Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Mon, 6 Oct 2008 14:02:10 -0700,    group: microsoft.public.project        back       


Project 2007 "Backward Scheduling"   
How do I set tasks to begin "X" days before another tasks "must finish on" 
date?
date: Mon, 6 Oct 2008 14:02:10 -0700   author:   aaronpw

Re: Project 2007 "Backward Scheduling"   
On Mon, 6 Oct 2008 14:02:10 -0700, aaronpw wrote:

> How do I set tasks to begin "X" days before another tasks "must finish on" 
> date?

Start to start relationship with X days lag. BTW, in general, not the best
way to schedule, particularly with the MFO constraint. If more than a few
of your tasks are constrained, you're in trouble. 

Hope this helps in your world.
date: Mon, 6 Oct 2008 15:29:14 -0600   author:   salgud

RE: Project 2007 "Backward Scheduling"   
Hi Aaronpw,

You can use the FS-"x"d, so the second task finish is "x" days before the 
start of the first task.  This will show a start date for the first task as 
late as possible but not as soon as possible.  If you set a deadline task 
that shows the first task must have started by the deadline date then you 
have float and the ability to cover off any delays that may occur and not 
have work being started at the last minute.  For that simply set the deadline 
task to be 'FS-"X"d' and then use that date as the deadline for the first 
task.

Hope this is some help

Regards

DavidC
"aaronpw" wrote:

> How do I set tasks to begin "X" days before another tasks "must finish on" 
> date?
date: Mon, 6 Oct 2008 14:42:23 -0700   author:   DavidC

RE: Project 2007 "Backward Scheduling"   
Might I email you away from this forum with additional detail?

"DavidC" wrote:

> Hi Aaronpw,
> 
> You can use the FS-"x"d, so the second task finish is "x" days before the 
> start of the first task.  This will show a start date for the first task as 
> late as possible but not as soon as possible.  If you set a deadline task 
> that shows the first task must have started by the deadline date then you 
> have float and the ability to cover off any delays that may occur and not 
> have work being started at the last minute.  For that simply set the deadline 
> task to be 'FS-"X"d' and then use that date as the deadline for the first 
> task.
> 
> Hope this is some help
> 
> Regards
> 
> DavidC
> "aaronpw" wrote:
> 
> > How do I set tasks to begin "X" days before another tasks "must finish on" 
> > date?
date: Mon, 6 Oct 2008 14:56:52 -0700   author:   aaronpw

RE: Project 2007 "Backward Scheduling"   
Sure,

try david.coatesatmightyriverdotcodotnz

"aaronpw" wrote:

> Might I email you away from this forum with additional detail?
> 
> "DavidC" wrote:
> 
> > Hi Aaronpw,
> > 
> > You can use the FS-"x"d, so the second task finish is "x" days before the 
> > start of the first task.  This will show a start date for the first task as 
> > late as possible but not as soon as possible.  If you set a deadline task 
> > that shows the first task must have started by the deadline date then you 
> > have float and the ability to cover off any delays that may occur and not 
> > have work being started at the last minute.  For that simply set the deadline 
> > task to be 'FS-"X"d' and then use that date as the deadline for the first 
> > task.
> > 
> > Hope this is some help
> > 
> > Regards
> > 
> > DavidC
> > "aaronpw" wrote:
> > 
> > > How do I set tasks to begin "X" days before another tasks "must finish on" 
> > > date?
date: Mon, 6 Oct 2008 15:04:53 -0700   author:   DavidC

RE: Project 2007 "Backward Scheduling"   
First, scheduling a "Must Finish On" date for a task is not a best practice. 
If you can avoid it, please do.

Given task B is "Must Finish On" with predecessor "A" that you wish to start 
17 days prior.  You can change the task type of Task A to "As Late As 
Possible" and then tweak it back to the desired start date using lag.

In general, it is not good to use negative lag (lead) on a task unless you 
know that the lagged task will finish on a specific date with certainty.  
This seems to be the case in your application.

However, what would happen if your task "B" finished early or late?
-- 
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"aaronpw" wrote:

> How do I set tasks to begin "X" days before another tasks "must finish on" 
> date?
date: Mon, 6 Oct 2008 19:03:01 -0700   author:   Jim Aksel

Re: Project 2007 "Backward Scheduling"   
Constraints in MS Project are restrictions on what the scheduling engine can 
do and as such describe a physical reality that is imposed on the schedule - 
the constraint condition is ALWAYS true no matter what we do in our project 
schedule.  When the boss says "This task must finish on XX date" or "That 
deliverable must be ready no later than YY date" he's not describing 
something that already exists, he's setting an objective for future 
perfomance.  The reason we use scheduling software is to help us determine 
the workflow that will enable to meet those performance objectives - will 
the way we're going to do the work meet the objectives we have to hit or 
will it result in missing it?  For it to do that we must let it freely 
calculate the results we are likely to obtain if we attempt to proceed with 
a particular workflow and resource deployment that we're considering, ie, if 
we try it this way will we finish on-time?  To see that we need to let 
Project show us the results without interference, ie, without constraints 
that basically force it to lie to us and promise we'll finish on-time 
regardless of whether we're really going to be able to do that or not.


-- 
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs



"aaronpw"  wrote in message 
news:CF7C6D13-88E3-4E29-B46E-C253790DCB12@microsoft.com...
> How do I set tasks to begin "X" days before another tasks "must finish on"
> date?
date: Thu, 9 Oct 2008 05:13:19 -0400   author:   Steve House sjhouse at hotmail dot com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us