Enterprise Custom Task field does not appear in resource timesheet
Sat, 8 Dec 2007 09:57:03 -0800
I have created an enterprise task text field [Tracking No.] and want that to
appear on the resource timesheet as my project has many tasks that have the
same name/description. [Against each change request we assign a tracking no.]
10001 Coding
10001 Testing
10002 Coding
10002 Testing
...
|
Project and multiple milestones on same line / modelling levels
Thu, 6 Dec 2007 13:12:45 -0000
I am looking for a way to place more than one milestone on a single task
line? Background: I have modelled the schedule and have 10% / 50% / 90%
confidence values against each task finish date and would like to show this
information on my gantt chart. I'm using ms project 2003 professional and
have 2003 p ...
|
Microsoft.Project.OLEDB.X.X provider not registered - help please
Wed, 21 Nov 2007 04:09:02 -0800
I am trying to import data from MS Project Pro 2007 using this connection
string:
Provider=Microsoft.Project.OLEDB.12.0;Project Name=C:\Documents and
Settings\Administrator\My Documents\test.mpp;
I have also saved the project as Project 2000 -2003 and tried the above
string with OLEDB.9.0(10.0 & 11.0) wh ...
|
Table &Entry in Enterprise global cannot be overwritten
Fri, 16 Nov 2007 16:16:37 -0400
We have a new project manager, I modified the project owner to be the new
project manager, however, the first time the new project manager tries to
connect to the projectserver (2003, sp2a), the message said
"the enterprise global already contains a filter named "enterprise
resources".
Do you want ...
|
New to the Forum, Need help with Project User Setup
Thu, 15 Nov 2007 23:16:12 +0530
Hello Geniuses,
I'm new to the forums and Project Server 2007 and just wanted to thank
everyone in advance for your help. Let me know if I?m not making myself
clear in any of my statements or if you need any more info. Basically we
are just trying to Restore a Customer's Database into an image of
project server ...
|
Lost Admin Password
Tue, 13 Nov 2007 10:32:23 -0800
Hi.
I have inherited an install of project 2003 (win 2003 server) and no one
seems to know the admin password. How I can I reset it? - complete newbie on
project so be gentle with me.
Lee
...
|
PROJ_INFO_START_DATE issues
Tue, 13 Nov 2007 08:47:37 +0100
Is there any way to update PROJ_INFO_START_DATE from
ProjectWebSvc.ProjectDataSet.ProjectRow class (Project Server 2007, custom
app done in C# using PSI) once the project is already published?
According to
http://msdn2.microsoft.com/en-us/library/websvcproject.projectdataset.projectrow.proj_info_start_date. ...
|
|
|
Project Server 2007 - View Assignments blank for some Resources
Mon, 12 Nov 2007 16:49:02 -0800
We have around 15 resources entered into MS Project Server 2007, and
most have Assignments. In the Resource Center some of the Resources
have a blank "View Assignments" page, even though clicking "View
Availability" on the same page clearly indicates they have open
assignments.
Has anyone else observed this, ...
|
Task creation problems in PWA
12 Nov 2007 14:40:19 -0800
Resources can add new tasks to existing projects for themselves in the
"My Tasks" page on PWA but those tasks don't seem to be added to the
project even after the project manager approves the projects. In
fact, if the project manager syncs the project with Project
Professional 2007, the tasks get deleted.
Wh ...
|
Error while building cubes-connection cannot be made
Mon, 12 Nov 2007 05:47:02 -0800
Hi All,
I get the following error while building the cube.It says Failed to connect
to the Analysis Services server.A connection cannot be made. Ensure that the
server is running.
The queue status shows that the job is 50% complete and the job has failed
but not blocking correlation.
How should i resolv ...
|