Re: Task Numbers are out of sequence
Hi Scrufnut,
You will have to resort them in the original order, but in the Sort dialog,
select to permanently renumber the tasks.
Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
Scrufnut wrote:
> Jan,
>
> Actually this did not do what I was trying to accomplish after all.
> It did reorder the tasks by their ID number but what I guess I wanted
> to do was, becasue the tasks themselves are already in the proper
> order, was to reassign new task ID #s based on the order that tasks
> are presently in.
>
> Is this even possible?
>
> "Jan De Messemaeker" wrote:
>
>> Hi,
>>
>> Project menu, Sort, Sort by ID
>> Greetings,
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Scrufnut" wrote in message
>> news:1559BA7A-A695-4F13-94AF-A3B91EE5D22C@microsoft.com...
>>> I have received a very large project schedule from a subcontractor
>>> to import.
>>> A number of task line item numbers are out of order (in other words
>>> Line Item
>>> 1661 follows Line Item 2671). Is there a way to sort these?
date: Fri, 5 Sep 2008 20:31:11 +0100
author: Mike Glen glenATmvps.org
|
|