Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Thu, 2 Oct 2008 08:50:03 -0700,    group: microsoft.public.project        back       


Gantt chart dates are different than task dates   
I've created a project w/ MS Project 2007.  The project starts in September 
2008 and runs until January 2009.  When I look at the Gantt chart, the 
timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
year ahead.  Same is true when I click on the Calendar view.  I checked to 
see if my version was missing a service update, but I am up-to-date w/ the 
latest patch.
date: Thu, 2 Oct 2008 08:50:03 -0700   author:   mmckeen

RE: Gantt chart dates are different than task dates   
Hello MMcKeen,

See FAQ #1 at:

http://project.mvps.org/faqs.htm

I hope this helps.

Julie

"mmckeen" wrote:

> I've created a project w/ MS Project 2007.  The project starts in September 
> 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> year ahead.  Same is true when I click on the Calendar view.  I checked to 
> see if my version was missing a service update, but I am up-to-date w/ the 
> latest patch.
date: Thu, 2 Oct 2008 09:17:03 -0700   author:   JulieS

RE: Gantt chart dates are different than task dates   
You may want to check to be sure the fiscal year hasn't been changed to 
something other than January. I believe this can cause what you are seeing.

Darrell

"mmckeen" wrote:

> I've created a project w/ MS Project 2007.  The project starts in September 
> 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> year ahead.  Same is true when I click on the Calendar view.  I checked to 
> see if my version was missing a service update, but I am up-to-date w/ the 
> latest patch.
date: Thu, 2 Oct 2008 09:22:10 -0700   author:   Darrell

RE: Gantt chart dates are different than task dates   
HI, I checked that and it is set to January.  My problem is that the Gantt 
displays EXACTLY one year off.  Today appears as October 2, 2009, when the 
task date is October 2, 2008.  If I create a new project, I get the same 
thing. 

"Darrell" wrote:

> You may want to check to be sure the fiscal year hasn't been changed to 
> something other than January. I believe this can cause what you are seeing.
> 
> Darrell
> 
> "mmckeen" wrote:
> 
> > I've created a project w/ MS Project 2007.  The project starts in September 
> > 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> > timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> > INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> > year ahead.  Same is true when I click on the Calendar view.  I checked to 
> > see if my version was missing a service update, but I am up-to-date w/ the 
> > latest patch.
date: Thu, 2 Oct 2008 09:26:00 -0700   author:   mmckeen

RE: Gantt chart dates are different than task dates   
Hi, my fical calendar is set to January.  The Gantt is thrown off by EXACTLY 
one year, displaying dates for the current month as October 2009 instead of 
October 2008.

"JulieS" wrote:

> Hello MMcKeen,
> 
> See FAQ #1 at:
> 
> http://project.mvps.org/faqs.htm
> 
> I hope this helps.
> 
> Julie
> 
> "mmckeen" wrote:
> 
> > I've created a project w/ MS Project 2007.  The project starts in September 
> > 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> > timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> > INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> > year ahead.  Same is true when I click on the Calendar view.  I checked to 
> > see if my version was missing a service update, but I am up-to-date w/ the 
> > latest patch.
date: Thu, 2 Oct 2008 09:27:01 -0700   author:   mmckeen

RE: Gantt chart dates are different than task dates   
Hi,

I don't have Project 2007 here to check, but check the timescale settings in 
the Gantt chart.  Right click over the Gantt and uncheck the option "use 
Fiscal Year".

Better?

Julie

"mmckeen" wrote:

> Hi, my fical calendar is set to January.  The Gantt is thrown off by EXACTLY 
> one year, displaying dates for the current month as October 2009 instead of 
> October 2008.
> 
> "JulieS" wrote:
> 
> > Hello MMcKeen,
> > 
> > See FAQ #1 at:
> > 
> > http://project.mvps.org/faqs.htm
> > 
> > I hope this helps.
> > 
> > Julie
> > 
> > "mmckeen" wrote:
> > 
> > > I've created a project w/ MS Project 2007.  The project starts in September 
> > > 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> > > timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> > > INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> > > year ahead.  Same is true when I click on the Calendar view.  I checked to 
> > > see if my version was missing a service update, but I am up-to-date w/ the 
> > > latest patch.
date: Thu, 2 Oct 2008 09:38:02 -0700   author:   JulieS

RE: Gantt chart dates are different than task dates   
THANK YOU!!  That worked!  I've been going nuts the past few days!

"JulieS" wrote:

> Hi,
> 
> I don't have Project 2007 here to check, but check the timescale settings in 
> the Gantt chart.  Right click over the Gantt and uncheck the option "use 
> Fiscal Year".
> 
> Better?
> 
> Julie
> 
> "mmckeen" wrote:
> 
> > Hi, my fical calendar is set to January.  The Gantt is thrown off by EXACTLY 
> > one year, displaying dates for the current month as October 2009 instead of 
> > October 2008.
> > 
> > "JulieS" wrote:
> > 
> > > Hello MMcKeen,
> > > 
> > > See FAQ #1 at:
> > > 
> > > http://project.mvps.org/faqs.htm
> > > 
> > > I hope this helps.
> > > 
> > > Julie
> > > 
> > > "mmckeen" wrote:
> > > 
> > > > I've created a project w/ MS Project 2007.  The project starts in September 
> > > > 2008 and runs until January 2009.  When I look at the Gantt chart, the 
> > > > timeline is September 2009 to January 2010.  The 'start date' in PROJECT 
> > > > INFORMATION is 2008, and I've been unable to figure out why the Gantt is one 
> > > > year ahead.  Same is true when I click on the Calendar view.  I checked to 
> > > > see if my version was missing a service update, but I am up-to-date w/ the 
> > > > latest patch.
date: Thu, 2 Oct 2008 10:01:01 -0700   author:   mmckeen

Re: Gantt chart dates are different than task dates   
Great --  I'm Glad to know that was the cause of the worries.  I'm 
glad to have helped and thanks for the feedback.

Julie

"mmckeen"  wrote in message 
news:94E1B776-74F7-4596-AE3A-C470A00F1ABF@microsoft.com...
> THANK YOU!!  That worked!  I've been going nuts the past few days!
>
> "JulieS" wrote:
>
>> Hi,
>>
>> I don't have Project 2007 here to check, but check the timescale 
>> settings in
>> the Gantt chart.  Right click over the Gantt and uncheck the 
>> option "use
>> Fiscal Year".
>>
>> Better?
>>
>> Julie
>>
>> "mmckeen" wrote:
>>
>> > Hi, my fical calendar is set to January.  The Gantt is thrown 
>> > off by EXACTLY
>> > one year, displaying dates for the current month as October 
>> > 2009 instead of
>> > October 2008.
>> >
>> > "JulieS" wrote:
>> >
>> > > Hello MMcKeen,
>> > >
>> > > See FAQ #1 at:
>> > >
>> > > http://project.mvps.org/faqs.htm
>> > >
>> > > I hope this helps.
>> > >
>> > > Julie
>> > >
>> > > "mmckeen" wrote:
>> > >
>> > > > I've created a project w/ MS Project 2007.  The project 
>> > > > starts in September
>> > > > 2008 and runs until January 2009.  When I look at the Gantt 
>> > > > chart, the
>> > > > timeline is September 2009 to January 2010.  The 'start 
>> > > > date' in PROJECT
>> > > > INFORMATION is 2008, and I've been unable to figure out why 
>> > > > the Gantt is one
>> > > > year ahead.  Same is true when I click on the Calendar 
>> > > > view.  I checked to
>> > > > see if my version was missing a service update, but I am 
>> > > > up-to-date w/ the
>> > > > latest patch.
date: Thu, 2 Oct 2008 18:17:29 -0400   author:   JulieS

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us