Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 8 Oct 2008 06:56:11 -0700,    group: microsoft.public.project        back       


Why would the BCWS field be 0.00?   
There are resources set so should this field automatically generate the cost 
scheduled?

Thanks
date: Wed, 8 Oct 2008 06:56:11 -0700   author:   Elle

Re: Why would the BCWS field be 0.00?   
Elle,
BCWS and other Earned Values data need 2 references : a Baselien and a 
Status date. Did you set these 2 references?
Gérard


"Elle"  a écrit dans le message de news: 
F09C47E9-8A5E-4CD8-8FAE-0C7676EC6862@microsoft.com...
> There are resources set so should this field automatically generate the 
> cost
> scheduled?
>
> Thanks
date: Wed, 8 Oct 2008 17:22:20 +0200   author:   G?rard Ducouret