Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 8 Oct 2008 07:14:30 -0700,    group: microsoft.public.project        back       


MS Project 2007 not accepting constraints   
Can someone tell me what is going on when I change a constraint type and date 
and the date remains the same?  I've deleted the task and added back and it 
still will not accept the new constraint date.  Btw, I'm going from an SNE 
date in Oct 08 to a Must Finish On date in Oct 2010.

Thanks.
date: Wed, 8 Oct 2008 07:14:30 -0700   author:   mikejw

Re: MS Project 2007 not accepting constraints   
Hi,

Two possibilities:
- Either in Tools, Options, Calculation, calculation is set to manual
- Or, you have a circular relationship. Delete all dependencies from and to 
summary tasks; that should rejuvenate your project.
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"mikejw"  wrote in message 
news:CAEB6AFB-2AB6-4C15-A639-3D560CBAC0D2@microsoft.com...
> Can someone tell me what is going on when I change a constraint type and 
> date
> and the date remains the same?  I've deleted the task and added back and 
> it
> still will not accept the new constraint date.  Btw, I'm going from an SNE
> date in Oct 08 to a Must Finish On date in Oct 2010.
>
> Thanks.
date: Wed, 8 Oct 2008 19:56:38 +0200   author:   Jan De Messemaeker

Re: MS Project 2007 not accepting constraints   
Thanks.  The change in options made the difference.

"Jan De Messemaeker" wrote:

> Hi,
> 
> Two possibilities:
> - Either in Tools, Options, Calculation, calculation is set to manual
> - Or, you have a circular relationship. Delete all dependencies from and to 
> summary tasks; that should rejuvenate your project.
> HTH
> 
> -- 
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "mikejw"  wrote in message 
> news:CAEB6AFB-2AB6-4C15-A639-3D560CBAC0D2@microsoft.com...
> > Can someone tell me what is going on when I change a constraint type and 
> > date
> > and the date remains the same?  I've deleted the task and added back and 
> > it
> > still will not accept the new constraint date.  Btw, I'm going from an SNE
> > date in Oct 08 to a Must Finish On date in Oct 2010.
> >
> > Thanks. 
> 
> 
>
date: Wed, 8 Oct 2008 11:38:15 -0700   author:   mikejw