sRegardless of what report type I select: Cost, Activities, Assignment; Project creates the Project "Overview Report." This issue is limited to a single project. Any recommendations how to correct or transfer all information over to a new project (including resources). TY.
Hello Kurt, To transfer all information to a new project -- create a new project and set the start date of the project equal to the start date of the old project. Choose Insert > Project and uncheck the option, "Link to project". That will insert all tasks and resources as a copy of the original project. Select all tasks except the first and outdent to adjust to the correct outline level. Delete the first task. I hope this helps. Julie "Kurt" wrote: > sRegardless of what report type I select: Cost, Activities, Assignment; > Project creates the Project "Overview Report." This issue is limited to a > single project. Any recommendations how to correct or transfer all > information over to a new project (including resources). > > TY.