Unassigned Tasks - hours showing up in custom view
Fri, 29 Aug 2008 09:05:01 -0700
Hi,
We use the resource pool to create a customized view which is a report by
project. For some reason, this report has been showing unassigned tasks with
"work" hours that are not assigned in each individual project plan. When the
master is run and left open when running our view out of the resource pool ...
|
How do I move an entire group of tasks
Fri, 29 Aug 2008 08:01:02 -0700
Hello
I am using Project 2007 to help manage Hospital Construction for a
contractor. What I am trying to do is move the start date of a group of
tasks, either earlier or later, based on changing conditions. If one trade
(i.e. plumbing) needs to adjust their schedule, the timing of the group of
tasks nee ...
|
Earned Values not Calculating With New Baseline
Fri, 29 Aug 2008 08:00:01 -0700
I have used MS Project 2007 to create a construction schedule. The schedule
is cost loaded, but will not calculate my Earned Values correctly for Task
Items that have lag (Ex: 100% Complete, but only 30% of cost is showing) .
These lagged items are incomplete work items that have been re-scheduled to
start ...
|
Project will not open!!
Fri, 29 Aug 2008 06:12:01 -0700
I saved the project yesterday and today when I try to open a box pops up and
says the file contains invalid data or to many rows.
It suggest to validate the data, but it will not open so I can do this. Any
suggestions? ...
|
Is there a way to set a rate per resource PER TASK 8/28
Fri, 29 Aug 2008 05:23:01 -0700
Can you set up separate billing amounts per resource per task in Microsoft
Project?
I would like to designate the rate at which the resource is billed by task.
In other words on one task this resource is billed at $35.00 per hour and on
another task the resource is billed at $50.00 per hour and so on and ...
|
Showing delays
Fri, 29 Aug 2008 02:50:04 -0700
I need to see the delay of a task, meaning that I need MS Project to
calculate how much time elapsed from task finish to a later date. Also, it
would be very useful to add to that delay also the duration corresponding to
outstanding work of that task.
Is there a solution to this? Thanks ...
|
Displaying rolled up milestones in a summary project
Thu, 28 Aug 2008 23:48:00 -0700
all I have a summary project containing a number of sub-projects. Each
sub-project has rolled up milestones displayed. When I open the summary
project the only way I can get the rolled up milestones to display is by
expanding each of the sub-projects first.
Is there a way I can get the rolled up milestones t ...
|
|
|
MS PROJECT : need help with a task
Fri, 29 Aug 2008 06:10:08 +0530
Hi guys i have a gannt chart, i have one task that goes over 2 days (
one task per day) it starts on the 30/11/08, and finishes on the
1/12/08.
i have the first task for 30/11/08 , the date is 30/11/08 on the task
then when i want to put in 1/12/08, it has the start date as the
1/12/08 and finishes on the 2/ ...
|
pmp exam
Thu, 28 Aug 2008 13:41:01 -0700
Hello everyone
What is the best way to prepare for the PMP Exam without having to attend a
very expensive boot camp/workshop. I have the PMBOK and I ahve the the
crossind serries manual and the PMP Prep Exm by Rita Mulchay. I have taken
the exam once but did not make although goingtot he exam, I felt I k ...
|
Re: Server Releases and Compatabile Client Releases
Thu, 28 Aug 2008 18:23:14 +0000
No problem - glad to help!
--
Stephen Sanderlin
Principal Consultant
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server Training: http://www.projectservertraining.com
Read my blog at: http://www.projectserverhelp.com/
Join the community at: ...
|