Re: Tas Numbers Out of Sequence (Part 2)
You're welcome, Scrufnut.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Scrufnut" wrote in message
news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
> Thanks Jan, it worked! Appreciate the assistance.
>
> "Jan De Messemaeker" wrote:
>
>> Good.
>>
>> Then I can tell you how to renumber automatically - providing the sorting
>> resopected the outline structure (meaning each task is still raked below
>> its
>> summary task)
>> Foirst take a backup since there is no turning back
>> Go to Project, Sort, Sort by...
>> Make sure both checkboxes below are on
>> - Keep outline structure
>> - Permanently renumber tasks.
>> That does it
>> If the sort has ranged the tasks out of their outline structure there is
>> no
>> automatic renumbering, sorry.
>>
>> Hope this helps,
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Scrufnut" wrote in message
>> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
>> > MS Project 2003.
>> >
>> > "Jan De Messemaeker" wrote:
>> >
>> >> Hi,
>> >>
>> >> Is that Project 2007 or not?
>> >> It used to work great but 2007 has a bug in this area.
>> >>
>> >> --
>> >> Jan De Messemaeker
>> >> Microsoft Project Most Valuable Professional
>> >> +32 495 300 620
>> >> For availability check:
>> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> "Scrufnut" wrote in message
>> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
>> >> > What Jan suggested I do worked great however it was not actually
>> >> > what I
>> >> > was
>> >> > trying to accomplish after all. It did reorder the tasks by their
>> >> > ID
>> >> > number
>> >> > but what I guess I wanted to do was, becasue the tasks themselves
>> >> > are
>> >> > already
>> >> > in the proper order, was to reassign new task ID #s based on the
>> >> > order
>> >> > that
>> >> > tasks are presently in.
>> >> >
>> >> > Is this even possible?
>> >> >
>> >>
>> >>
>> >>
>>
>>
>>
date: Sat, 6 Sep 2008 08:14:34 +0200
author: Jan De Messemaeker
Re: Tas Numbers Out of Sequence (Part 2)
I've had the same problem. I'm using Project 2007 Standard. When I select
the resort and premanent renumber option, it does the sort and renumber;
however, after I close and reopen the file, the numbers reverts back to the
original ID numbers. Has MS develope a patch for this problem?
--
Joel
"Jan De Messemaeker" wrote:
> You're welcome, Scrufnut.
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Scrufnut" wrote in message
> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
> > Thanks Jan, it worked! Appreciate the assistance.
> >
> > "Jan De Messemaeker" wrote:
> >
> >> Good.
> >>
> >> Then I can tell you how to renumber automatically - providing the sorting
> >> resopected the outline structure (meaning each task is still raked below
> >> its
> >> summary task)
> >> Foirst take a backup since there is no turning back
> >> Go to Project, Sort, Sort by...
> >> Make sure both checkboxes below are on
> >> - Keep outline structure
> >> - Permanently renumber tasks.
> >> That does it
> >> If the sort has ranged the tasks out of their outline structure there is
> >> no
> >> automatic renumbering, sorry.
> >>
> >> Hope this helps,
> >>
> >> --
> >> Jan De Messemaeker
> >> Microsoft Project Most Valuable Professional
> >> +32 495 300 620
> >> For availability check:
> >> http://users.online.be/prom-ade/Calendar.pdf
> >> "Scrufnut" wrote in message
> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
> >> > MS Project 2003.
> >> >
> >> > "Jan De Messemaeker" wrote:
> >> >
> >> >> Hi,
> >> >>
> >> >> Is that Project 2007 or not?
> >> >> It used to work great but 2007 has a bug in this area.
> >> >>
> >> >> --
> >> >> Jan De Messemaeker
> >> >> Microsoft Project Most Valuable Professional
> >> >> +32 495 300 620
> >> >> For availability check:
> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> "Scrufnut" wrote in message
> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
> >> >> > What Jan suggested I do worked great however it was not actually
> >> >> > what I
> >> >> > was
> >> >> > trying to accomplish after all. It did reorder the tasks by their
> >> >> > ID
> >> >> > number
> >> >> > but what I guess I wanted to do was, becasue the tasks themselves
> >> >> > are
> >> >> > already
> >> >> > in the proper order, was to reassign new task ID #s based on the
> >> >> > order
> >> >> > that
> >> >> > tasks are presently in.
> >> >> >
> >> >> > Is this even possible?
> >> >> >
> >> >>
> >> >>
> >> >>
> >>
> >>
> >>
>
>
>
date: Mon, 8 Sep 2008 07:53:01 -0700
author: Joel
Re: Tas Numbers Out of Sequence (Part 2)
Hello Joel,
In quick testing with Project 2007 with SP-1 and the Infrastructure
update installed, I see what you report. Sorry, neither seems to
have corrected that issue. I believe those are the latest patches.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Joel" wrote in message
news:F434EB91-8F44-479C-AD70-5AFEE2F020CD@microsoft.com...
> I've had the same problem. I'm using Project 2007 Standard. When
> I select
> the resort and premanent renumber option, it does the sort and
> renumber;
> however, after I close and reopen the file, the numbers reverts
> back to the
> original ID numbers. Has MS develope a patch for this problem?
> --
> Joel
>
>
> "Jan De Messemaeker" wrote:
>
>> You're welcome, Scrufnut.
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Scrufnut" wrote in message
>> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
>> > Thanks Jan, it worked! Appreciate the assistance.
>> >
>> > "Jan De Messemaeker" wrote:
>> >
>> >> Good.
>> >>
>> >> Then I can tell you how to renumber automatically - providing
>> >> the sorting
>> >> resopected the outline structure (meaning each task is still
>> >> raked below
>> >> its
>> >> summary task)
>> >> Foirst take a backup since there is no turning back
>> >> Go to Project, Sort, Sort by...
>> >> Make sure both checkboxes below are on
>> >> - Keep outline structure
>> >> - Permanently renumber tasks.
>> >> That does it
>> >> If the sort has ranged the tasks out of their outline
>> >> structure there is
>> >> no
>> >> automatic renumbering, sorry.
>> >>
>> >> Hope this helps,
>> >>
>> >> --
>> >> Jan De Messemaeker
>> >> Microsoft Project Most Valuable Professional
>> >> +32 495 300 620
>> >> For availability check:
>> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> "Scrufnut" wrote in
>> >> message
>> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
>> >> > MS Project 2003.
>> >> >
>> >> > "Jan De Messemaeker" wrote:
>> >> >
>> >> >> Hi,
>> >> >>
>> >> >> Is that Project 2007 or not?
>> >> >> It used to work great but 2007 has a bug in this area.
>> >> >>
>> >> >> --
>> >> >> Jan De Messemaeker
>> >> >> Microsoft Project Most Valuable Professional
>> >> >> +32 495 300 620
>> >> >> For availability check:
>> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> "Scrufnut" wrote in
>> >> >> message
>> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
>> >> >> > What Jan suggested I do worked great however it was not
>> >> >> > actually
>> >> >> > what I
>> >> >> > was
>> >> >> > trying to accomplish after all. It did reorder the tasks
>> >> >> > by their
>> >> >> > ID
>> >> >> > number
>> >> >> > but what I guess I wanted to do was, becasue the tasks
>> >> >> > themselves
>> >> >> > are
>> >> >> > already
>> >> >> > in the proper order, was to reassign new task ID #s based
>> >> >> > on the
>> >> >> > order
>> >> >> > that
>> >> >> > tasks are presently in.
>> >> >> >
>> >> >> > Is this even possible?
>> >> >> >
>> >> >>
>> >> >>
>> >> >>
>> >>
>> >>
>> >>
>>
>>
>>
date: Wed, 10 Sep 2008 17:47:48 -0400
author: JulieS
Re: Tas Numbers Out of Sequence (Part 2)
Julie, thanks for the confirmation, but this "bug" really causes lots of
problems for my clients and me. This feature works in Project 2003, so MS
should have a "fix" for the problem by going back to version 2003. There are
a few other nuisance problems with printing that worked in version 2003, but
not in 2007.
Begging for a patch,
Joel
--
Joel
"JulieS" wrote:
> Hello Joel,
>
> In quick testing with Project 2007 with SP-1 and the Infrastructure
> update installed, I see what you report. Sorry, neither seems to
> have corrected that issue. I believe those are the latest patches.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
>
> "Joel" wrote in message
> news:F434EB91-8F44-479C-AD70-5AFEE2F020CD@microsoft.com...
> > I've had the same problem. I'm using Project 2007 Standard. When
> > I select
> > the resort and premanent renumber option, it does the sort and
> > renumber;
> > however, after I close and reopen the file, the numbers reverts
> > back to the
> > original ID numbers. Has MS develope a patch for this problem?
> > --
> > Joel
> >
> >
> > "Jan De Messemaeker" wrote:
> >
> >> You're welcome, Scrufnut.
> >>
> >> --
> >> Jan De Messemaeker
> >> Microsoft Project Most Valuable Professional
> >> +32 495 300 620
> >> For availability check:
> >> http://users.online.be/prom-ade/Calendar.pdf
> >> "Scrufnut" wrote in message
> >> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
> >> > Thanks Jan, it worked! Appreciate the assistance.
> >> >
> >> > "Jan De Messemaeker" wrote:
> >> >
> >> >> Good.
> >> >>
> >> >> Then I can tell you how to renumber automatically - providing
> >> >> the sorting
> >> >> resopected the outline structure (meaning each task is still
> >> >> raked below
> >> >> its
> >> >> summary task)
> >> >> Foirst take a backup since there is no turning back
> >> >> Go to Project, Sort, Sort by...
> >> >> Make sure both checkboxes below are on
> >> >> - Keep outline structure
> >> >> - Permanently renumber tasks.
> >> >> That does it
> >> >> If the sort has ranged the tasks out of their outline
> >> >> structure there is
> >> >> no
> >> >> automatic renumbering, sorry.
> >> >>
> >> >> Hope this helps,
> >> >>
> >> >> --
> >> >> Jan De Messemaeker
> >> >> Microsoft Project Most Valuable Professional
> >> >> +32 495 300 620
> >> >> For availability check:
> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> "Scrufnut" wrote in
> >> >> message
> >> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
> >> >> > MS Project 2003.
> >> >> >
> >> >> > "Jan De Messemaeker" wrote:
> >> >> >
> >> >> >> Hi,
> >> >> >>
> >> >> >> Is that Project 2007 or not?
> >> >> >> It used to work great but 2007 has a bug in this area.
> >> >> >>
> >> >> >> --
> >> >> >> Jan De Messemaeker
> >> >> >> Microsoft Project Most Valuable Professional
> >> >> >> +32 495 300 620
> >> >> >> For availability check:
> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> >> "Scrufnut" wrote in
> >> >> >> message
> >> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
> >> >> >> > What Jan suggested I do worked great however it was not
> >> >> >> > actually
> >> >> >> > what I
> >> >> >> > was
> >> >> >> > trying to accomplish after all. It did reorder the tasks
> >> >> >> > by their
> >> >> >> > ID
> >> >> >> > number
> >> >> >> > but what I guess I wanted to do was, becasue the tasks
> >> >> >> > themselves
> >> >> >> > are
> >> >> >> > already
> >> >> >> > in the proper order, was to reassign new task ID #s based
> >> >> >> > on the
> >> >> >> > order
> >> >> >> > that
> >> >> >> > tasks are presently in.
> >> >> >> >
> >> >> >> > Is this even possible?
> >> >> >> >
> >> >> >>
> >> >> >>
> >> >> >>
> >> >>
> >> >>
> >> >>
> >>
> >>
> >>
>
>
>
date: Wed, 10 Sep 2008 16:20:05 -0700
author: Joel
Re: Tas Numbers Out of Sequence (Part 2)
Hi Joel,
Sorry, I have no pull with Microsoft and their bug fixes. You can
certainly contact Microsoft support directly and they may have
better news than I or there may be a hot-fix that they have
available that I am unaware of.
If you have not installed SP-1 and the infrastructure update, I
suggest you do so -- it has solved some other problems -- sadly --
just not the renumbering one.
Sorry I couldn't be of more assistance.
Julie
"Joel" wrote in message
news:4481F498-CAD4-49C6-BD3D-BBD8E8BA9560@microsoft.com...
> Julie, thanks for the confirmation, but this "bug" really causes
> lots of
> problems for my clients and me. This feature works in Project
> 2003, so MS
> should have a "fix" for the problem by going back to version 2003.
> There are
> a few other nuisance problems with printing that worked in version
> 2003, but
> not in 2007.
>
> Begging for a patch,
>
> Joel
> --
> Joel
>
>
> "JulieS" wrote:
>
>> Hello Joel,
>>
>> In quick testing with Project 2007 with SP-1 and the
>> Infrastructure
>> update installed, I see what you report. Sorry, neither seems to
>> have corrected that issue. I believe those are the latest
>> patches.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>> "Joel" wrote in message
>> news:F434EB91-8F44-479C-AD70-5AFEE2F020CD@microsoft.com...
>> > I've had the same problem. I'm using Project 2007 Standard.
>> > When
>> > I select
>> > the resort and premanent renumber option, it does the sort and
>> > renumber;
>> > however, after I close and reopen the file, the numbers reverts
>> > back to the
>> > original ID numbers. Has MS develope a patch for this problem?
>> > --
>> > Joel
>> >
>> >
>> > "Jan De Messemaeker" wrote:
>> >
>> >> You're welcome, Scrufnut.
>> >>
>> >> --
>> >> Jan De Messemaeker
>> >> Microsoft Project Most Valuable Professional
>> >> +32 495 300 620
>> >> For availability check:
>> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> "Scrufnut" wrote in
>> >> message
>> >> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
>> >> > Thanks Jan, it worked! Appreciate the assistance.
>> >> >
>> >> > "Jan De Messemaeker" wrote:
>> >> >
>> >> >> Good.
>> >> >>
>> >> >> Then I can tell you how to renumber automatically -
>> >> >> providing
>> >> >> the sorting
>> >> >> resopected the outline structure (meaning each task is
>> >> >> still
>> >> >> raked below
>> >> >> its
>> >> >> summary task)
>> >> >> Foirst take a backup since there is no turning back
>> >> >> Go to Project, Sort, Sort by...
>> >> >> Make sure both checkboxes below are on
>> >> >> - Keep outline structure
>> >> >> - Permanently renumber tasks.
>> >> >> That does it
>> >> >> If the sort has ranged the tasks out of their outline
>> >> >> structure there is
>> >> >> no
>> >> >> automatic renumbering, sorry.
>> >> >>
>> >> >> Hope this helps,
>> >> >>
>> >> >> --
>> >> >> Jan De Messemaeker
>> >> >> Microsoft Project Most Valuable Professional
>> >> >> +32 495 300 620
>> >> >> For availability check:
>> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> "Scrufnut" wrote in
>> >> >> message
>> >> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
>> >> >> > MS Project 2003.
>> >> >> >
>> >> >> > "Jan De Messemaeker" wrote:
>> >> >> >
>> >> >> >> Hi,
>> >> >> >>
>> >> >> >> Is that Project 2007 or not?
>> >> >> >> It used to work great but 2007 has a bug in this area.
>> >> >> >>
>> >> >> >> --
>> >> >> >> Jan De Messemaeker
>> >> >> >> Microsoft Project Most Valuable Professional
>> >> >> >> +32 495 300 620
>> >> >> >> For availability check:
>> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> >> "Scrufnut" wrote in
>> >> >> >> message
>> >> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
>> >> >> >> > What Jan suggested I do worked great however it was
>> >> >> >> > not
>> >> >> >> > actually
>> >> >> >> > what I
>> >> >> >> > was
>> >> >> >> > trying to accomplish after all. It did reorder the
>> >> >> >> > tasks
>> >> >> >> > by their
>> >> >> >> > ID
>> >> >> >> > number
>> >> >> >> > but what I guess I wanted to do was, becasue the tasks
>> >> >> >> > themselves
>> >> >> >> > are
>> >> >> >> > already
>> >> >> >> > in the proper order, was to reassign new task ID #s
>> >> >> >> > based
>> >> >> >> > on the
>> >> >> >> > order
>> >> >> >> > that
>> >> >> >> > tasks are presently in.
>> >> >> >> >
>> >> >> >> > Is this even possible?
>> >> >> >> >
>> >> >> >>
>> >> >> >>
>> >> >> >>
>> >> >>
>> >> >>
>> >> >>
>> >>
>> >>
>> >>
>>
>>
>>
date: Wed, 10 Sep 2008 20:12:42 -0400
author: JulieS
Re: Tas Numbers Out of Sequence (Part 2)
Julie, who at MS will listen? How do I contact him/her?
--
Joel
"JulieS" wrote:
> Hi Joel,
>
> Sorry, I have no pull with Microsoft and their bug fixes. You can
> certainly contact Microsoft support directly and they may have
> better news than I or there may be a hot-fix that they have
> available that I am unaware of.
>
> If you have not installed SP-1 and the infrastructure update, I
> suggest you do so -- it has solved some other problems -- sadly --
> just not the renumbering one.
>
> Sorry I couldn't be of more assistance.
>
> Julie
> "Joel" wrote in message
> news:4481F498-CAD4-49C6-BD3D-BBD8E8BA9560@microsoft.com...
> > Julie, thanks for the confirmation, but this "bug" really causes
> > lots of
> > problems for my clients and me. This feature works in Project
> > 2003, so MS
> > should have a "fix" for the problem by going back to version 2003.
> > There are
> > a few other nuisance problems with printing that worked in version
> > 2003, but
> > not in 2007.
> >
> > Begging for a patch,
> >
> > Joel
> > --
> > Joel
> >
> >
> > "JulieS" wrote:
> >
> >> Hello Joel,
> >>
> >> In quick testing with Project 2007 with SP-1 and the
> >> Infrastructure
> >> update installed, I see what you report. Sorry, neither seems to
> >> have corrected that issue. I believe those are the latest
> >> patches.
> >>
> >> I hope this helps. Let us know how you get along.
> >>
> >> Julie
> >> Project MVP
> >>
> >> Visit http://project.mvps.org/ for the FAQs and additional
> >> information about Microsoft Project
> >>
> >> "Joel" wrote in message
> >> news:F434EB91-8F44-479C-AD70-5AFEE2F020CD@microsoft.com...
> >> > I've had the same problem. I'm using Project 2007 Standard.
> >> > When
> >> > I select
> >> > the resort and premanent renumber option, it does the sort and
> >> > renumber;
> >> > however, after I close and reopen the file, the numbers reverts
> >> > back to the
> >> > original ID numbers. Has MS develope a patch for this problem?
> >> > --
> >> > Joel
> >> >
> >> >
> >> > "Jan De Messemaeker" wrote:
> >> >
> >> >> You're welcome, Scrufnut.
> >> >>
> >> >> --
> >> >> Jan De Messemaeker
> >> >> Microsoft Project Most Valuable Professional
> >> >> +32 495 300 620
> >> >> For availability check:
> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> "Scrufnut" wrote in
> >> >> message
> >> >> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
> >> >> > Thanks Jan, it worked! Appreciate the assistance.
> >> >> >
> >> >> > "Jan De Messemaeker" wrote:
> >> >> >
> >> >> >> Good.
> >> >> >>
> >> >> >> Then I can tell you how to renumber automatically -
> >> >> >> providing
> >> >> >> the sorting
> >> >> >> resopected the outline structure (meaning each task is
> >> >> >> still
> >> >> >> raked below
> >> >> >> its
> >> >> >> summary task)
> >> >> >> Foirst take a backup since there is no turning back
> >> >> >> Go to Project, Sort, Sort by...
> >> >> >> Make sure both checkboxes below are on
> >> >> >> - Keep outline structure
> >> >> >> - Permanently renumber tasks.
> >> >> >> That does it
> >> >> >> If the sort has ranged the tasks out of their outline
> >> >> >> structure there is
> >> >> >> no
> >> >> >> automatic renumbering, sorry.
> >> >> >>
> >> >> >> Hope this helps,
> >> >> >>
> >> >> >> --
> >> >> >> Jan De Messemaeker
> >> >> >> Microsoft Project Most Valuable Professional
> >> >> >> +32 495 300 620
> >> >> >> For availability check:
> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> >> "Scrufnut" wrote in
> >> >> >> message
> >> >> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
> >> >> >> > MS Project 2003.
> >> >> >> >
> >> >> >> > "Jan De Messemaeker" wrote:
> >> >> >> >
> >> >> >> >> Hi,
> >> >> >> >>
> >> >> >> >> Is that Project 2007 or not?
> >> >> >> >> It used to work great but 2007 has a bug in this area.
> >> >> >> >>
> >> >> >> >> --
> >> >> >> >> Jan De Messemaeker
> >> >> >> >> Microsoft Project Most Valuable Professional
> >> >> >> >> +32 495 300 620
> >> >> >> >> For availability check:
> >> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
> >> >> >> >> "Scrufnut" wrote in
> >> >> >> >> message
> >> >> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
> >> >> >> >> > What Jan suggested I do worked great however it was
> >> >> >> >> > not
> >> >> >> >> > actually
> >> >> >> >> > what I
> >> >> >> >> > was
> >> >> >> >> > trying to accomplish after all. It did reorder the
> >> >> >> >> > tasks
> >> >> >> >> > by their
> >> >> >> >> > ID
> >> >> >> >> > number
> >> >> >> >> > but what I guess I wanted to do was, becasue the tasks
> >> >> >> >> > themselves
> >> >> >> >> > are
> >> >> >> >> > already
> >> >> >> >> > in the proper order, was to reassign new task ID #s
> >> >> >> >> > based
> >> >> >> >> > on the
> >> >> >> >> > order
> >> >> >> >> > that
> >> >> >> >> > tasks are presently in.
> >> >> >> >> >
> >> >> >> >> > Is this even possible?
> >> >> >> >> >
> >> >> >> >>
> >> >> >> >>
> >> >> >> >>
> >> >> >>
> >> >> >>
> >> >> >>
> >> >>
> >> >>
> >> >>
> >>
> >>
> >>
>
>
>
date: Thu, 11 Sep 2008 01:26:00 -0700
author: Joel
Re: Tas Numbers Out of Sequence (Part 2)
Hi Joel,
You'll need to contact MS through any service agreement you may have
or you'll need to contact tech support. In Project, see Help > About
Tech Support for details on contacting MS. There is a support fee I
believe.
Julie
"Joel" wrote in message
news:43F90424-FFF8-4CFB-92C4-3EA20F3C9211@microsoft.com...
> Julie, who at MS will listen? How do I contact him/her?
> --
> Joel
>
>
> "JulieS" wrote:
>
>> Hi Joel,
>>
>> Sorry, I have no pull with Microsoft and their bug fixes. You
>> can
>> certainly contact Microsoft support directly and they may have
>> better news than I or there may be a hot-fix that they have
>> available that I am unaware of.
>>
>> If you have not installed SP-1 and the infrastructure update, I
>> suggest you do so -- it has solved some other problems --
>> sadly --
>> just not the renumbering one.
>>
>> Sorry I couldn't be of more assistance.
>>
>> Julie
>> "Joel" wrote in message
>> news:4481F498-CAD4-49C6-BD3D-BBD8E8BA9560@microsoft.com...
>> > Julie, thanks for the confirmation, but this "bug" really
>> > causes
>> > lots of
>> > problems for my clients and me. This feature works in Project
>> > 2003, so MS
>> > should have a "fix" for the problem by going back to version
>> > 2003.
>> > There are
>> > a few other nuisance problems with printing that worked in
>> > version
>> > 2003, but
>> > not in 2007.
>> >
>> > Begging for a patch,
>> >
>> > Joel
>> > --
>> > Joel
>> >
>> >
>> > "JulieS" wrote:
>> >
>> >> Hello Joel,
>> >>
>> >> In quick testing with Project 2007 with SP-1 and the
>> >> Infrastructure
>> >> update installed, I see what you report. Sorry, neither seems
>> >> to
>> >> have corrected that issue. I believe those are the latest
>> >> patches.
>> >>
>> >> I hope this helps. Let us know how you get along.
>> >>
>> >> Julie
>> >> Project MVP
>> >>
>> >> Visit http://project.mvps.org/ for the FAQs and additional
>> >> information about Microsoft Project
>> >>
>> >> "Joel" wrote in message
>> >> news:F434EB91-8F44-479C-AD70-5AFEE2F020CD@microsoft.com...
>> >> > I've had the same problem. I'm using Project 2007 Standard.
>> >> > When
>> >> > I select
>> >> > the resort and premanent renumber option, it does the sort
>> >> > and
>> >> > renumber;
>> >> > however, after I close and reopen the file, the numbers
>> >> > reverts
>> >> > back to the
>> >> > original ID numbers. Has MS develope a patch for this
>> >> > problem?
>> >> > --
>> >> > Joel
>> >> >
>> >> >
>> >> > "Jan De Messemaeker" wrote:
>> >> >
>> >> >> You're welcome, Scrufnut.
>> >> >>
>> >> >> --
>> >> >> Jan De Messemaeker
>> >> >> Microsoft Project Most Valuable Professional
>> >> >> +32 495 300 620
>> >> >> For availability check:
>> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> "Scrufnut" wrote in
>> >> >> message
>> >> >> news:FAC5607E-C164-4731-98F4-D8C9B9C67794@microsoft.com...
>> >> >> > Thanks Jan, it worked! Appreciate the assistance.
>> >> >> >
>> >> >> > "Jan De Messemaeker" wrote:
>> >> >> >
>> >> >> >> Good.
>> >> >> >>
>> >> >> >> Then I can tell you how to renumber automatically -
>> >> >> >> providing
>> >> >> >> the sorting
>> >> >> >> resopected the outline structure (meaning each task is
>> >> >> >> still
>> >> >> >> raked below
>> >> >> >> its
>> >> >> >> summary task)
>> >> >> >> Foirst take a backup since there is no turning back
>> >> >> >> Go to Project, Sort, Sort by...
>> >> >> >> Make sure both checkboxes below are on
>> >> >> >> - Keep outline structure
>> >> >> >> - Permanently renumber tasks.
>> >> >> >> That does it
>> >> >> >> If the sort has ranged the tasks out of their outline
>> >> >> >> structure there is
>> >> >> >> no
>> >> >> >> automatic renumbering, sorry.
>> >> >> >>
>> >> >> >> Hope this helps,
>> >> >> >>
>> >> >> >> --
>> >> >> >> Jan De Messemaeker
>> >> >> >> Microsoft Project Most Valuable Professional
>> >> >> >> +32 495 300 620
>> >> >> >> For availability check:
>> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> >> "Scrufnut" wrote in
>> >> >> >> message
>> >> >> >> news:4B9B7CE2-A679-4CD1-B874-7015E07A9D2F@microsoft.com...
>> >> >> >> > MS Project 2003.
>> >> >> >> >
>> >> >> >> > "Jan De Messemaeker" wrote:
>> >> >> >> >
>> >> >> >> >> Hi,
>> >> >> >> >>
>> >> >> >> >> Is that Project 2007 or not?
>> >> >> >> >> It used to work great but 2007 has a bug in this
>> >> >> >> >> area.
>> >> >> >> >>
>> >> >> >> >> --
>> >> >> >> >> Jan De Messemaeker
>> >> >> >> >> Microsoft Project Most Valuable Professional
>> >> >> >> >> +32 495 300 620
>> >> >> >> >> For availability check:
>> >> >> >> >> http://users.online.be/prom-ade/Calendar.pdf
>> >> >> >> >> "Scrufnut" wrote
>> >> >> >> >> in
>> >> >> >> >> message
>> >> >> >> >> news:99A07AC0-7233-4B76-BE7E-E32F6C46486C@microsoft.com...
>> >> >> >> >> > What Jan suggested I do worked great however it was
>> >> >> >> >> > not
>> >> >> >> >> > actually
>> >> >> >> >> > what I
>> >> >> >> >> > was
>> >> >> >> >> > trying to accomplish after all. It did reorder the
>> >> >> >> >> > tasks
>> >> >> >> >> > by their
>> >> >> >> >> > ID
>> >> >> >> >> > number
>> >> >> >> >> > but what I guess I wanted to do was, becasue the
>> >> >> >> >> > tasks
>> >> >> >> >> > themselves
>> >> >> >> >> > are
>> >> >> >> >> > already
>> >> >> >> >> > in the proper order, was to reassign new task ID #s
>> >> >> >> >> > based
>> >> >> >> >> > on the
>> >> >> >> >> > order
>> >> >> >> >> > that
>> >> >> >> >> > tasks are presently in.
>> >> >> >> >> >
>> >> >> >> >> > Is this even possible?
>> >> >> >> >> >
>> >> >> >> >>
>> >> >> >> >>
>> >> >> >> >>
>> >> >> >>
>> >> >> >>
>> >> >> >>
>> >> >>
>> >> >>
>> >> >>
>> >>
>> >>
>> >>
>>
>>
>>
date: Thu, 11 Sep 2008 06:56:43 -0400
author: JulieS
|
|