Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Wed, 8 Oct 2008 06:04:01 -0700,    group: microsoft.public.project        back       


Can I establish start and finish time for specific task?   
Does MS Project 2007 have the capabilities to input a start and finish time 
for a specific task in conjunction with the Start and Finish dates?
Example: 
Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
etc.
Thanks in advance for your help
Damon
date: Wed, 8 Oct 2008 06:04:01 -0700   author:   Damon

Re: Can I establish start and finish time for specific task?   
Damon,

You can specify scheduling to the accuracy you require in MS Project by 
following these 3 steps.

1: Ensure that both your Options\Calendar settings and the Base Calendar for 
your project (Change Working Time dialogue box) are in Synch and allow for a 
working day that is not the default OOTB. In your case you are looking to 
achieve a 12 hour day with no lunchbreak.

2: To display the time go Tools>Options>View and in the Date Format section 
select the format most suited to your needs - typically you will want one of 
the selections that displays time as well as date.

3: Looking at your list of tasks if your working day spans from 07:00 
through to 19:00 hours with no interruptions you could simply enter the 
tasks, edit durations to be 5h, 2h and 5h respectively and link them 
together - the 2nd & 3rd tasks would start at the desired times - if they 
don't odds are that you have not edited the settings mentioned in 1: above.

Let us know how you get on.
-- 
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

www.projectability.co.uk


"Damon"  wrote in message 
news:A9AF3E4F-8529-4BED-B408-B9BB5367A26D@microsoft.com...
> Does MS Project 2007 have the capabilities to input a start and finish 
> time
> for a specific task in conjunction with the Start and Finish dates?
> Example:
> Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
> Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
> Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
> etc.
> Thanks in advance for your help
> Damon
date: Wed, 8 Oct 2008 14:19:33 +0100   author:   Dominic

RE: Can I establish start and finish time for specific task?   
Hi Damon,

A short answer is no.  You can set either a start or finish date but 
generally not both.  Project calculates dates from data you enter about the 
work or duration required to complete each task.  So if your task "Excavate 
dirt you expect to take .5d (7:00am to 12:00am) then set duration to 0.5d, 
the successor to that is then "build forms" duration 2hrs, and the successor 
to that is "form rebar" duration 3hrs.  This will automatically set start and 
finsh dates for all your tasks, except the start of the first task which must 
have a start date set if there is no predecessor.  However it also does mean 
that you will need to check your calendar settings, and make sure the default 
settings for hours per day, days per week match that of your calendar.  Also 
do not allow the default 'none' to be set as the task calendar, set the task 
calendar to the calendar appropriate to that task.  It is a good habit to get 
into.

Hope this helps

Regards

DavidC

"Damon" wrote:

> Does MS Project 2007 have the capabilities to input a start and finish time 
> for a specific task in conjunction with the Start and Finish dates?
> Example: 
> Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
> Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
> Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
> etc.
> Thanks in advance for your help
> Damon
date: Wed, 8 Oct 2008 15:08:29 -0700   author:   DavidC

Re: Can I establish start and finish time for specific task?   
All date fields in Project are really date/time fields and when manually 
doing an entry all you need do is type the time as part of your entry.  To 
see the times, as others have mentioned, go to the Tools, Options menu and 
on the View page select a date format that also displays the time.  Of much 
greater importance is the fact that you should not be entering task start 
and finish dates at all, whether you specify time or not.  It's Project's 
job to calculate those dates and times for you, based on the project kickoff 
date, the durations of the various tasks, the workflow modeled in the task 
links, and the availability of the resources required to do the work.  You 
don't tell it when you think tasks should take place - it tells you when 
tasks can take place.
-- 
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs

.
"Damon"  wrote in message 
news:A9AF3E4F-8529-4BED-B408-B9BB5367A26D@microsoft.com...
> Does MS Project 2007 have the capabilities to input a start and finish 
> time
> for a specific task in conjunction with the Start and Finish dates?
> Example:
> Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
> Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
> Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
> etc.
> Thanks in advance for your help
> Damon
date: Fri, 10 Oct 2008 08:11:01 -0400   author:   Steve House [MVP] sjhouse at hotmail dot com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us