Hi there, Fairly new to Project 2007 - but not to project management. I wonder if someone can shed some light on the following. I have a task on a plan with resource ASH 75% loading. The task was due to take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put extra hours in and finished the task early but using the full time allocation. When I enter the actual end date / hours taken etc. the calculations do one of two things. 1. If I say complete 100%, 0 remaining and actual finish date the task duration changes to 6 days (fine as the elapsed is 6 days), but the actual hours change to 36. 2. If I say complete 100%, 0 remaining, 48hours actual and actual finish date the task duration changes to 8 days, actual hours 48 but end date changes back to 8 day elapsed from start. I was hoping to show that the task has finished early but keep the actual hours correct. Any ideas?? Regs -- Andy H JAZ Computer Services www.jazcomputerservices.co.uk
Hi, Simplest solution (there are several) is to fuirst set the assignment units to 100% and then put tha task to 100% complete. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Andy H" wrote in message news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com... > Hi there, > > Fairly new to Project 2007 - but not to project management. I wonder if > someone can shed some light on the following. > > I have a task on a plan with resource ASH 75% loading. The task was due to > take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put > extra > hours in and finished the task early but using the full time allocation. > When > I enter the actual end date / hours taken etc. the calculations do one of > two > things. > > 1. If I say complete 100%, 0 remaining and actual finish date the task > duration changes to 6 days (fine as the elapsed is 6 days), but the actual > hours change to 36. > 2. If I say complete 100%, 0 remaining, 48hours actual and actual finish > date the task duration changes to 8 days, actual hours 48 but end date > changes back to 8 day elapsed from start. > > I was hoping to show that the task has finished early but keep the actual > hours correct. > > Any ideas?? > > Regs > > -- > Andy H > JAZ Computer Services > www.jazcomputerservices.co.uk
Many thanks - new there had to be an easy answer - I now have a task showing finished before schedule with the same costing. Thanks again. -- Andy H JAZ Computer Services www.jazcomputerservices.co.uk "Jan De Messemaeker" wrote: > Hi, > > Simplest solution (there are several) is to fuirst set the assignment units > to 100% and then put tha task to 100% complete. > HTH > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "Andy H" wrote in message > news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com... > > Hi there, > > > > Fairly new to Project 2007 - but not to project management. I wonder if > > someone can shed some light on the following. > > > > I have a task on a plan with resource ASH 75% loading. The task was due to > > take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put > > extra > > hours in and finished the task early but using the full time allocation. > > When > > I enter the actual end date / hours taken etc. the calculations do one of > > two > > things. > > > > 1. If I say complete 100%, 0 remaining and actual finish date the task > > duration changes to 6 days (fine as the elapsed is 6 days), but the actual > > hours change to 36. > > 2. If I say complete 100%, 0 remaining, 48hours actual and actual finish > > date the task duration changes to 8 days, actual hours 48 but end date > > changes back to 8 day elapsed from start. > > > > I was hoping to show that the task has finished early but keep the actual > > hours correct. > > > > Any ideas?? > > > > Regs > > > > -- > > Andy H > > JAZ Computer Services > > www.jazcomputerservices.co.uk > > >
You're welcome, Andy -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Andy H" wrote in message news:1AC8E712-8405-496E-94C8-E51B20D23FCC@microsoft.com... > Many thanks - new there had to be an easy answer - I now have a task > showing > finished before schedule with the same costing. > > Thanks again. > > -- > Andy H > JAZ Computer Services > www.jazcomputerservices.co.uk > > > "Jan De Messemaeker" wrote: > >> Hi, >> >> Simplest solution (there are several) is to fuirst set the assignment >> units >> to 100% and then put tha task to 100% complete. >> HTH >> -- >> Jan De Messemaeker >> Microsoft Project Most Valuable Professional >> +32 495 300 620 >> For availability check: >> http://users.online.be/prom-ade/Calendar.pdf >> "Andy H" wrote in message >> news:54229272-CEC5-48C0-9FBB-F72C0E76FAE4@microsoft.com... >> > Hi there, >> > >> > Fairly new to Project 2007 - but not to project management. I wonder if >> > someone can shed some light on the following. >> > >> > I have a task on a plan with resource ASH 75% loading. The task was due >> > to >> > take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put >> > extra >> > hours in and finished the task early but using the full time >> > allocation. >> > When >> > I enter the actual end date / hours taken etc. the calculations do one >> > of >> > two >> > things. >> > >> > 1. If I say complete 100%, 0 remaining and actual finish date the task >> > duration changes to 6 days (fine as the elapsed is 6 days), but the >> > actual >> > hours change to 36. >> > 2. If I say complete 100%, 0 remaining, 48hours actual and actual >> > finish >> > date the task duration changes to 8 days, actual hours 48 but end date >> > changes back to 8 day elapsed from start. >> > >> > I was hoping to show that the task has finished early but keep the >> > actual >> > hours correct. >> > >> > Any ideas?? >> > >> > Regs >> > >> > -- >> > Andy H >> > JAZ Computer Services >> > www.jazcomputerservices.co.uk >> >> >>