There are resources set so should this field automatically generate the cost scheduled? Thanks
Elle, BCWS and other Earned Values data need 2 references : a Baselien and a Status date. Did you set these 2 references? Gérard "Elle" a écrit dans le message de news: F09C47E9-8A5E-4CD8-8FAE-0C7676EC6862@microsoft.com... > There are resources set so should this field automatically generate the > cost > scheduled? > > Thanks