I have used MS Project 2007 to create a construction schedule. The schedule is cost loaded, but will not calculate my Earned Values correctly for Task Items that have lag (Ex: 100% Complete, but only 30% of cost is showing) . These lagged items are incomplete work items that have been re-scheduled to start/continue at the next possible date. I have looked at the resources and they show, for example: XYZ [129%]. I have also checked my dates and percent complete to make sure that everything is correct...and it is. How can I get my earned values to calculate correctly?
On Aug 29, 5:00 pm, Rooster_17 wrote: > I have used MS Project 2007 to create a construction schedule. The schedule > is cost loaded, but will not calculate my Earned Values correctly for Task > Items that have lag (Ex: 100% Complete, but only 30% of cost is showing) . > These lagged items are incomplete work items that have been re-scheduled to > start/continue at the next possible date. I have looked at the resources and > they show, for example: XYZ [129%]. I have also checked my dates and percent > complete to make sure that everything is correct...and it is. How can I get > my earned values to calculate correctly? Hi , Is the new baseline saved to baseline 0 ? EVA will by default look at baseline 0 for info and not on Baseline 1-10. Hope this helps Andre