Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Mon, 1 Sep 2008 04:19:00 -0700,    group: microsoft.public.project        back       


Task Links Issues with Integrated Project plans   
Hi All

After i link tasks with multiple project files, when ever i integrate them 
into single project plan - because of ghost tasks i get mis links - meaning - 
the link item i linked previsouly is getting changed (for ex: i have two 
project plans - p1 and p2. when i link row 23 of p1 with row 40 of p2 - after 
a integrated plan refresh i get row 41 of p2. how to avoid it - all i want 
is, once linked the plan should not automatically change task link - is there 
any option to switch off..?? 

Thanks.
date: Mon, 1 Sep 2008 04:19:00 -0700   author:   Muthukumar G.

Re: Task Links Issues with Integrated Project plans   
Hi Muthukumar ,

Welcome to this Microsoft Project newsgroup :)

Links can be somewhat unstable!  The safest way is to create a master file, 
insert the 2 projects via Windows/New Window..., and then apply the links. 
Make sure you have the latest SP installed.

FAQs, companion products and other useful Project information can be seen at 
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


 Muthukumar G. wrote:
> Hi All
>
> After i link tasks with multiple project files, when ever i integrate
> them into single project plan - because of ghost tasks i get mis
> links - meaning - the link item i linked previsouly is getting
> changed (for ex: i have two project plans - p1 and p2. when i link
> row 23 of p1 with row 40 of p2 - after a integrated plan refresh i
> get row 41 of p2. how to avoid it - all i want is, once linked the
> plan should not automatically change task link - is there any option
> to switch off..??
>
> Thanks.
date: Mon, 1 Sep 2008 14:27:23 +0100   author:   Mike Glen glenATmvps.org