to
> >> > > indicate that, in reality, 'R' was overloaded and spent effort
> >> > > equivalent to 125% units (as against planned 100% units planned).
> >> > >
> >> > > Issue: (4) above does not work. When I enter the actual finish as
> >> > > Thursday, then the MPP will go and change the 'Actual Work' to what 
> >> > > is
> >> > > thinks is possible in 4 days. Since I want the actual work to be
> >> > > accurate, I'm forced to live with a situation where the actual finish
> >> > > is incorrect. How do I resolve this situation?
> >> > >
> >> > > Thanks in advance.
> >> > >
> >> > > Prashanth
> >> > > Bangalore, India
> >> >
> >> > 
> 
>
date: Wed, 9 Jul 2008 21:21:00 -0700   author:   Hemmige S Prashanth

Re: Having MPP calculate units based on actual finish dates   
Good luck and let me know if you need help with a macro to update your 
projects.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"Hemmige S Prashanth"  wrote in 
message news:A035C760-987C-4B56-9034-2B505D211818@microsoft.com...
> Hello Rod,
>
> You are right. I only need accuracy on a 'week' basis (i.e. I only need to
> understand that a task was completed / started in a particular week - the
> exact day may not be needed), so that should help a little.
>
> However, I think I should explore the automation. We do have unique IDs in
> the timesheets so we should be able to plug that into the MPP in the
> Timephased view.
>
> Thanks so much Rod!
>
> Robin, thanks for your inputs too! I did not know about the "Updating task
> status updates resource status" option.
>
> Thanks,
> Prashanth
>
> "Rod Gill" wrote:
>
>> Hi,
>>
>> Firstly you have to decide how accurately you need to report progress. If
>> this is by month, then you don't need to worry about a day here or there.
>> Make sure you update the actual start date for tasks and then updating
>> actual work and remaining work will be fine.
>>
>> If you do need complete accuracy, then you need some automation. Provided
>> your timesheet has the unique ID of each task, then a VBA macro to update
>> your schedules automatically is relatively easy for a good VBA 
>> programmer.
>>
>> -- 
>>
>> Rod Gill
>> Microsoft MVP for Project
>>
>> Author of the only book on Project VBA, see:
>> http://www.projectvbabook.com
>>
>>
>>
>> "Robin Roe"  wrote in message
>> news:E2063403-F103-4809-9126-DA89D0FD9F15@microsoft.com...
>> > Prashanth
>> >
>> > I am having the exact same problem which I haven't fully resolved.
>> > As Rod previously mentioned, all it seems you can do is enter the 
>> > actual
>> > work in the time phased sheet, which I agree with. But like you I don't
>> > want
>> > to enter time on a daily basis for all resources. I would rather just
>> > enter
>> > the total actual work for each resource. One way I have reduced the 
>> > number
>> > of
>> > inputs is to actually change the timescale on the right to say months 
>> > or
>> > years. So rather than entering actual hours per day, you enter it per
>> > year,
>> > this will spread the single input evenly over the duration of the task. 
>> > (I
>> > enter the actual Start and actual Finish dates first and then the 
>> > actual
>> > time). Of course if the task spans two calendar years, you need two
>> > inputs.
>> >
>> > I have also played around with the "Updating task status updates 
>> > resource
>> > status" (under Tools/Options/Calculations), but this only seems to work 
>> > as
>> > long as the task is not 100% complete.
>> >
>> > Would be very interested to know if you find a proper solution.
>> >
>> > -- 
>> > Robin
>> >
>> >
>> > "Hemmige S Prashanth" wrote:
>> >
>> >> Hello Rod,
>> >>
>> >> Superb! It worked! Thanks so much! I did what you said and found that 
>> >> the
>> >> actual went to 125%.
>> >>
>> >> However, is there still a way for MPP to automatically do it? The
>> >> resource
>> >> usage view takes lot of time to update. I have 30 people on my team 
>> >> and
>> >> it is
>> >> quite difficult to keep changing data on a 'day' basis.
>> >>
>> >> Thanks again!
>> >>
>> >> Prashanth
>> >>
>> >>
>> >> "Rod Gill" wrote:
>> >>
>> >> > Hi,
>> >> >
>> >> > Simplest is to select the Resource Usage View
>> >> >
>> >> > Right click the yellow timephased area and select Actual Work. Now
>> >> > enter
>> >> > actual hours as entered into the timesheet. If you have 10h per day,
>> >> > then
>> >> > there will be no work left for Friday and an actual finish date of
>> >> > Thursday
>> >> > evening.
>> >> >
>> >> > -- 
>> >> >
>> >> > Rod Gill
>> >> > Microsoft MVP for Project
>> >> >
>> >> > Author of the only book on Project VBA, see:
>> >> > http://www.projectvbabook.com
>> >> >
>> >> >
>> >> >
>> >> >  wrote in message
>> >> > news:758edb6c-fb43-4f17-a79d-03b78a59c036@e53g2000hsa.googlegroups.com...
>> >> > > Dear MPP users,
>> >> > >
>> >> > > I need one help. I use MPP 2003.
>> >> > >
>> >> > > 1. Let us say, I have a task A that has a planned work of 40 
>> >> > > hours,
>> >> > > spanning Monday through Friday. This task has a resource 'R'
>> >> > > allocated. 'R' is supposed to spend 8 hours every day.
>> >> > > 2. Now, on the 'next' Monday, when I want to take status from 'R', 
>> >> > > I
>> >> > > find from his timesheet, that he has over stayed and completed the
>> >> > > task in 4 days.
>> >> > > 3. I now go to the 'Actual Work' column, enter 40, and then go to 
>> >> > > the
>> >> > > 'Actual Finish' and say that the task finished on Thursday as 
>> >> > > against
>> >> > > a planned finish of Friday.
>> >> > > 4. At this point I would expect MPP to change the units on 'R' to
>> >> > > indicate that, in reality, 'R' was overloaded and spent effort
>> >> > > equivalent to 125% units (as against planned 100% units planned).
>> >> > >
>> >> > > Issue: (4) above does not work. When I enter the actual finish as
>> >> > > Thursday, then the MPP will go and change the 'Actual Work' to 
>> >> > > what
>> >> > > is
>> >> > > thinks is possible in 4 days. Since I want the actual work to be
>> >> > > accurate, I'm forced to live with a situation where the actual 
>> >> > > finish
>> >> > > is incorrect. How do I resolve this situation?
>> >> > >
>> >> > > Thanks in advance.
>> >> > >
>> >> > > Prashanth
>> >> > > Bangalore, India
>> >> >
>> >> >
>>
>>
date: Thu, 10 Jul 2008 17:02:36 +1200   author:   Rod Gill rodATproject-systemsDOTcoDOTnz

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us