|
|
|
date: Mon, 6 Oct 2008 12:25:01 -0700,
group: microsoft.public.project
back
Re: Adjust Task Duration For Resource Productivity
Hi,
I'm not with you.
When you cut the working hours back for a resource (through tools, change
working time, NOT through tools, options, calendar) working on a task (as
the only resource) the true duration (finish-start) of the task will
increase. It just will.
The duration field will still show the same amount of time, but your
schedule is correct.
Also, of course, the resource usage will show fewer hours worked during
those days.
All true, but I solved your problem, and I hoped that was what you were
looking for...
Greetings,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Bill Bradshaw" wrote in message
news:939DC15E-AC29-41B3-B94B-8583CC409776@microsoft.com...
>I am still having a problem. They both work the same number of hours but
>one
> has a more productive piece of equipment (D-8 versus D-9). I created a
> new
> resource and then cut the working hours back for that resource. I can not
> seem to make the task adjust properly and also the resource view does not
> show the employee working a full workday. I must be missing something -
> like
> can you give me more detailed directions :-)?
>
> <Bill>
>
> "Jan De Messemaeker" wrote:
>
>> Hi,
>>
>> This may sound crazy, but it works.
>> Give the laggards a calendar with less than 8 hours work but keep on
>> assigning everybody as 100%.
>> HTH
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Bill Bradshaw" wrote in message
>> news:AF917F12-9771-4494-9AAC-58E807332E0D@microsoft.com...
>> > Resource 1 by itself will take 5 days duration to complete a task. I
>> > want
>> > to
>> > add Resource 2 which is 150% more productive than Resource 1. This
>> > should
>> > reduce the duration to 2 days from 5 days. By increasing Resource 2's
>> > units
>> > from 100% to 150% will give me the correct duration of 2 days but it
>> > also
>> > gives me an over allocation error (which it should). So how do I
>> > handle
>> > resources assigned to a task which are doing the same work but have
>> > different
>> > productivity rates?
>
date: Tue, 7 Oct 2008 10:20:22 +0200
author: Jan De Messemaeker
|
|