Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Thu, 2 Oct 2008 19:48:06 +0200,    group: microsoft.public.project        back       


peak units   
Hello all,

Can anybody please explain to me how peak units in resource usage get 
calculated? The idea is to use resource usage view for planning and 
monitoring hours resources have spent already (actual work) and are likely 
to spend (work) in the future and compare it with the original planning 
(baseline work).   I thought 40 hours a week is taken as 100 % peak units. 
Therefore 32 hours would be 80% of peak units and so on..However, I seem to 
experience strange and unexplainable behaviour. For example, if 
planned/baselined work was 40 hours a week for a resource but he worked less 
hours, peak units for the coming weeks became 92% in first 3 weeks and then 
106% in the week after. Or if somebody did not work for a month because of 
holiday, then the peak units in the coming four weeks became 127% and after 
that  peak units are 112% without any obvious reason.

I truly hope somebody out there can help.

Many thanks,

Vera
date: Thu, 2 Oct 2008 19:48:06 +0200   author:   vdz

Re: peak units   
Hi,

From what you describe I think you have put task type as fixed duration.
In that case when work is les sthan planned in a period, since the duration 
does not change, the remainder Work is spread out over the remaining time 
period and units go up.
I've seen more than 5000% once..

I duration ever fixed?

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"vdz"  wrote in message 
news:48e50953$0$24400$5fc3050@news.tiscali.nl...
> Hello all,
>
> Can anybody please explain to me how peak units in resource usage get 
> calculated? The idea is to use resource usage view for planning and 
> monitoring hours resources have spent already (actual work) and are likely 
> to spend (work) in the future and compare it with the original planning 
> (baseline work).   I thought 40 hours a week is taken as 100 % peak units. 
> Therefore 32 hours would be 80% of peak units and so on..However, I seem 
> to experience strange and unexplainable behaviour. For example, if 
> planned/baselined work was 40 hours a week for a resource but he worked 
> less hours, peak units for the coming weeks became 92% in first 3 weeks 
> and then 106% in the week after. Or if somebody did not work for a month 
> because of holiday, then the peak units in the coming four weeks became 
> 127% and after that  peak units are 112% without any obvious reason.
>
> I truly hope somebody out there can help.
>
> Many thanks,
>
> Vera
>
>
>
date: Thu, 2 Oct 2008 20:44:37 +0200   author:   Jan De Messemaeker

Re: peak units   
On Thu, 2 Oct 2008 19:48:06 +0200, vdz wrote:

> Hello all,
> 
> Can anybody please explain to me how peak units in resource usage get 
> calculated? The idea is to use resource usage view for planning and 
> monitoring hours resources have spent already (actual work) and are likely 
> to spend (work) in the future and compare it with the original planning 
> (baseline work).   I thought 40 hours a week is taken as 100 % peak units. 
> Therefore 32 hours would be 80% of peak units and so on..However, I seem to 
> experience strange and unexplainable behaviour. For example, if 
> planned/baselined work was 40 hours a week for a resource but he worked less 
> hours, peak units for the coming weeks became 92% in first 3 weeks and then 
> 106% in the week after. Or if somebody did not work for a month because of 
> holiday, then the peak units in the coming four weeks became 127% and after 
> that  peak units are 112% without any obvious reason.
> 
> I truly hope somebody out there can help.
> 
> Many thanks,
> 
> Vera

Peak Units is not calculated, it's entered. It's the max no. of units of
the resource available at any given time. I.e. if I have 4 capenders
available to my project, peak units is 4. Can be expressed as units (4 in
this case) or percentage (400% in this case)

Hope this helps in your world.
date: Thu, 2 Oct 2008 12:47:22 -0600   author:   Dave

Re: peak units   
Hi,

Sorry Dave, what you refer to is Max.Units
Peak units is the highest assignment unit during a certain period.
HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Dave"  wrote in message 
news:1nvmzwt727tjx.17m1wcmuvn1wc.dlg@40tude.net...
> On Thu, 2 Oct 2008 19:48:06 +0200, vdz wrote:
>
>> Hello all,
>>
>> Can anybody please explain to me how peak units in resource usage get
>> calculated? The idea is to use resource usage view for planning and
>> monitoring hours resources have spent already (actual work) and are 
>> likely
>> to spend (work) in the future and compare it with the original planning
>> (baseline work).   I thought 40 hours a week is taken as 100 % peak 
>> units.
>> Therefore 32 hours would be 80% of peak units and so on..However, I seem 
>> to
>> experience strange and unexplainable behaviour. For example, if
>> planned/baselined work was 40 hours a week for a resource but he worked 
>> less
>> hours, peak units for the coming weeks became 92% in first 3 weeks and 
>> then
>> 106% in the week after. Or if somebody did not work for a month because 
>> of
>> holiday, then the peak units in the coming four weeks became 127% and 
>> after
>> that  peak units are 112% without any obvious reason.
>>
>> I truly hope somebody out there can help.
>>
>> Many thanks,
>>
>> Vera
>
> Peak Units is not calculated, it's entered. It's the max no. of units of
> the resource available at any given time. I.e. if I have 4 capenders
> available to my project, peak units is 4. Can be expressed as units (4 in
> this case) or percentage (400% in this case)
>
> Hope this helps in your world.
date: Thu, 2 Oct 2008 21:01:29 +0200   author:   Jan De Messemaeker

Re: peak units   
Peak units are an instantaneous measure.  If a resource is assigned to 2 
tasks at 100% each and those tasks overlap each other by even 1 minute, the 
resource's peak units is 200%.  In that 1 minute of time, he is expected to 
produce 2 minutes worth of work.  OR viewed another way, for 1 minute he is 
expected to be in two places at once.  The resource units only represent the 
percentage of his calendar when viewed at a very superficial level.  What 
the percentage really means is the rate at which the resource is able to 
convert time into work.  An assignment of 100% means that for each hour of 
time spent, 1 man-hour of work is achieved.  An assignment of 50% means that 
for each hour of time spent on the task, only 1/2 hour's worth of full-time 
equivalent work is realized.
-- 
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"vdz"  wrote in message 
news:48e50953$0$24400$5fc3050@news.tiscali.nl...
> Hello all,
>
> Can anybody please explain to me how peak units in resource usage get 
> calculated? The idea is to use resource usage view for planning and 
> monitoring hours resources have spent already (actual work) and are likely 
> to spend (work) in the future and compare it with the original planning 
> (baseline work).   I thought 40 hours a week is taken as 100 % peak units. 
> Therefore 32 hours would be 80% of peak units and so on..However, I seem 
> to experience strange and unexplainable behaviour. For example, if 
> planned/baselined work was 40 hours a week for a resource but he worked 
> less hours, peak units for the coming weeks became 92% in first 3 weeks 
> and then 106% in the week after. Or if somebody did not work for a month 
> because of holiday, then the peak units in the coming four weeks became 
> 127% and after that  peak units are 112% without any obvious reason.
>
> I truly hope somebody out there can help.
>
> Many thanks,
>
> Vera
>
>
>
date: Thu, 2 Oct 2008 19:15:11 -0400   author:   Steve House sjhouse at hotmail dot com

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us