Tas Numbers Out of Sequence (Part 2)
Fri, 5 Sep 2008 10:54:01 -0700
What Jan suggested I do worked great however it was not actually what I was
trying to accomplish after all. It did reorder the tasks by their ID number
but what I guess I wanted to do was, becasue the tasks themselves are already
in the proper order, was to reassign new task ID #s based on the order that
ta ...
|
Work subcategories / timesheet
Fri, 5 Sep 2008 08:53:01 -0700
I am using Project Professional 2007 and I have a two-part question. I am
trying to track a higher granularity of work in Project. Rather than just
tracking work, IĆ¢??d like to break it into 3 categories (normal, rework, and
scope change) but still have that roll up into a cumulative work field. What
are my ...
|
Task Numbers are out of sequence
Fri, 5 Sep 2008 08:21:03 -0700
I have received a very large project schedule from a subcontractor to import.
A number of task line item numbers are out of order (in other words Line Item
1661 follows Line Item 2671). Is there a way to sort these? ...
|
Task bar is not displaying in Gantt Chart
Fri, 5 Sep 2008 06:46:10 -0700
Hi there,
I have copied another person's MS Project Plan (version 2003) and then
modified it with additional tasks for a similar project I am managing.
Inexplicably some of the tasks are not displaying in the Gantt Chart.
I have compared the tasks not displaying with tasks that are displaying by
going to ...
|
Recording the Actuals - Help Needed
Fri, 5 Sep 2008 05:53:03 -0700
Hi there,
Fairly new to Project 2007 - but not to project management. I wonder if
someone can shed some light on the following.
I have a task on a plan with resource ASH 75% loading. The task was due to
take 6 days and was sheduled as 75% thus the elapsed as 8 days. ASH put extra
hours in and finished th ...
|
weekend and duration dates conflict
Fri, 5 Sep 2008 05:44:00 -0700
I am in Sales and I create a "preliminary" Microsoft schedule for my
proposal. This schedule is intended to start / end dates and task duration
along with required predecessor/successor links.
Our company just recently converted to Microsoft Project 2007.
For installation of the work, I need to show weeken ...
|
Microsoft Project 2007 Calendars??????
Fri, 5 Sep 2008 04:18:01 -0700
I've entered a 1 day duration into project, but the length of the actual
activity shown on the calender goes over 1 day, i haven't changed anything as
i'm using the standard project calender, so how has this happened, can anyone
please help? ...
|
|
|
How to hide task which is deleted
Fri, 5 Sep 2008 13:54:18 +0700
Dear Everyone,
I use MSP 2003. When I click tab Task, all deleted task not hide.
How to hide deleted task?
Thanks
...
|
Enterprise Project 2007 - consultant/trainer needed - Melbourne
Thu, 4 Sep 2008 22:07:00 -0700
I may need an expert in Microsoft Entreprise Project 2007 to supply
training/consulting, in Melbourne.
If you know of anyone with suitably advanced knowledge of Enterprise Project
2007, I would welcome contact details in repsponse to this message.
...
|
Cell color in MS Project 2003
Thu, 4 Sep 2008 20:36:20 -0700 (PDT)
Hi,
I am working with MS Project 2003 and I would like to know if we are
able to color a cell background when task meets some condition. Ex: if
my task is completed and Finish date happened more than 10 days ago
then color a task row to red...
Thanks in advance..
...
|