MS Project 2007 not accepting constraints
Wed, 8 Oct 2008 07:14:30 -0700
Can someone tell me what is going on when I change a constraint type and date
and the date remains the same? I've deleted the task and added back and it
still will not accept the new constraint date. Btw, I'm going from an SNE
date in Oct 08 to a Must Finish On date in Oct 2010.
Thanks. ...
|
Why would the BCWS field be 0.00?
Wed, 8 Oct 2008 06:56:11 -0700
There are resources set so should this field automatically generate the cost
scheduled?
Thanks ...
|
How do I enter Actual Costs?
Wed, 8 Oct 2008 06:33:01 -0700
I thought i could just insert the column and put it in there but it won't let
me. I went to the cost table and tried there and it won't let me do that
either. ...
|
Jack heirarchy macro - adding excel formatting steps
Wed, 8 Oct 2008 06:26:03 -0700
Hi,
I'm developing some extra coding onto the end of Jack's Heirarchy macro with
some formatting steps so that I do not have to format the spreadsheet every
tme i run the macro.
I have come up against a little bit of an annoyance, though, and as I'm no
expert, would like some help in resolving it.
The f ...
|
Can I establish start and finish time for specific task?
Wed, 8 Oct 2008 06:04:01 -0700
Does MS Project 2007 have the capabilities to input a start and finish time
for a specific task in conjunction with the Start and Finish dates?
Example:
Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
Task 2-Form Rebar- Monday Oct1. 14:00hrs to 1 ...
|
Save Baseline in P3
Wed, 8 Oct 2008 01:24:54 -0700 (PDT)
Hi ,
How can I save a baseline in P#? ...
|
Duration in Summary Task
Tue, 7 Oct 2008 23:58:01 -0700
Is there any way to not include lag time in the duration value for summary
tasks?
Here is some more detail:
My projects are IT projects.
A QA(quality assurance) person can test a task after a D(developer)
completes his task. But QA testing occours the day after D finishes work. So,
if D finishes
today ...
|
|
|
Plotting Milestones along single Time Line
Tue, 7 Oct 2008 23:12:04 -0700
I am currently using MSP2003
I would like to be able to plot all the milestones of my project along a
single time line.
This is not the same as the Milestone Rollup View because that view shows
the milestones in separate lines to correspond with the tasks. Is there a
view/report that wwould allow me t ...
|
resource usage per shift
Wed, 8 Oct 2008 08:16:14 +0530
I am using MSP 2003. My schedule includes trades as resources (ex:
welders, mechanics, etc). We are working on a two shift schedule that
goes from 7:30-17:30 and 18:30-4:30. I have defined the work day as:
00:00 - 4:30
7:30 - 17:30
18:30 - 00
My concern is getting the correct resource usage. I have two
...
|
text too small
Tue, 7 Oct 2008 15:27:00 -0700
I created a year-long schedule that I printed on a 3' x 2' arch D-sized
paper. My client likes having the schedule on one page but he can't read the
text as it's too small.
I'm going to enlarge the text in the task information cells, but will the
name that is to the right of the bar on the Gantt chart also ...
|