Ureader.com  
Microsoft software help and Community
   home   |   control panel login   |   archive   |  
 
other
informationbridge
office.intranets
office.misc
office.setup
office.xml
officeupdate
onenote
photodraw.discussion
powerpoint
producer
proj.standard&server
project
project.developer
project.pro_and_serve
project.server
project.vba
project2000
publisher
publisher.prepress
publisher.programming
publisher.webdesign
visio
visio.createshapes
visio.database.modeling
visio.dev.diagrams
visio.dev.shapesheet
visio.dev.vba
visio.dev.vc
visio.developer
visio.general
visio.installation
visio.printing
visio.software.modeling
visio.troubleshoot
  
 
group : microsoft.public.project      view archive
page nr.   1      2      3      4      5      6      7      8      9      10      11      12      13      14      15      16      17      18      19      20    next >>



Help with a formula - colour coding late finishes     Thu, 2 Oct 2008 11:16:01 -0700
I'm trying to add a formula that provides a colour code eg. red, yellow, green visual representation if the finish date has past and a task is not complete. Can someone help? Ideally: Late > 7 days = Red Late > 1 day = Yellow On Track = Green And for any tasks that have not yet start (based on start d ...

peak units     Thu, 2 Oct 2008 19:48:06 +0200
Hello all, Can anybody please explain to me how peak units in resource usage get calculated? The idea is to use resource usage view for planning and monitoring hours resources have spent already (actual work) and are likely to spend (work) in the future and compare it with the original planning (baseline ...

Gantt chart dates are different than task dates     Thu, 2 Oct 2008 08:50:03 -0700
I've created a project w/ MS Project 2007. The project starts in September 2008 and runs until January 2009. When I look at the Gantt chart, the timeline is September 2009 to January 2010. The 'start date' in PROJECT INFORMATION is 2008, and I've been unable to figure out why the Gantt is one year ahead. ...

Weight Average Summary Task of Custom field     Thu, 2 Oct 2008 08:16:01 -0700
Hi. I"m trying to have my custom field to roll up but to summary as a weighted average by the Effort (Work). The same thing % work complete would roll up. Unfortunately the only method is MS project has is simple average. this is distorting my comparaison with the % work complete. Any help is apprecia ...

Linking Columns     Thu, 2 Oct 2008 07:30:12 -0700
Hallo there, I want to link too Columns. Let me explain. I have a Cost table with the amounts showing. Now I want to add a KM Cost table that has a fix amount in currency and not per km/mph. When I type $ 2000 in the KM Cost Table it must Automatically update the Cost Total. ...

How to print time range on Gantt chart     Thu, 2 Oct 2008 17:35:50 +0530
I am running MSP 2003 SP3. I want to print the time range of each task on the Gantt chart. It is a 5 day project with 1000 tasks, so it would be helpful to include both the start time and end time above the bar. I don't want the date as this would be too crowded. I have seen this before on a print out, but I ...

Assigning alternative resource while primary resource is on leave - anyone know how?     Thu, 2 Oct 2008 15:57:37 +0530
Just a quick example: Task 'Build Walls' is due to run from 6th October for 15 days and Bob is assigned to do the work. However, Bob is on leave from 13th October for 5 days. I'd like Joe to build the walls while Bob is away enjoying himself, and for Bob to pick the work back up and complete the job when he retu ...

Assigning alternative resource while primary resource is on leave     Thu, 2 Oct 2008 03:55:00 -0700
Just a quick example: Task 'Build Walls' is due to run from 6th October for 15 days and Bob is assigned to do the work. However, Bob is on leave from 13th October for 5 days. I'd like Joe to build the walls while Bob is away enjoying himself, and for Bob to pick the work back up and complete the job when he ...

WSS Workspace Create generates "GeneralQueueJobFailed" error messa     Thu, 2 Oct 2008 01:57:01 -0700
Hello Team, (MS Project 2007 + i have several queued job error messages generated when project managers are publishing a project, the workspace is generated by with wrong permissions, as by default inheritance. The resoult is that the project manager is not able to access the workspace and doc library, Ac ...

Freezing Tasks     Thu, 2 Oct 2008 01:21:01 -0700
Is there anyway you can freeze a task in Project? Some of the work has been carried out but there is no definate date of when or if the remaining work will resume? Many thanks ...


page nr.: page nr.   1      2      3      4      5      6      7      8      9      10      11      12      13      14      15      16      17      18      19      20    next >>
Google
 
Web ureader.com


    COPYRIGHT 2007, YARDI TECHNOLOGY LIMITED, ALL RIGHT RESERVE  |   contact us