Start and Finish dates determined by links, dynamic duration
Wed, 8 Oct 2008 23:58:11 -0700
I need to show a "provide on-call support" task for several support teams for
an IT project.
The start of this on-call support for my project is linked to the start
date/time of the first activity on the cut over weekend.
The end is determined by the finish date/time of the last activity on the
cut over week ...
|
How do you change who task updates are sent to? (enterprise edition)
Thu, 9 Oct 2008 07:10:35 +0530
Hi,
We're using the enterprise edition of project. Is there a way to change
who task updates are sent to?
We've changed the owner of the project in the project center, but when
the individuals submit updates, they're sent to the previous owner of
the project (and creator of it) for approval.
Is there some pla ...
|
How do I remove or un-passoword protect an 07Project file?
Wed, 8 Oct 2008 18:31:00 -0700
I have write protected my 2007 Project file and now want to un-protect it.
Doing a SaveAs and deleting the password from the Tools-General Options-Save
Options window doesn't work. I've even tried creating a new file from the
old one but the password protection copies with the file. How do I turn it
off? ...
|
How do you change who task updates are sent to? (enterprise edition)
Thu, 9 Oct 2008 06:02:17 +0530
Hi,
We're using the enterprise edition of project. Is there a way to change
who task updates are sent to?
We've changed the owner of the project in the project center, but when
the individuals submit updates, they're sent to the previous owner of
the project (and creator of it) for approval.
Is there some pla ...
|
Microsoft project Printing Settings
Thu, 9 Oct 2008 02:49:42 +0530
Hey i am new here and do have a decent knowlegde with project and
Primavera although i am having some difficulty printing a total of 17
items that are displayed on a bigger portion of the sheet rather that
1/4 of it. If anyone knows a resolution to this problem that would be
greatly appreciated. Thank You
--
d ...
|
Using Project with multiple users
Wed, 8 Oct 2008 13:59:01 -0700
Hi,
I was recently put in charge of finding project management software to help
our company run more efficiently when a work order is issued. I have looked
primarily at Project to solve this problem, but I have a question. I would
like to be able to connect with other departments here on site. Would I need ...
|
Fully Allocate a Resource
Wed, 8 Oct 2008 12:16:21 -0700
Hi,
I'm working in Project 2003 and I'm having an issue where it won't fully
allocate a resource who is assigned to a task at 100%. This is happening in
several instances where it only assigns someone for say 2 hrs per day
(instead of 8). Again they are 100% on the task and I can't find a valid
reason f ...
|
|
|
Remove "days" from duration field(s)
Wed, 8 Oct 2008 11:43:14 -0700
How do I remove days from the duration fields during export to Excel? I am
trying to calculate my critical path duration PLUS the standard deviation on
the critical path using PERT values. ...
|
Re: How do I get a Text field to show up in the Resource Usage dis
Wed, 8 Oct 2008 09:34:00 -0700
I am tagging onto this since I am having trouble being able to start a new
questions
Is it possible to write a macro that uses the TASK.NAME Field instead of
from Task.text to Assignment.text? Also, how can you see the assignment
fields?
I want the Name field to = Task.Text9 (Task.Text9 holds formula t ...
|
Finsh No Later Than Constraints
Wed, 8 Oct 2008 07:43:05 -0700
I have to finish a project on a certain date but I schedule the project from
a start date as I want all tasks to start As Soon As Possible. I use a Finsh
No Later Than constraint on a milestone task at the end of the project to
forewarn me (when I update my project plan with actual information) if the
proje ...
|