Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Mon, 6 Oct 2008 12:30:15 -0700,    group: microsoft.public.project        back       


Command to highlight successor task relationships   
Hello...I'm using MS Project 2007 with a very complex project. I noted that 
if I change or update a task date, the succeeding linked task dates are 
highlighted in light blue.

This is very useful for finding broken or mis-connected links...however, is 
there a way beyond changing a date in a cell to see all the cells that are 
affected "downstream" of the one task? I know there is a relationship view 
screen, but I really like the blue highlighted cells of affected tasks.

Thanks
date: Mon, 6 Oct 2008 12:30:15 -0700   author:   New-PM

Re: Command to highlight successor task relationships   
Hello New-PM,

See if the Task Drivers pane helps.  On the Standard toolbar find 
the task drivers button.  When clicked it will open the task drivers 
pane and you can then select a task to see a list of all items 
(predecessors, resources) which is affecting the start of the 
selected task.

Project will highlight changed tasks if a task's date changes -- so, 
if you change duration manually or add or subtract resource to an 
effort driven task, or change work etc -- that will usually change 
duration and you'll see the change highlighting.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional 
information about Microsoft Project


"New-PM"  wrote in message 
news:9CBCA311-723B-4534-8D15-705816365F44@microsoft.com...
> Hello...I'm using MS Project 2007 with a very complex project. I 
> noted that
> if I change or update a task date, the succeeding linked task 
> dates are
> highlighted in light blue.
>
> This is very useful for finding broken or mis-connected 
> links...however, is
> there a way beyond changing a date in a cell to see all the cells 
> that are
> affected "downstream" of the one task? I know there is a 
> relationship view
> screen, but I really like the blue highlighted cells of affected 
> tasks.
>
> Thanks
date: Mon, 6 Oct 2008 15:44:04 -0400   author:   JulieS

Re: Command to highlight successor task relationships   
Thanks Julie...I tried it and it sort of does what I need but not as easily 
or neatly as changing a date or duration...with MS Project being so skittish 
at times on what gets changed where, it is not my most favorite thing to 
start changing dates or durations to flesh out what successor tasks are 
linked and affected by the task I'm curious about.

Thanks for your help! Maybe a word back to Microsoft to develop a couple of 
commands:
"highlight all linked tasks" and 
"highlight all affected tasks"

Now that would be useful!

Regards,
New-PM

"JulieS" wrote:

> Hello New-PM,
> 
> See if the Task Drivers pane helps.  On the Standard toolbar find 
> the task drivers button.  When clicked it will open the task drivers 
> pane and you can then select a task to see a list of all items 
> (predecessors, resources) which is affecting the start of the 
> selected task.
> 
> Project will highlight changed tasks if a task's date changes -- so, 
> if you change duration manually or add or subtract resource to an 
> effort driven task, or change work etc -- that will usually change 
> duration and you'll see the change highlighting.
> 
> I hope this helps.  Let us know how you get along.
> 
> Julie
> Project MVP
> 
> Visit http://project.mvps.org/ for the FAQs and additional 
> information about Microsoft Project
> 
> 
> "New-PM"  wrote in message 
> news:9CBCA311-723B-4534-8D15-705816365F44@microsoft.com...
> > Hello...I'm using MS Project 2007 with a very complex project. I 
> > noted that
> > if I change or update a task date, the succeeding linked task 
> > dates are
> > highlighted in light blue.
> >
> > This is very useful for finding broken or mis-connected 
> > links...however, is
> > there a way beyond changing a date in a cell to see all the cells 
> > that are
> > affected "downstream" of the one task? I know there is a 
> > relationship view
> > screen, but I really like the blue highlighted cells of affected 
> > tasks.
> >
> > Thanks 
> 
> 
>
date: Mon, 6 Oct 2008 13:55:29 -0700   author:   New-PM

Re: Command to highlight successor task relationships   
You're welcome.  Glad to have helped and thanks for the feedback.

Just as a side note, you really shouldn't be changing dates.  As you 
note, setting task predecessors/successors is the way to go.

Jack Dahlgren (Project MVP) does have a macro on his website which 
will help trace successors.  You might find it useful.  Jack's 
website is:

http://masamiki.com/project/macros.htm

See the "Trace" macro.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional 
information about Microsoft Project

"New-PM"  wrote in message 
news:766A0863-EA88-4478-BACC-AC0440D66419@microsoft.com...
> Thanks Julie...I tried it and it sort of does what I need but not 
> as easily
> or neatly as changing a date or duration...with MS Project being 
> so skittish
> at times on what gets changed where, it is not my most favorite 
> thing to
> start changing dates or durations to flesh out what successor 
> tasks are
> linked and affected by the task I'm curious about.
>
> Thanks for your help! Maybe a word back to Microsoft to develop a 
> couple of
> commands:
> "highlight all linked tasks" and
> "highlight all affected tasks"
>
> Now that would be useful!
>
> Regards,
> New-PM
>
> "JulieS" wrote:
>
>> Hello New-PM,
>>
>> See if the Task Drivers pane helps.  On the Standard toolbar find
>> the task drivers button.  When clicked it will open the task 
>> drivers
>> pane and you can then select a task to see a list of all items
>> (predecessors, resources) which is affecting the start of the
>> selected task.
>>
>> Project will highlight changed tasks if a task's date changes --  
>> so,
>> if you change duration manually or add or subtract resource to an
>> effort driven task, or change work etc -- that will usually 
>> change
>> duration and you'll see the change highlighting.
>>
>> I hope this helps.  Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>>
>> "New-PM"  wrote in message
>> news:9CBCA311-723B-4534-8D15-705816365F44@microsoft.com...
>> > Hello...I'm using MS Project 2007 with a very complex project. 
>> > I
>> > noted that
>> > if I change or update a task date, the succeeding linked task
>> > dates are
>> > highlighted in light blue.
>> >
>> > This is very useful for finding broken or mis-connected
>> > links...however, is
>> > there a way beyond changing a date in a cell to see all the 
>> > cells
>> > that are
>> > affected "downstream" of the one task? I know there is a
>> > relationship view
>> > screen, but I really like the blue highlighted cells of 
>> > affected
>> > tasks.
>> >
>> > Thanks
>>
>>
>>
date: Mon, 6 Oct 2008 17:12:27 -0400   author:   JulieS

Re: Command to highlight successor task relationships   
One way to assess the impact of the change you have made is to use on of the 
10 Baselines available to you using the "Interim Plan" option in the Set 
Baseline dialogue box and to then update this baseline (Baseline N) prior to 
making changes and to then make a copy of the slipping tasks filter renaming 
it to something memorable such as "Change Impact" and edit the values so 
that Baseline Finish N does not equal NA and Finish is greater than Baseline 
Finish N. This will then show you all tasks impacted by the change you have 
just made with the earliest displayed task being the "Culprit" and all other 
tasks being the "Victims" of the change you have made. This does of course 
assume that you have a complete network of dependencies through your 
schedule.

-- 
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

www.projectability.co.uk


"JulieS"  wrote in message 
news:uBW69g$JJHA.2164@TK2MSFTNGP02.phx.gbl...
> You're welcome.  Glad to have helped and thanks for the feedback.
>
> Just as a side note, you really shouldn't be changing dates.  As you note, 
> setting task predecessors/successors is the way to go.
>
> Jack Dahlgren (Project MVP) does have a macro on his website which will 
> help trace successors.  You might find it useful.  Jack's website is:
>
> http://masamiki.com/project/macros.htm
>
> See the "Trace" macro.
>
> I hope this helps.  Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information 
> about Microsoft Project
>
> "New-PM"  wrote in message 
> news:766A0863-EA88-4478-BACC-AC0440D66419@microsoft.com...
>> Thanks Julie...I tried it and it sort of does what I need but not as 
>> easily
>> or neatly as changing a date or duration...with MS Project being so 
>> skittish
>> at times on what gets changed where, it is not my most favorite thing to
>> start changing dates or durations to flesh out what successor tasks are
>> linked and affected by the task I'm curious about.
>>
>> Thanks for your help! Maybe a word back to Microsoft to develop a couple 
>> of
>> commands:
>> "highlight all linked tasks" and
>> "highlight all affected tasks"
>>
>> Now that would be useful!
>>
>> Regards,
>> New-PM
>>
>> "JulieS" wrote:
>>
>>> Hello New-PM,
>>>
>>> See if the Task Drivers pane helps.  On the Standard toolbar find
>>> the task drivers button.  When clicked it will open the task drivers
>>> pane and you can then select a task to see a list of all items
>>> (predecessors, resources) which is affecting the start of the
>>> selected task.
>>>
>>> Project will highlight changed tasks if a task's date changes --  so,
>>> if you change duration manually or add or subtract resource to an
>>> effort driven task, or change work etc -- that will usually change
>>> duration and you'll see the change highlighting.
>>>
>>> I hope this helps.  Let us know how you get along.
>>>
>>> Julie
>>> Project MVP
>>>
>>> Visit http://project.mvps.org/ for the FAQs and additional
>>> information about Microsoft Project
>>>
>>>
>>> "New-PM"  wrote in message
>>> news:9CBCA311-723B-4534-8D15-705816365F44@microsoft.com...
>>> > Hello...I'm using MS Project 2007 with a very complex project. I
>>> > noted that
>>> > if I change or update a task date, the succeeding linked task
>>> > dates are
>>> > highlighted in light blue.
>>> >
>>> > This is very useful for finding broken or mis-connected
>>> > links...however, is
>>> > there a way beyond changing a date in a cell to see all the cells
>>> > that are
>>> > affected "downstream" of the one task? I know there is a
>>> > relationship view
>>> > screen, but I really like the blue highlighted cells of affected
>>> > tasks.
>>> >
>>> > Thanks
>>>
>>>
>>>
>
>
date: Tue, 7 Oct 2008 11:49:45 +0100   author:   Dominic

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us