Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Fri, 5 Sep 2008 06:46:10 -0700,    group: microsoft.public.project        back       


Task bar is not displaying in Gantt Chart   
Hi there, 

I have copied another person's MS Project Plan (version 2003) and then 
modified it with additional tasks for a similar project I am managing. 
Inexplicably some of the tasks are not displaying in the Gantt Chart. 
I have compared the tasks not displaying with tasks that are displaying by 
going to the task information on both of them and also to the view menu and 
compariing the calendar information - the tasks that are not displaying do 
not have 'hide task bar' checked. 
It is very perplexing - but I'm sure there is a simple solution!

Any help greatly appreciated. 

Alayna
date: Fri, 5 Sep 2008 06:46:10 -0700   author:   Alayna

Re: Task bar is not displaying in Gantt Chart   
On Sep 5, 3:46 pm, Alayna  wrote:
> Hi there,
>
> I have copied another person's MS Project Plan (version 2003) and then
> modified it with additional tasks for a similar project I am managing.
> Inexplicably some of the tasks are not displaying in the Gantt Chart.
> I have compared the tasks not displaying with tasks that are displaying by
> going to the task information on both of them and also to the view menu and
> compariing the calendar information - the tasks that are not displaying do
> not have 'hide task bar' checked.
> It is very perplexing - but I'm sure there is a simple solution!
>
> Any help greatly appreciated.
>
> Alayn


Hi

Are you sure that you are displaying all outline levels -- check on
the toolbar ....

Andre
date: Fri, 5 Sep 2008 07:02:55 -0700 (PDT)   author:   ProjmanZA

Re: Task bar is not displaying in Gantt Chart   
Hi Andre, 

Thanks for your post. 

Since posting my query, about 1 minute ago - I found out what the problem 
was. 
The person who had produced the Gantt chart before me - that I have copied 
and am using as a template - had set some of the bar formats so they 
displayed 'white' under the colour option. So this meant I couldn't see the 
bars displayed, even if they were there. 

I have changed the colour of all bars under the Format menu/then chose 'Bar'. 

And presto - no more problem. 

Thanks again, 

Alayna

"ProjmanZA" wrote:

> On Sep 5, 3:46 pm, Alayna  wrote:
> > Hi there,
> >
> > I have copied another person's MS Project Plan (version 2003) and then
> > modified it with additional tasks for a similar project I am managing.
> > Inexplicably some of the tasks are not displaying in the Gantt Chart.
> > I have compared the tasks not displaying with tasks that are displaying by
> > going to the task information on both of them and also to the view menu and
> > compariing the calendar information - the tasks that are not displaying do
> > not have 'hide task bar' checked.
> > It is very perplexing - but I'm sure there is a simple solution!
> >
> > Any help greatly appreciated.
> >
> > Alayn
> 
> 
> Hi
> 
> Are you sure that you are displaying all outline levels -- check on
> the toolbar ....
> 
> Andre
> 
> 
> 
> 
> 
> 
> 
> 
>
date: Fri, 5 Sep 2008 07:28:05 -0700   author:   Alayna

Re: Task bar is not displaying in Gantt Chart   
On Sep 5, 4:28 pm, Alayna  wrote:
> Hi Andre,
>
> Thanks for your post.
>
> Since posting my query, about 1 minute ago - I found out what the problem
> was.
> The person who had produced the Gantt chart before me - that I have copied
> and am using as a template - had set some of the bar formats so they
> displayed 'white' under the colour option. So this meant I couldn't see the
> bars displayed, even if they were there.
>
> I have changed the colour of all bars under the Format menu/then chose 'Bar'.
>
> And presto - no more problem.
>
> Thanks again,
>
> Alayna
>
>
>
> "ProjmanZA" wrote:
> > On Sep 5, 3:46 pm, Alayna  wrote:
> > > Hi there,
>
> > > I have copied another person's MS Project Plan (version 2003) and then
> > > modified it with additional tasks for a similar project I am managing> > > Inexplicably some of the tasks are not displaying in the Gantt Chart.
> > > I have compared the tasks not displaying with tasks that are displaying by
> > > going to the task information on both of them and also to the view menu and
> > > compariing the calendar information - the tasks that are not displaying do
> > > not have 'hide task bar' checked.
> > > It is very perplexing - but I'm sure there is a simple solution!
>
> > > Any help greatly appreciated.
>
> > > Alayn
>
> > Hi
>
> > Are you sure that you are displaying all outline levels -- check on
> > the toolbar ....
>
> > Andre- Hide quoted text -
>
> - Show quoted text -

Lol -- Thats would have been a "tricky" one to resolve have you not
found that !!!

Well Done !!
date: Sun, 7 Sep 2008 22:51:47 -0700 (PDT)   author:   ProjmanZA