Task Usage View
Thu, 6 Nov 2008 18:05:01 -0800
I'm trying to create a task usage view that would allow me to filter on
specific resources so that they can easily see what they have upcoming over
the next few weeks. I was able to create a filter that shows the tasks
assigned to the selected resource(s) along with the assignment info for the
resource(s). ...
|
Warning Notes of Deadlines
Thu, 6 Nov 2008 15:00:01 -0800
Hello,
Is there any method in MSP 2003 to warn us of imminent deadlines for tasks
just before the deadline ? Something similar to checking the % task remaining
(hours or %).
Thanks,
Dip ...
|
Resource Planning across multiple projects
Thu, 6 Nov 2008 14:02:02 -0800
hello,
i inserted multiple projects into a new MPP doc and was hoping to generate
some kind of report that would enable me to view the usage for single
resources that are allocated for more than one project. i'm having trouble
figuring this out. can anyone help me with this?
thanks ...
|
Average Days by Task
Thu, 6 Nov 2008 12:46:01 -0800
Hello,
Please don't think me silly. I am a new user to Project Professional 2007
and I love it thus far. I am seeking a solution or some direction on how to
go about my request below.
I have 50 Summary Tasks with 20 SubTasks that I track. I am looking to
obtain an average number of days it takes to start ...
|
Not All Rolled Up Milestones Appearing on Summary Bar
Thu, 6 Nov 2008 10:42:07 -0800
I have several milestones showing rolled up on my summary bars. I have
recently added two new milestones but they are not showing on the summary
bars. I have already checked the "roll up to summary bar" box. What else do
I need to do? ...
|
Convert Master Schedule into a Single File
Thu, 6 Nov 2008 10:24:15 -0800
Every so often, a customer will ask to have the schedule delivered as a
stand-alone schedule instead of a master and subproject files. I think at one
time, you could just send the consolidated schedule, fully expanded and all
the data was there for viewing. Now when you send the consolidated schedule,
subpro ...
|
Report - Visual Reports and EVM
Thu, 6 Nov 2008 18:46:12 +0100
Hello,
How can we create the S Curves graph with BCWS, BCWP and ACWP ? I don't find
these values in any "template" of these Blind Reports!
Thanks for your help!
...
|
|
|
Disappearing Tasks
Thu, 6 Nov 2008 09:28:24 -0800
I use MS Project 2003 and save as MS Project 98 so other co-workers can view
the file. When I re-open files, many of my tasks have disappeared. Other data
for the tasks still appear, such as Durations, Start, Finish, Resources, but
the Task Name has disappeared. ...
|
OutLook and Project add-in options
Thu, 6 Nov 2008 08:45:02 -0800
After installing the Project Add-on to Outlook there is of course the two
option to interact with Project server these are
â??Update Project WEB accessâ? and â??Import New Assignmentsâ?
Iâ??m going to explain this the way my Brain see things
Are these the differences if not or Iâ??m confused please correc ...
|
% work Complete, % Complete
Thu, 6 Nov 2008 08:33:01 -0800
How do you prevent an update in one of the columns (% work complete) from
updating the other (% Complete) with the same vaule and vice versa. I want
differnet statuses reflected in each column and I cannot get to stop
reflecting the same?? ...
|