Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 8 Oct 2008 12:16:21 -0700,    group: microsoft.public.project        back       


Fully Allocate a Resource   
Hi,

I'm working in Project 2003 and I'm having an issue where it won't fully 
allocate a resource who is assigned to a task at 100%.  This is happening in 
several instances where it only assigns someone for say 2 hrs per day 
(instead of 8).  Again they are 100% on the task and I can't find a valid 
reason for this.  I am using leveling as well on a Minute by Minute basis.

Any ideas?

-- 
Vic
date: Wed, 8 Oct 2008 12:16:21 -0700   author:   Vic

Re: Fully Allocate a Resource   
Vic,

Are you sure that somebody did not enter a Work value for these tasks?
For example 20h of Work on a task, the Duration of which is 10d.
If you click Assign for a resource, Project calculate Units = 0.25 and the 
work for each day is 2h.

Gérard Ducouret

"Vic"  a écrit dans le message de news: 
E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
> Hi,
>
> I'm working in Project 2003 and I'm having an issue where it won't fully
> allocate a resource who is assigned to a task at 100%.  This is happening 
> in
> several instances where it only assigns someone for say 2 hrs per day
> (instead of 8).  Again they are 100% on the task and I can't find a valid
> reason for this.  I am using leveling as well on a Minute by Minute basis.
>
> Any ideas?
>
> -- 
> Vic
date: Wed, 8 Oct 2008 22:02:38 +0200   author:   G?rard Ducouret

Re: Fully Allocate a Resource   
Yes, I've been entering work values based on how much they've worked on a 
task.  That seems to be the tasks this happens with.  So you're definitely on 
to something :).  Thanks.

What should I be doing different or how can I adjust so it schedules the 
remaining hours appropriately (ie. 8 hours per day)? 


-- 
Vic


"Gérard Ducouret" wrote:

> Vic,
> 
> Are you sure that somebody did not enter a Work value for these tasks?
> For example 20h of Work on a task, the Duration of which is 10d.
> If you click Assign for a resource, Project calculate Units = 0.25 and the 
> work for each day is 2h.
> 
> Gérard Ducouret
> 
> "Vic"  a écrit dans le message de news: 
> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
> > Hi,
> >
> > I'm working in Project 2003 and I'm having an issue where it won't fully
> > allocate a resource who is assigned to a task at 100%.  This is happening 
> > in
> > several instances where it only assigns someone for say 2 hrs per day
> > (instead of 8).  Again they are 100% on the task and I can't find a valid
> > reason for this.  I am using leveling as well on a Minute by Minute basis.
> >
> > Any ideas?
> >
> > -- 
> > Vic 
> 
> 
>
date: Wed, 8 Oct 2008 13:23:04 -0700   author:   Vic

Re: Fully Allocate a Resource   
Vic,

If you want to enter work values based on how much they've worked on a task, 
don't use the "Work" field but the "Actual Work" field.
Hope this helps,

Gérard Ducouret


"Vic"  a écrit dans le message de news: 
63533834-B45E-4B9D-8EBD-826FBF115C15@microsoft.com...
> Yes, I've been entering work values based on how much they've worked on a
> task.  That seems to be the tasks this happens with.  So you're definitely 
> on
> to something :).  Thanks.
>
> What should I be doing different or how can I adjust so it schedules the
> remaining hours appropriately (ie. 8 hours per day)?
>
>
> -- 
> Vic
>
>
> "Gérard Ducouret" wrote:
>
>> Vic,
>>
>> Are you sure that somebody did not enter a Work value for these tasks?
>> For example 20h of Work on a task, the Duration of which is 10d.
>> If you click Assign for a resource, Project calculate Units = 0.25 and 
>> the
>> work for each day is 2h.
>>
>> Gérard Ducouret
>>
>> "Vic"  a écrit dans le message de news:
>> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
>> > Hi,
>> >
>> > I'm working in Project 2003 and I'm having an issue where it won't 
>> > fully
>> > allocate a resource who is assigned to a task at 100%.  This is 
>> > happening
>> > in
>> > several instances where it only assigns someone for say 2 hrs per day
>> > (instead of 8).  Again they are 100% on the task and I can't find a 
>> > valid
>> > reason for this.  I am using leveling as well on a Minute by Minute 
>> > basis.
>> >
>> > Any ideas?
>> >
>> > -- 
>> > Vic
>>
>>
>>
date: Wed, 8 Oct 2008 22:31:17 +0200   author:   G?rard Ducouret

Re: Fully Allocate a Resource   
Thanks.  

Sorry, that's what I've been using, the Actual Work.  On occasion I might 
have entered something in the Work field to force a task to start earlier 
(same resource working on two tasks but Project placed them in a different 
sequence than I wanted).  

Do you think this is caused if I entered something in Work field?  Is there 
a way to correct that?


-- 
Vic


"Gérard Ducouret" wrote:

> Vic,
> 
> If you want to enter work values based on how much they've worked on a task, 
> don't use the "Work" field but the "Actual Work" field.
> Hope this helps,
> 
> Gérard Ducouret
> 
> 
> "Vic"  a écrit dans le message de news: 
> 63533834-B45E-4B9D-8EBD-826FBF115C15@microsoft.com...
> > Yes, I've been entering work values based on how much they've worked on a
> > task.  That seems to be the tasks this happens with.  So you're definitely 
> > on
> > to something :).  Thanks.
> >
> > What should I be doing different or how can I adjust so it schedules the
> > remaining hours appropriately (ie. 8 hours per day)?
> >
> >
> > -- 
> > Vic
> >
> >
> > "Gérard Ducouret" wrote:
> >
> >> Vic,
> >>
> >> Are you sure that somebody did not enter a Work value for these tasks?
> >> For example 20h of Work on a task, the Duration of which is 10d.
> >> If you click Assign for a resource, Project calculate Units = 0.25 and 
> >> the
> >> work for each day is 2h.
> >>
> >> Gérard Ducouret
> >>
> >> "Vic"  a écrit dans le message de news:
> >> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
> >> > Hi,
> >> >
> >> > I'm working in Project 2003 and I'm having an issue where it won't 
> >> > fully
> >> > allocate a resource who is assigned to a task at 100%.  This is 
> >> > happening
> >> > in
> >> > several instances where it only assigns someone for say 2 hrs per day
> >> > (instead of 8).  Again they are 100% on the task and I can't find a 
> >> > valid
> >> > reason for this.  I am using leveling as well on a Minute by Minute 
> >> > basis.
> >> >
> >> > Any ideas?
> >> >
> >> > -- 
> >> > Vic
> >>
> >>
> >> 
> 
> 
>
date: Wed, 8 Oct 2008 14:01:00 -0700   author:   Vic

Re: Fully Allocate a Resource   
Hi Vic,

Pardon me for bumping in, but what time in the day does the task 
begin?  If the task doesn't begin at the start of the working day, I 
wouldn't expect to get 8 hours of work in.

Also, you mention that you are using Resource Leveling on a minute 
by minute basis.  It's possible that in order to resolve 
overallocation that the task has been split to allow other tasks to 
be scheduled on that day.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional 
information about Microsoft Project


"Vic"  wrote in message 
news:F669607B-58BA-40D1-989D-838DB22B93E6@microsoft.com...
> Thanks.
>
> Sorry, that's what I've been using, the Actual Work.  On occasion 
> I might
> have entered something in the Work field to force a task to start 
> earlier
> (same resource working on two tasks but Project placed them in a 
> different
> sequence than I wanted).
>
> Do you think this is caused if I entered something in Work field? 
> Is there
> a way to correct that?
>
>
> -- 
> Vic
>
>
> "Gérard Ducouret" wrote:
>
>> Vic,
>>
>> If you want to enter work values based on how much they've worked 
>> on a task,
>> don't use the "Work" field but the "Actual Work" field.
>> Hope this helps,
>>
>> Gérard Ducouret
>>
>>
>> "Vic"  a écrit dans le message de 
>> news:
>> 63533834-B45E-4B9D-8EBD-826FBF115C15@microsoft.com...
>> > Yes, I've been entering work values based on how much they've 
>> > worked on a
>> > task.  That seems to be the tasks this happens with.  So you're 
>> > definitely
>> > on
>> > to something :).  Thanks.
>> >
>> > What should I be doing different or how can I adjust so it 
>> > schedules the
>> > remaining hours appropriately (ie. 8 hours per day)?
>> >
>> >
>> > -- 
>> > Vic
>> >
>> >
>> > "Gérard Ducouret" wrote:
>> >
>> >> Vic,
>> >>
>> >> Are you sure that somebody did not enter a Work value for 
>> >> these tasks?
>> >> For example 20h of Work on a task, the Duration of which is 
>> >> 10d.
>> >> If you click Assign for a resource, Project calculate Units = 
>> >> 0.25 and
>> >> the
>> >> work for each day is 2h.
>> >>
>> >> Gérard Ducouret
>> >>
>> >> "Vic"  a écrit dans le message 
>> >> de news:
>> >> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
>> >> > Hi,
>> >> >
>> >> > I'm working in Project 2003 and I'm having an issue where it 
>> >> > won't
>> >> > fully
>> >> > allocate a resource who is assigned to a task at 100%.  This 
>> >> > is
>> >> > happening
>> >> > in
>> >> > several instances where it only assigns someone for say 2 
>> >> > hrs per day
>> >> > (instead of 8).  Again they are 100% on the task and I can't 
>> >> > find a
>> >> > valid
>> >> > reason for this.  I am using leveling as well on a Minute by 
>> >> > Minute
>> >> > basis.
>> >> >
>> >> > Any ideas?
>> >> >
>> >> > -- 
>> >> > Vic
>> >>
>> >>
>> >>
>>
>>
>>
date: Fri, 10 Oct 2008 09:06:10 -0400   author:   JulieS

Re: Fully Allocate a Resource   
Hi Julie,

On the leveling I didn't allow splitting of a task.  And I'm not sure how to 
check the time of a task starting.  Please let me know on that just out of 
curiousity.  But I don't believe that is it because it's many days and many 
tasks that it happens.

I was able to resolve the problem by changing the Work Contour and 
prioritizing some tasks.  When I entered Actual Work it changed the Work 
Contour from "Flat" to "Contour" - is that normal?  So I changed them back to 
Flat and in addition to the prioritization that seemed to start scheduling 
the work so they had an 8 hour day (or at least close to it in some cases).

Hope that makes sense.  While it seems to be corrected, I would still be 
curious to know why it does that and if there's a better way to handle the 
situation.  Your help is appreciated. 


-- 
Vic


"JulieS" wrote:

> Hi Vic,
> 
> Pardon me for bumping in, but what time in the day does the task 
> begin?  If the task doesn't begin at the start of the working day, I 
> wouldn't expect to get 8 hours of work in.
> 
> Also, you mention that you are using Resource Leveling on a minute 
> by minute basis.  It's possible that in order to resolve 
> overallocation that the task has been split to allow other tasks to 
> be scheduled on that day.
> 
> I hope this helps.  Let us know how you get along.
> 
> Julie
> Project MVP
> 
> Visit http://project.mvps.org/ for the FAQs and additional 
> information about Microsoft Project
> 
> 
> "Vic"  wrote in message 
> news:F669607B-58BA-40D1-989D-838DB22B93E6@microsoft.com...
> > Thanks.
> >
> > Sorry, that's what I've been using, the Actual Work.  On occasion 
> > I might
> > have entered something in the Work field to force a task to start 
> > earlier
> > (same resource working on two tasks but Project placed them in a 
> > different
> > sequence than I wanted).
> >
> > Do you think this is caused if I entered something in Work field? 
> > Is there
> > a way to correct that?
> >
> >
> > -- 
> > Vic
> >
> >
> > "Gérard Ducouret" wrote:
> >
> >> Vic,
> >>
> >> If you want to enter work values based on how much they've worked 
> >> on a task,
> >> don't use the "Work" field but the "Actual Work" field.
> >> Hope this helps,
> >>
> >> Gérard Ducouret
> >>
> >>
> >> "Vic"  a écrit dans le message de 
> >> news:
> >> 63533834-B45E-4B9D-8EBD-826FBF115C15@microsoft.com...
> >> > Yes, I've been entering work values based on how much they've 
> >> > worked on a
> >> > task.  That seems to be the tasks this happens with.  So you're 
> >> > definitely
> >> > on
> >> > to something :).  Thanks.
> >> >
> >> > What should I be doing different or how can I adjust so it 
> >> > schedules the
> >> > remaining hours appropriately (ie. 8 hours per day)?
> >> >
> >> >
> >> > -- 
> >> > Vic
> >> >
> >> >
> >> > "Gérard Ducouret" wrote:
> >> >
> >> >> Vic,
> >> >>
> >> >> Are you sure that somebody did not enter a Work value for 
> >> >> these tasks?
> >> >> For example 20h of Work on a task, the Duration of which is 
> >> >> 10d.
> >> >> If you click Assign for a resource, Project calculate Units = 
> >> >> 0.25 and
> >> >> the
> >> >> work for each day is 2h.
> >> >>
> >> >> Gérard Ducouret
> >> >>
> >> >> "Vic"  a écrit dans le message 
> >> >> de news:
> >> >> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
> >> >> > Hi,
> >> >> >
> >> >> > I'm working in Project 2003 and I'm having an issue where it 
> >> >> > won't
> >> >> > fully
> >> >> > allocate a resource who is assigned to a task at 100%.  This 
> >> >> > is
> >> >> > happening
> >> >> > in
> >> >> > several instances where it only assigns someone for say 2 
> >> >> > hrs per day
> >> >> > (instead of 8).  Again they are 100% on the task and I can't 
> >> >> > find a
> >> >> > valid
> >> >> > reason for this.  I am using leveling as well on a Minute by 
> >> >> > Minute
> >> >> > basis.
> >> >> >
> >> >> > Any ideas?
> >> >> >
> >> >> > -- 
> >> >> > Vic
> >> >>
> >> >>
> >> >>
> >>
> >>
> >> 
> 
> 
>
date: Fri, 10 Oct 2008 19:41:00 -0700   author:   Vic

Re: Fully Allocate a Resource   
You can make project display the start time by going to tools, options 
and selecting the view tab.  In the date format you can opt to show or 
hide the time.

As a general observation, do you actually have to track what your 
resources are doing minute by minute?  That's a very fine level of 
granularity.  If you are only interested in ensuring that they get a 
number of activities done in a day then I would suggest day-by-day 
levelling or even week-by-week levelling might be more appropriate 
although your particular circumstances may dictate otherwise.

I don't understand how what you have done has resolved the problem and 
wonder whether you are expecting too much from the levelling engine.

Levelling is not an optimisation tool in that it won't adjust the work 
to fill the gaps in a resource's working day.  It actually does 
something closer to the opposite - it simply delays tasks until there 
are no overallocations in the resource's schedule.

If, after levelling, a resource is not working sufficiently many hours 
in a day then you need to manually adjust the length of that task (and 
possibly level again - you may find it useful to fix those elements of 
the plan you are happy with by setting their priority to 1000).

You shouldn't have to adjust the contour and I wouldn't worry about it. 
  By definition, unless the resource works exactly the same number of 
hours every day on a task then it is contoured.  Instead, if I wasn't 
happy with the hours that a resource had been scheduled to work then I 
would alter that either by directly entering the planned hours or by 
adjusting the length of the task, although when doing this you need to 
consider the totality of hours worked by the resource across all the 
tasks occurring on that day.

Vic wrote:
> Hi Julie,
> 
> On the leveling I didn't allow splitting of a task.  And I'm not sure how to 
> check the time of a task starting.  Please let me know on that just out of 
> curiousity.  But I don't believe that is it because it's many days and many 
> tasks that it happens.
> 
> I was able to resolve the problem by changing the Work Contour and 
> prioritizing some tasks.  When I entered Actual Work it changed the Work 
> Contour from "Flat" to "Contour" - is that normal?  So I changed them back to 
> Flat and in addition to the prioritization that seemed to start scheduling 
> the work so they had an 8 hour day (or at least close to it in some cases).
> 
> Hope that makes sense.  While it seems to be corrected, I would still be 
> curious to know why it does that and if there's a better way to handle the 
> situation.  Your help is appreciated. 
> 
>
date: Sat, 11 Oct 2008 08:06:06 +0100   author:   Dave

Re: Fully Allocate a Resource   
Hi Vic,

It looks like Dave has handled a number of your questions -- Thanks 
Dave.

Let us know if you have any additional questions.

Julie

"Vic"  wrote in message 
news:A4444D88-578D-44AE-82AC-720FE5916438@microsoft.com...
> Hi Julie,
>
> On the leveling I didn't allow splitting of a task.  And I'm not 
> sure how to
> check the time of a task starting.  Please let me know on that 
> just out of
> curiousity.  But I don't believe that is it because it's many days 
> and many
> tasks that it happens.
>
> I was able to resolve the problem by changing the Work Contour and
> prioritizing some tasks.  When I entered Actual Work it changed 
> the Work
> Contour from "Flat" to "Contour" - is that normal?  So I changed 
> them back to
> Flat and in addition to the prioritization that seemed to start 
> scheduling
> the work so they had an 8 hour day (or at least close to it in 
> some cases).
>
> Hope that makes sense.  While it seems to be corrected, I would 
> still be
> curious to know why it does that and if there's a better way to 
> handle the
> situation.  Your help is appreciated.
>
>
> -- 
> Vic
>
>
> "JulieS" wrote:
>
>> Hi Vic,
>>
>> Pardon me for bumping in, but what time in the day does the task
>> begin?  If the task doesn't begin at the start of the working 
>> day, I
>> wouldn't expect to get 8 hours of work in.
>>
>> Also, you mention that you are using Resource Leveling on a 
>> minute
>> by minute basis.  It's possible that in order to resolve
>> overallocation that the task has been split to allow other tasks 
>> to
>> be scheduled on that day.
>>
>> I hope this helps.  Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>>
>> "Vic"  wrote in message
>> news:F669607B-58BA-40D1-989D-838DB22B93E6@microsoft.com...
>> > Thanks.
>> >
>> > Sorry, that's what I've been using, the Actual Work.  On 
>> > occasion
>> > I might
>> > have entered something in the Work field to force a task to 
>> > start
>> > earlier
>> > (same resource working on two tasks but Project placed them in 
>> > a
>> > different
>> > sequence than I wanted).
>> >
>> > Do you think this is caused if I entered something in Work 
>> > field?
>> > Is there
>> > a way to correct that?
>> >
>> >
>> > -- 
>> > Vic
>> >
>> >
>> > "Gérard Ducouret" wrote:
>> >
>> >> Vic,
>> >>
>> >> If you want to enter work values based on how much they've 
>> >> worked
>> >> on a task,
>> >> don't use the "Work" field but the "Actual Work" field.
>> >> Hope this helps,
>> >>
>> >> Gérard Ducouret
>> >>
>> >>
>> >> "Vic"  a écrit dans le message 
>> >> de
>> >> news:
>> >> 63533834-B45E-4B9D-8EBD-826FBF115C15@microsoft.com...
>> >> > Yes, I've been entering work values based on how much 
>> >> > they've
>> >> > worked on a
>> >> > task.  That seems to be the tasks this happens with.  So 
>> >> > you're
>> >> > definitely
>> >> > on
>> >> > to something :).  Thanks.
>> >> >
>> >> > What should I be doing different or how can I adjust so it
>> >> > schedules the
>> >> > remaining hours appropriately (ie. 8 hours per day)?
>> >> >
>> >> >
>> >> > -- 
>> >> > Vic
>> >> >
>> >> >
>> >> > "Gérard Ducouret" wrote:
>> >> >
>> >> >> Vic,
>> >> >>
>> >> >> Are you sure that somebody did not enter a Work value for
>> >> >> these tasks?
>> >> >> For example 20h of Work on a task, the Duration of which is
>> >> >> 10d.
>> >> >> If you click Assign for a resource, Project calculate Units 
>> >> >> =
>> >> >> 0.25 and
>> >> >> the
>> >> >> work for each day is 2h.
>> >> >>
>> >> >> Gérard Ducouret
>> >> >>
>> >> >> "Vic"  a écrit dans le 
>> >> >> message
>> >> >> de news:
>> >> >> E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@microsoft.com...
>> >> >> > Hi,
>> >> >> >
>> >> >> > I'm working in Project 2003 and I'm having an issue where 
>> >> >> > it
>> >> >> > won't
>> >> >> > fully
>> >> >> > allocate a resource who is assigned to a task at 100%. 
>> >> >> > This
>> >> >> > is
>> >> >> > happening
>> >> >> > in
>> >> >> > several instances where it only assigns someone for say 2
>> >> >> > hrs per day
>> >> >> > (instead of 8).  Again they are 100% on the task and I 
>> >> >> > can't
>> >> >> > find a
>> >> >> > valid
>> >> >> > reason for this.  I am using leveling as well on a Minute 
>> >> >> > by
>> >> >> > Minute
>> >> >> > basis.
>> >> >> >
>> >> >> > Any ideas?
>> >> >> >
>> >> >> > -- 
>> >> >> > Vic
>> >> >>
>> >> >>
>> >> >>
>> >>
>> >>
>> >>
>>
>>
>>
date: Sat, 11 Oct 2008 08:16:53 -0400   author:   JulieS

Re: Fully Allocate a Resource   
Thanks.  I can try to scale it back to day by day.  I went minute by minute 
to resolve some overallocation flags.

Yeah, I know the purpose of the leveling engine, but I do expect Project to 
optimize people's days to a large extent.  I can't tell you why the Work 
Contour and prioritization worked, I was hoping you could :).  But it did 
work.  Maybe it was the prioritization.  

I did try to manual schedule planned work, but that caused other problems (I 
can't remember what they were now - probably over allocation based on what 
you said). I can try that again and keep an eye on that.

Thanks for your help.  And you too Julie :)

-- 
Vic


"Dave" wrote:

> You can make project display the start time by going to tools, options 
> and selecting the view tab.  In the date format you can opt to show or 
> hide the time.
> 
> As a general observation, do you actually have to track what your 
> resources are doing minute by minute?  That's a very fine level of 
> granularity.  If you are only interested in ensuring that they get a 
> number of activities done in a day then I would suggest day-by-day 
> levelling or even week-by-week levelling might be more appropriate 
> although your particular circumstances may dictate otherwise.
> 
> I don't understand how what you have done has resolved the problem and 
> wonder whether you are expecting too much from the levelling engine.
> 
> Levelling is not an optimisation tool in that it won't adjust the work 
> to fill the gaps in a resource's working day.  It actually does 
> something closer to the opposite - it simply delays tasks until there 
> are no overallocations in the resource's schedule.
> 
> If, after levelling, a resource is not working sufficiently many hours 
> in a day then you need to manually adjust the length of that task (and 
> possibly level again - you may find it useful to fix those elements of 
> the plan you are happy with by setting their priority to 1000).
> 
> You shouldn't have to adjust the contour and I wouldn't worry about it. 
>   By definition, unless the resource works exactly the same number of 
> hours every day on a task then it is contoured.  Instead, if I wasn't 
> happy with the hours that a resource had been scheduled to work then I 
> would alter that either by directly entering the planned hours or by 
> adjusting the length of the task, although when doing this you need to 
> consider the totality of hours worked by the resource across all the 
> tasks occurring on that day.
> 
> Vic wrote:
> > Hi Julie,
> > 
> > On the leveling I didn't allow splitting of a task.  And I'm not sure how to 
> > check the time of a task starting.  Please let me know on that just out of 
> > curiousity.  But I don't believe that is it because it's many days and many 
> > tasks that it happens.
> > 
> > I was able to resolve the problem by changing the Work Contour and 
> > prioritizing some tasks.  When I entered Actual Work it changed the Work 
> > Contour from "Flat" to "Contour" - is that normal?  So I changed them back to 
> > Flat and in addition to the prioritization that seemed to start scheduling 
> > the work so they had an 8 hour day (or at least close to it in some cases).
> > 
> > Hope that makes sense.  While it seems to be corrected, I would still be 
> > curious to know why it does that and if there's a better way to handle the 
> > situation.  Your help is appreciated. 
> > 
> > 
>
date: Sat, 11 Oct 2008 18:33:01 -0700   author:   Vic

Re: Fully Allocate a Resource   
You're welcome Vic.  Glad to have helped and thanks for the 
feedback.
Julie
"Vic"  wrote in message 
news:C34D4A26-B85B-421D-8758-C8FEB867DB27@microsoft.com...
> Thanks.  I can try to scale it back to day by day.  I went minute 
> by minute
> to resolve some overallocation flags.
>
> Yeah, I know the purpose of the leveling engine, but I do expect 
> Project to
> optimize people's days to a large extent.  I can't tell you why 
> the Work
> Contour and prioritization worked, I was hoping you could :).  But 
> it did
> work.  Maybe it was the prioritization.
>
> I did try to manual schedule planned work, but that caused other 
> problems (I
> can't remember what they were now - probably over allocation based 
> on what
> you said). I can try that again and keep an eye on that.
>
> Thanks for your help.  And you too Julie :)
>
> -- 
> Vic
>
>
> "Dave" wrote:
>
>> You can make project display the start time by going to tools, 
>> options
>> and selecting the view tab.  In the date format you can opt to 
>> show or
>> hide the time.
>>
>> As a general observation, do you actually have to track what your
>> resources are doing minute by minute?  That's a very fine level 
>> of
>> granularity.  If you are only interested in ensuring that they 
>> get a
>> number of activities done in a day then I would suggest 
>> day-by-day
>> levelling or even week-by-week levelling might be more 
>> appropriate
>> although your particular circumstances may dictate otherwise.
>>
>> I don't understand how what you have done has resolved the 
>> problem and
>> wonder whether you are expecting too much from the levelling 
>> engine.
>>
>> Levelling is not an optimisation tool in that it won't adjust the 
>> work
>> to fill the gaps in a resource's working day.  It actually does
>> something closer to the opposite - it simply delays tasks until 
>> there
>> are no overallocations in the resource's schedule.
>>
>> If, after levelling, a resource is not working sufficiently many 
>> hours
>> in a day then you need to manually adjust the length of that task 
>> (and
>> possibly level again - you may find it useful to fix those 
>> elements of
>> the plan you are happy with by setting their priority to 1000).
>>
>> You shouldn't have to adjust the contour and I wouldn't worry 
>> about it.
>>   By definition, unless the resource works exactly the same 
>> number of
>> hours every day on a task then it is contoured.  Instead, if I 
>> wasn't
>> happy with the hours that a resource had been scheduled to work 
>> then I
>> would alter that either by directly entering the planned hours or 
>> by
>> adjusting the length of the task, although when doing this you 
>> need to
>> consider the totality of hours worked by the resource across all 
>> the
>> tasks occurring on that day.
>>
>> Vic wrote:
>> > Hi Julie,
>> >
>> > On the leveling I didn't allow splitting of a task.  And I'm 
>> > not sure how to
>> > check the time of a task starting.  Please let me know on that 
>> > just out of
>> > curiousity.  But I don't believe that is it because it's many 
>> > days and many
>> > tasks that it happens.
>> >
>> > I was able to resolve the problem by changing the Work Contour 
>> > and
>> > prioritizing some tasks.  When I entered Actual Work it changed 
>> > the Work
>> > Contour from "Flat" to "Contour" - is that normal?  So I 
>> > changed them back to
>> > Flat and in addition to the prioritization that seemed to start 
>> > scheduling
>> > the work so they had an 8 hour day (or at least close to it in 
>> > some cases).
>> >
>> > Hope that makes sense.  While it seems to be corrected, I would 
>> > still be
>> > curious to know why it does that and if there's a better way to 
>> > handle the
>> > situation.  Your help is appreciated.
>> >
>> >
>>
date: Sat, 11 Oct 2008 21:59:17 -0400   author:   JulieS

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us