Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Fri, 5 Sep 2008 05:53:03 -0700,    group: microsoft.public.project        back       


Recording the Actuals - Help Needed   
Hi there,

Fairly new to Project 2007 - but not to project management. I wonder if 
someone can shed some light on the following.

I have a task on a plan with resource ASH 75% loading. The task was due to 
take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put extra 
hours in and finished the task early but using the full time allocation. When 
I enter the actual end date / hours taken etc. the calculations do one of two 
things.

1. If I say complete 100%, 0 remaining and actual finish date the task 
duration changes to 6 days (fine as the elapsed is 6 days), but the actual 
hours change to 36.
2. If I say complete 100%, 0 remaining, 48hours actual and actual finish 
date the task duration changes to 8 days, actual hours 48 but end date 
changes back to 8 day elapsed from start.

I was hoping to show that the task has finished early but keep the actual 
hours correct.

Any ideas??

Regs
 
-- 
Andy H
JAZ Computer Services
www.jazcomputerservices.co.uk
date: Fri, 5 Sep 2008 05:53:03 -0700   author:   Andy H

Re: Recording the Actuals - Help Needed   
Hi,

Simplest solution (there are several) is to fuirst set the assignment units 
to 100% and then put tha task to 100% complete.
HTH
-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Andy H"  wrote in message 
news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com...
> Hi there,
>
> Fairly new to Project 2007 - but not to project management. I wonder if
> someone can shed some light on the following.
>
> I have a task on a plan with resource ASH 75% loading. The task was due to
> take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put 
> extra
> hours in and finished the task early but using the full time allocation. 
> When
> I enter the actual end date / hours taken etc. the calculations do one of 
> two
> things.
>
> 1. If I say complete 100%, 0 remaining and actual finish date the task
> duration changes to 6 days (fine as the elapsed is 6 days), but the actual
> hours change to 36.
> 2. If I say complete 100%, 0 remaining, 48hours actual and actual finish
> date the task duration changes to 8 days, actual hours 48 but end date
> changes back to 8 day elapsed from start.
>
> I was hoping to show that the task has finished early but keep the actual
> hours correct.
>
> Any ideas??
>
> Regs
>
> -- 
> Andy H
> JAZ Computer Services
> www.jazcomputerservices.co.uk
date: Fri, 5 Sep 2008 15:22:11 +0200   author:   Jan De Messemaeker

Re: Recording the Actuals - Help Needed   
Many thanks - new there had to be an easy answer - I now have a task showing 
finished before schedule with the same costing.

Thanks again.

-- 
Andy H
JAZ Computer Services
www.jazcomputerservices.co.uk


"Jan De Messemaeker" wrote:

> Hi,
> 
> Simplest solution (there are several) is to fuirst set the assignment units 
> to 100% and then put tha task to 100% complete.
> HTH
> -- 
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Andy H"  wrote in message 
> news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com...
> > Hi there,
> >
> > Fairly new to Project 2007 - but not to project management. I wonder if
> > someone can shed some light on the following.
> >
> > I have a task on a plan with resource ASH 75% loading. The task was due to
> > take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put 
> > extra
> > hours in and finished the task early but using the full time allocation. 
> > When
> > I enter the actual end date / hours taken etc. the calculations do one of 
> > two
> > things.
> >
> > 1. If I say complete 100%, 0 remaining and actual finish date the task
> > duration changes to 6 days (fine as the elapsed is 6 days), but the actual
> > hours change to 36.
> > 2. If I say complete 100%, 0 remaining, 48hours actual and actual finish
> > date the task duration changes to 8 days, actual hours 48 but end date
> > changes back to 8 day elapsed from start.
> >
> > I was hoping to show that the task has finished early but keep the actual
> > hours correct.
> >
> > Any ideas??
> >
> > Regs
> >
> > -- 
> > Andy H
> > JAZ Computer Services
> > www.jazcomputerservices.co.uk 
> 
> 
>
date: Fri, 5 Sep 2008 06:48:16 -0700   author:   Andy H

Re: Recording the Actuals - Help Needed   
You're welcome, Andy

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Andy H"  wrote in message 
news:1AC8E712-8405-496E-94C8-E51B20D23FCC@microsoft.com...
> Many thanks - new there had to be an easy answer - I now have a task 
> showing
> finished before schedule with the same costing.
>
> Thanks again.
>
> -- 
> Andy H
> JAZ Computer Services
> www.jazcomputerservices.co.uk
>
>
> "Jan De Messemaeker" wrote:
>
>> Hi,
>>
>> Simplest solution (there are several) is to fuirst set the assignment 
>> units
>> to 100% and then put tha task to 100% complete.
>> HTH
>> -- 
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Andy H"  wrote in message
>> news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com...
>> > Hi there,
>> >
>> > Fairly new to Project 2007 - but not to project management. I wonder if
>> > someone can shed some light on the following.
>> >
>> > I have a task on a plan with resource ASH 75% loading. The task was due 
>> > to
>> > take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put
>> > extra
>> > hours in and finished the task early but using the full time 
>> > allocation.
>> > When
>> > I enter the actual end date / hours taken etc. the calculations do one 
>> > of
>> > two
>> > things.
>> >
>> > 1. If I say complete 100%, 0 remaining and actual finish date the task
>> > duration changes to 6 days (fine as the elapsed is 6 days), but the 
>> > actual
>> > hours change to 36.
>> > 2. If I say complete 100%, 0 remaining, 48hours actual and actual 
>> > finish
>> > date the task duration changes to 8 days, actual hours 48 but end date
>> > changes back to 8 day elapsed from start.
>> >
>> > I was hoping to show that the task has finished early but keep the 
>> > actual
>> > hours correct.
>> >
>> > Any ideas??
>> >
>> > Regs
>> >
>> > -- 
>> > Andy H
>> > JAZ Computer Services
>> > www.jazcomputerservices.co.uk
>>
>>
>>
date: Fri, 5 Sep 2008 17:29:45 +0200   author:   Jan De Messemaeker

Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us