Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
date: Fri, 29 Aug 2008 09:05:01 -0700,    group: microsoft.public.project        back       


Unassigned Tasks - hours showing up in custom view   
Hi,

We use the resource pool to create a customized view which is a report by 
project.  For some reason, this report has been showing unassigned tasks with 
"work" hours that are not assigned in each individual project plan.  When the 
master is run and left open when running our view out of the resource pool, 
these unassigned hours go away.  The hours go away also when an individual 
project plan is opened.
My questions...
Where is it getting the hours?
Why is it showing hours that are not in the plan until we open either the 
individual plan or the master?
Why does it show hours that are not in the MSP?

Help!

Tammy
date: Fri, 29 Aug 2008 09:05:01 -0700   author:   Tammy

Re: Unassigned Tasks - hours showing up in custom view   
Hi Tammy,

Can you please give us a bit more information?
What version of Project? 2003? 2007?
What service pack?
Are you using Project server?

I'm not sure I follow -- your comment about "work" hours.  Where 
(what view) do you see the unassigned tasks?  In what file do you 
see the tasks -- in the resource pool file?  In the master?

Please let us know more details and we'll try to help.

Julie

"Tammy"  wrote in message 
news:173FB5C7-58B4-4EB6-ADAC-BE5EA13E708B@microsoft.com...
> Hi,
>
> We use the resource pool to create a customized view which is a 
> report by
> project.  For some reason, this report has been showing unassigned 
> tasks with
> "work" hours that are not assigned in each individual project 
> plan.  When the
> master is run and left open when running our view out of the 
> resource pool,
> these unassigned hours go away.  The hours go away also when an 
> individual
> project plan is opened.
> My questions...
> Where is it getting the hours?
> Why is it showing hours that are not in the plan until we open 
> either the
> individual plan or the master?
> Why does it show hours that are not in the MSP?
>
> Help!
>
> Tammy
date: Fri, 29 Aug 2008 18:09:39 -0400   author:   JulieS