Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
group : microsoft.public.project      view archive
page nr.   1      2      3      4      5      6      7      8      9      10      11      12      13      14      15      16      17      18      19      20    next >>



Project Professional 2007 installed on a Win2008 Terminal Server x64 and x32     Wed, 27 Aug 2008 18:49:56 -0700 (PDT)
Hi all, I tried to install MS Project Professional 2007 on both x64 and x32 version Windows 2008 Terminal Servers. After I install and open it, the system pop up a message that the Project Professional 2007 cannot be installed on a terminal server:( I tried to install Project 2007 SP1 on the x32 server, i ...

Formula check and indicator anomaly     Wed, 27 Aug 2008 15:37:48 -0700 (PDT)
This is Project Pro 2007 with SP1 and several hotfixes (with Project Server), but NOT the infrastructure update yet. The field is an enterprise task field, but my validation is ALL in Project Pro. It doesn't work as expected in the Project Pro client. I have a formula that returns useful information: slipp ...

RE: updating actual work does not always expand hours     Wed, 27 Aug 2008 14:24:00 -0700
Hey peter I just started using this site I can't seem to find where I ask a question -- guido "Peter" wrote: > A task has 40 hours spread over 2 weeks to complete - 20 hours per week. > Task attributes are fixed work with no constraints or links > In the Resource Usage (or Task Usage) views I a ...

Top Down or Bottom Up?     Wed, 27 Aug 2008 09:43:55 -0700
I would think that entering the project top down would work out better most of the time for most projects. Right? Should I start with the major milestones, then the highest level tasks, then work my way down? ...

overtime     Wed, 27 Aug 2008 09:08:01 -0700
What are some of the best strategies for determining whether to have employees on a project work OT or not? Also, where in Project (views/tables) should I look to see what effect adding OT on a particular task would have on (1) the duration and the (2) cost? I've been viewing the Gantt Chart and splitti ...

MS Project -importing from excel-predecessors are not populated     Wed, 27 Aug 2008 07:06:00 -0700
I am exporting project data from an excel spreadsheet, how do I get the predecessors to populate and match ...

Labor Escalation     Wed, 27 Aug 2008 06:41:01 -0700
How can I escalate labor rates over time? ...

Dates withink project don't agree with Actual calender days     Wed, 27 Aug 2008 06:28:01 -0700
since moving onto MPP 2003 I have been experience problems with task start and end dates. for expample I create a task which starts on 29/09 (as a start as soon as possible/no Lag days) is is a 30 day task , MPP calculates it finish as 04/11. I caluclate it finsh as being 07/11. I have checked all my resou ...

Hiding cost data     Wed, 27 Aug 2008 06:26:02 -0700
Is there a way to hide resource cost data? My management wants the ability to look at the data, but they don't necessarily want others to have access to the data. For example: Jim's billable cost is 10.00/hour, on a Project Schedule, his total cost for the task he's assigned to is 100.00 Bill is Jim's ...

How does one forecast completion date based on current progress?     Wed, 27 Aug 2008 05:01:01 -0700
Is there a way that MS Project can forecast a new completion(finish) date, based on the % complete progress update? In other words if the % complete makes the project with a "LATE" status, the forecast completion(finish) date will move out, and vice versa. If so, please explain the process to me. ...


page nr.: page nr.   1      2      3      4      5      6      7      8      9      10      11      12      13      14      15      16      17      18      19      20    next >>
Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us