Adding to Baseline data
Wed, 23 Jul 2008 06:16:59 -0700 (PDT)
Dear MPP users,
I need one help. I use project 2003.
I have one schedule already baselined. However, at the time of
baselining, I had forgot to update the resources charge rate and it
remained as $0. Now I have begun tracking the schedule, but SPI never
shows up because BCWP is $0. I can go and re-baseline, ...
|
A way to suppress dialog boxes when saving/publishing MS Project 2
Wed, 23 Jul 2008 05:59:18 -0700
Is there a way to suppress dialog dialog boxes when running a macro from VBA
in MS Project 2007?
I'm calling the Application.FileSave() method followed by the
application.PublishAllInformation() method to cycle through some projects and
save/publish them, but when I call the PublishAllInformation() metho ...
|
How to display CommandBar as a popup (context) menu in Ms Project
Wed, 23 Jul 2008 00:26:00 -0700
hi,
i have created the commandbar as Menu using C#. i want to
add CommandBar as a popup (context) menu in Ms Projecct. is it Possible? how?
...
|
Updating Projects with Current Enterprise Resource Information
Tue, 22 Jul 2008 14:40:10 -0700
I have been attempting to programmatically update all projects to display
accurate cost information through PWA (after recently adding a new cost rate
to each resource with a future dated effective date).
The documentation displays this information:
========================================
Enterprise reso ...
|
Read Project Server 2007 Lookup tables values in C# COM Add-in prj
Tue, 22 Jul 2008 13:37:03 -0700
I am using Project Server 2007 and Project professional. I created one
Lookup table Field with Some values. I created a Text Field based on the
Lookup
table. The Text Field will be appear in each task(Task Level Text Custom
Field). If I open the Project Professional I get the lookup table values in
the Te ...
|
Any working samples for Visaul Studio 2008 RTM
Tue, 22 Jul 2008 09:08:04 -0700
Hi,
Are there any samples that have been re-worked for the release version of
Visual Studio 2008? All the samples I have were for Beta 2 and just don't
work.
I've been unable to find any information on the changes from Beta 2 to RTM
to make the samples work.
Thanks in advance
--
Martin ...
|
Export Task Information to Excel
Tue, 22 Jul 2008 04:08:00 -0700
Hi
I am using the code kindly made available by Jack Dahlgren to export certain
data to Excel. I am exporting Milestone information to a spreadsheet however
on some of the milestones it is only exporting the milestone name and not the
following fields I have requested:
Milestone
Work
Actual Work
Duratio ...
|
|
|
Resource assignment report for 2 users
Mon, 21 Jul 2008 07:59:00 -0700
Hi,
I have a requirement of creating 2 reports ie; resource assignment view for
2 users say test1 and test 2. report for test1 should open when clicked on a
link, with a view view1. and that of test2 should open on the click on
another link with view view2.
How can I put the links so that it goes 2 user ...
|
Resource Custom field
Mon, 21 Jul 2008 01:00:00 -0700
Hi all
Iâ??m working on some customization for the project server 2007 , and I have
faced the following problem I have added a custom field to the resources
which is â??Roleâ? , what we need exactly that a resource may have 2 different
roles in 2 different projects ??? each time I save a project the changes ...
|
RE: PSI WSDL File not found error
Sun, 20 Jul 2008 02:52:00 -0700
G'day,
The only things that spring to mind are: -
1) Privilages
2) that the url is wrong.
What url are you using?
"Bryant Likes" wrote:
> I've been doing a lot of work with the PSI and usually everything works
> great when adding a web reference. However, I cannot seem to get a reference
> to Cu ...
|