OK, I am a beginner I have 2 releases. v1.0 and 1.1 If I create a milestone (task - 0 time) for end of v1.0 can I just then like all the v1.1 tasks to start after the milestone? they will not start at theat exact time? correct? I can just use that as a starting guide for v1.1? thanks
Hi, Yes to all. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "greg" wrote in message news:OEWbHmnGJHA.2580@TK2MSFTNGP05.phx.gbl... > OK, I am a beginner > I have 2 releases. v1.0 and 1.1 > If I create a milestone (task - 0 time) for end of v1.0 > can I just then like all the v1.1 tasks to start after the milestone? > they will not start at theat exact time? correct? > I can just use that as a starting guide for v1.1? > thanks >